What makes a resort plan different
In Florida law, a resort is an RV park. The statute makes "RV resort", "camping resort" and "travel resort" synonymous with "recreational vehicle park" (F.S. 513.01(11)), so a resort carries the full state permit burden and is exempt from Chapter 509 hotel regulation (513.012) [6]. The difference is the program and the way it is planned. A park is drawn as one site plan. A resort is drawn as a master plan: the full build-out of roads, utility backbone, amenity core and unit sections, with phase lines, and each phase is then drawn as its own site plan inside it. The site-level standards (pad sizes, separations, road widths, the NEC 551 receptacle mix and state density caps) are tabulated on the RV park site plan page, and the state rules on RV park regulations by state; this page covers what changes at resort scale.
The model resort program used here is 150 to 250 sites with a clubhouse, pool, pickleball, a dog park and an optional cabin or park model section, on an unincorporated Hill Country tract and, for contrast, in a Tennessee resort city.
At this scale the density cap rarely binds. Florida's 25 units per gross acre would allow up to 500 RV units on 20 gross acres [7]. Bandera County, Texas has no county zoning, and its rules apply to the unincorporated area only [3]. There, wastewater and water resize the site plan before density does: at Burnet County's adopted design flow of 100 gallons per space per day, 150 to 250 sites produce 15,000 to 25,000 gpd, three to five times TCEQ's 5,000 gpd line, and the water system is a TCEQ public water system at 15 connections [1, 2]. Site count is then set by road geometry, drainage, the wastewater system's footprint, well yield and the floodplain.
The resort program and the rules each part triggers
| Program element | What the master plan fixes | Rule that reaches it |
|---|---|---|
| RV sites | Pad mix, pull-through share, 50 A share, phase by phase | NEC 551.71 (2023 text) floor of 40 percent 50 A for new sites [8] |
| Cabins and park models | A separate pod, its own sewer and its own approval track | Texas SB 1 requires roof-access ladders in campground cabins in the floodplain [5]; a manufactured home section in Bandera County falls under the rental community infrastructure plan, whose originals carry surveyor and engineer seals [3] |
| Clubhouse, pool, bathhouses | Footprints, parking, accessible routes | Building permits; Pigeon Forge defines "Architecture" including entertainment-themed styles (307.7, Ord. 1063), so elevations are customary at PUD review [4] |
| Recreation area | Open space and amenity lawn | Holtville, California requires 2,000 sq ft of recreation area in an RV park (Chapter 17.50) [9] |
| Entrance | Gate, office, stacking, sign | Bandera County requires a permanent sign at the subdivision entrance (Regs. 3.6.17) [3] |
| Lighting | Pole and fixture plan | Pigeon Forge 320(b): a photometric plan "signed and sealed", with foot-candles every 5 to 10 ft [4] |
| Perimeter | Buffers and screening | Pigeon Forge Section 306: a plant screen at least 6 ft tall [4] |
| Water and wastewater core | Well field, storage, treatment plant or drain field, reserved for full build-out | TCEQ public water system and wastewater permit triggers [2, 10] |
Cabins and park models
The unit section is where classification decides the approval track:
- Park model RVs. ANSI A119.5, as quoted in North Carolina guidance, caps a park model at 400 sq ft in setup mode, and North Carolina's August 2024 guidance sizes park model wastewater at 150 gpd per unit [11]. Florida allows one park model on an RV space [7]. In Mohave County, Arizona, an independent park model counts as an RV in an RV park, while a dependent park model may be a permanent residence [12]. The Town of Parker, Arizona bans park models [13].
- Cabins. Tennessee's organized camp definition includes permanent or semipermanent sleeping structures, so resort cabins in Sevier County sit inside the state camp permit [14]. In Michigan a unit over 400 sq ft, permanently attached or with interior water is a "resort cabin" that cannot go on a licensed campsite [15]. In Texas, SB 1, signed September 5, 2025, requires campground operators to develop an emergency evacuation plan, with a copy to local authorities, and to install roof-access ladders in floodplain cabins [5].
- Manufactured homes in Bandera County. Appendix A of the county rules covers land rented "for the installation of manufactured homes for use and occupancy as residences" [3]. Its infrastructure plan carries a review fee of $250 plus $10 per rental space, requires finished floors at least 1 ft above base flood elevation, and, where on-site sewage serves the spaces, gives each one at least 50 ft of road frontage [3].
Drawing the units as their own pod lets that section be sized, permitted or dropped without reworking the RV loops.
The premium pad mix
The plan counts pads by type. Site dimensions run from 30 x 50 ft back-in to 45 x 70 ft pull-through in a 2026 construction guide (secondary) [16]. Where a code sets the space, it sets the floor: the Town of Parker, Arizona requires 1,250 sq ft and a 30 ft width, and Holtville, California 1,250 sq ft spaces [13, 9]. On the electrical side the NEC (2023 text) sets a floor, not a target: at least 40 percent of new sites need a 50 A receptacle, and the Informational Note warns that seasonal parks could approach 100 percent 50 A [8]. Under 551.73 a 20/30 A site carries a 3,600 VA demand load and a 20 A-only site 2,400 VA [17]; the 50 A per-site load is taken from the NEC edition the state has adopted. The 50 A share drawn on the master plan therefore sets the load the engineer of record sizes the transformers to.

Master plan logic: what moves the count
1. The road standard. Bandera County's public road standard is a 60 ft right-of-way with 22 ft of local pavement and 4 ft shoulders, a dead-end turnaround of 150 ft right-of-way diameter with 100 ft paved, a 12% maximum grade on local roads and an 8 in. compacted base in two courses [3]. Where a road is built without curbs, the flexible base must be at least 8 in. thick after compaction and at least 30 feet wide (Regs. 6.9), and utility dedications run at least 20 ft wide (Regs. 3.6.13) [3]. Whether the county applies that standard to private internal resort lanes decides how much land the roads take. On an illustrative 200-site plan with roughly 8,000 linear feet of lanes, a 60 ft corridor consumes about 11 acres; a 24 ft private lane consumes about 4.4 acres [3]. The question is settled in writing at the sketch stage, before the loops are drawn. Bandera's subdivision rules refuse "unconventional layouts" that cause unsatisfactory drainage or complicate street maintenance, and its rental community appendix bars flag lots or other contrivances that restrict emergency access in all types of weather [3].
2. Water. A system serving at least 15 connections or 25 people at least 60 days a year is a public water system, so any resort of this size needs TCEQ plan approval, well capacity and storage [10, 3]. Bandera County is a priority groundwater management area: the plat carries a groundwater availability certification sealed by a PE or P.G., backed by a 24 hour minimum aquifer test and drawdown projections at 10 and 30 years [3]. Well yield can cap the site count. Under LGC 232.109 a county may also require fire water storage: 2,500 gal under 50 units, and for 50 or more units 2,500 gal with centralized water or 5,000 gal [18].
3. Wastewater. Burnet County found that RVs "are being used as full time residences therefore a flow rate of 100 gallons per day per space will be required" [1]. At that rate a 150 to 250 site resort produces 15,000 to 25,000 gpd [1]. TCEQ's on-site ceiling is 5,000 gpd: "If your OSSF treats more than 5,000 gallons of wastewater on-site each day, then you may need a domestic wastewater permit" [2], and the on-site sewage rules define an RV park as a tract with "a combined wastewater flow of less than 5,000 gallons per day" [19]. A discharge permit can turn contested: The Village at Grape Creek, a tiny home village in Fredericksburg, sought a TPDES permit to discharge "up to 20,000 gallons per day... into the Pedernales River" and was referred to a contested case hearing (SOAH Docket 582-25-15494) [20]. The treatment plant or land application area is drawn into the master plan from the first phase.
4. Floodplain and egress. Kerr County requires a floodplain determination or permit for any work in the floodplain, and much of its floodplain is "Zone A", without detailed study [21]. The Houston Chronicle reported (secondary) that of the 136 people confirmed killed in the July 4, 2025 flood, at least 44 died in RV parks or campgrounds [22]. At Old River Road RV Resort in Kerr County, an advocacy site (secondary) records opponents citing flood exposure at the "confluence of the Guadalupe River, Turtle Creek and Nowlin's Hollow" and a single exit "only wide enough for one RV at a time" [23]. Kerr suspended statutory plat deadlines on July 22, 2026 under LGC 418.016(e) [21]. In Bandera's rental community rules, finished floors sit at least 1 ft above base flood elevation and the drainage plan may not increase the 100-year peak flow [3]. The master plan keeps sites and cabins out of mapped and estimated flood areas and shows a second way out; evacuation and single-exit questions come up at riverside hearings.
5. The Edwards Aquifer. TCEQ's RG-499 says the Edwards Aquifer Protection Plan rules affect "construction sites in Medina, Bexar, Comal, Kinney, Uvalde, Hays, Travis, and Williamson counties" [10]. Over the Recharge, Contributing or Transition Zone, TCEQ says "more stormwater requirements may apply", so the parcel is checked against TCEQ's Edwards Aquifer Map Viewer before the layout is fixed [2].
Phasing the master plan
The master plan is approved whole and built in pieces, and the rules decide where the phase lines fall:
- Texas. Bandera County allows phased plats: a preliminary plan may show phased development, with each phase approved in its own final plat and the date of each phase's final plat application stated [3]. The preliminary plan, preliminary plat and final plat are considered at separate Commissioners Court meetings, each submitted at least 30 days ahead; a preliminary plan expires in 12 months; and construction must start within 90 days and finish within 12 months of final plat approval [3]. Because the full build-out crosses the 5,000 gpd on-site ceiling, the treatment site is reserved from the start [2].
- Florida. Added spaces are a modification that needs Department of Health review (64E-15.001(6)), and the permittee must notify the department in writing at least 30 days before each one [7]. Separation distances are fixed at initial approval (F.S. 513.1115), so the full geometry belongs on the first approved plan [6]. A water management district conceptual approval lasts 20 years if the first phase starts [24]. The Polk County model shows this sequence under the county's rewritten Section 303 [25].
- Arizona. In Mohave County, the first final plat or site plan is due within 2 years of PAD approval [26].
- Market pacing. Two development guides (secondary, not Texas-specific) put zoning and permits at 3 to 9 months, site work at 4 to 8 months and stabilization at 18 to 36 months, and one suggests opening "25-30 sites first" [27, 16].
Two model jurisdictions
| Item | Bandera County, Texas (Hill Country) | Pigeon Forge, Sevier County, Tennessee |
|---|---|---|
| Land use control | Unzoned county; rules apply to unincorporated areas only (Regs. 1.3.4) [3] | A travel trailer park is "any plot of land approved as a planned unit development" (340.1), under Section 407 [4] |
| Approval steps | Sketch plan, preliminary plan, preliminary plat, final plat, at separate court meetings; rental community infrastructure plan for a manufactured home section; TCEQ water and wastewater, floodplain and driveway permits [3] | Rezoning where the district requires it (Article XII, 1201 to 1203), preliminary and final PUD plans, site and lighting plans, floodplain, the state organized camp permit, building permits [4, 14] |
| Plan preparation | Sketch plan "not required to be drawn with precision"; preliminary plan by a registered surveyor or engineer [3] | PUD plans on the 2019 Planning Commission agenda were prepared by engineering firms [28] |
| Seals | PE seal on road and drainage plans before preliminary plat; PE or P.G. on the groundwater certification [3] | Photometric plan "signed and sealed" (320(b)) [4] |
| Published county fees | $250 plus $10 per rental space for an infrastructure plan; plat recording $100 plus $3 per lot over 33 [3] | Not stated |
| Clocks | Submit at least 30 days before court; LGC 232.0025 gives 10 business days for an incompleteness notice and 30 days to decide [3, 18] | Not stated |
| Layout numbers | 60 ft right-of-way, 22 ft local road, 12% maximum grade, finished floors 1 ft above base flood elevation [3] | Plant screen at least 6 ft tall (306); units 15 ft or more apart under the state camp rule (July 2002 text) [4, 29] |
| Recorded resort items | Not stated | Smoky Mountain RV Park & Resort Phase 1 revised final PUD on the October 22, 2019 agenda [28] |
In Texas, LGC 232.00285 bars a county from requiring a development plan, a term that includes a preliminary plat and a site plan, unless other law explicitly authorizes it [18]. Bandera's optional sketch plan is the one stage free of content and preparer requirements, which is where the preliminary layout goes first [3]. The county-by-county detail is in RV park approval in Texas counties, on RV park site plans in Texas and on the Texas state page. For Tennessee, see RV park site plans in Tennessee and the Tennessee state page.
What the engineer of record adds at resort scale
The preliminary master plan carries the layout, the phasing, the program areas, a schematic of utilities and the site data tables. Using Bandera County's submittal stages as the template:
| Stage | On the preliminary plan | Added by the engineer or surveyor of record |
|---|---|---|
| Sketch plan | Full layout, site counts, amenities, yield table | None required |
| Preliminary plan | Layout, phasing, data tables | Boundary survey; a registered surveyor or engineer as preparer |
| Preliminary plat | Program areas, schematic utilities, flood avoidance concept | Survey, 5 ft contours, FIRM panel and date, sealed road and drainage plans, groundwater test |
| Infrastructure plan for a manufactured home section | Space layout and space-area table, drawn at 1 in = 200 ft on 24 by 36 in sheets | Sealed survey, PE drainage design and certification |
| Final plat | None | All survey content, with fiscal surety |
Source for the stages: [3]. Outside the plat, the engineer of record designs the public water system and the wastewater plant for the TCEQ permits, and sizes the electrical feeders and transformers to the pad mix the plan fixes.
Cost and supply benchmarks
Published per-site costs are secondary and national, not Texas or Tennessee specific. One industry source gives $15,000 to $50,000+ per site and "$5 million or more for 100-site resort-quality properties" [30]. A development guide (secondary) gives $15,000 to $35,000 per site in total [27]. On supply, trade reporting (secondary) counts 31 new parks with 4,146 RV sites and 36 expansions with 1,570 in the 2024 to early 2026 pipeline [31]. The studio's own cost notes are in RV park development cost per pad.
Visuals for the court and the neighbors
Bandera County's rules govern roads, drainage, water and wastewater, and require no renderings, elevations or landscape plan [3]. Visuals there serve commissioners courts, neighbors and lenders rather than a checklist, and a variance may only be granted by the Commissioners' Court acting on a formal agenda item [3]. The objections recorded at Old River Road were flooding and a single exit (advocacy site, secondary) [23], and an exhibit that draws the flood limits and both exits on the plan answers them directly. In Pigeon Forge, where "Architecture" is a defined term, building elevations and the sealed photometric plan are part of PUD review [4]. The view set for a resort, from the aerial master plan to night lighting, is on RV park and resort rendering.
Model projects and related plans
- RV resort, Bandera County, Texas: the Hill Country model, on Bandera's rule text.
- RV resort with cabins, Sevier County, Tennessee: the PUD path in Pigeon Forge.
- RV park, Polk County, Florida, snowbird RV park, Mohave County, Arizona and campground with cabins, Chaffee County, Colorado.
State RV pages: Florida RV parks, Arizona RV parks and North Carolina RV parks, with the state context on the Florida, Arizona and North Carolina pages.
Related plans: RV park site plans, RV sites per acre, glamping site plans for tent and cabin units, campground site plans and RV and boat storage site plans. For the planning argument in long form, see the notes on master planning for RV resorts, RV park versus RV resort, RV resort entitlement and RV park design standards. The plan itself is described on preliminary site plans.
Frequently asked questions
What is the difference between an RV park and an RV resort?
In Florida law there is none: F.S. 513.01(11) makes "RV resort", "camping resort" and "travel resort" synonymous with "recreational vehicle park", so a resort carries the full Department of Health permit burden [6]. The difference is the program: an amenity core, a premium pad mix, cabins or park models, and a phased master plan.
Will a septic system work for a 200-site RV resort?
Can cabins and park models share an RV resort site plan?
Yes, with care. Florida allows one park model on an RV space [7]. Michigan treats a unit over 400 sq ft, permanently attached or with interior water as a resort cabin that cannot sit on a licensed campsite [15]. The Town of Parker, Arizona bans park models [13]. In Texas, SB 1 requires roof-access ladders in campground cabins in the floodplain [5].
What does Bandera County charge for a resort's plats and infrastructure plan?
The rental community infrastructure plan review fee is $250 plus $10 per rental space, and plat recording is $100 plus $3 per lot over 33 [3].
When must construction start after a Bandera County final plat?
Construction must start within 90 days and be completed within 12 months of final plat approval [3].
Can an RV resort be phased in Bandera County?
Yes. A preliminary plan may show phased development, with each phase approved in its own final plat, and it must state the date by which each phase's final plat application will be submitted [3].
Sources
- 1)Burnet County order for on-site sewage facilities, Burnet County, Texas. Accessed 2026-10-09.
- 2)RV Parks: Compliance Resources, Texas Commission on Environmental Quality. Accessed 2026-10-09.
- 3)Bandera County Subdivision and Land Development Regulations (revised through August 25, 2022), Bandera County, Texas. Accessed 2026-10-09.
- 4)Pigeon Forge Zoning Ordinance (updated through July 2023), City of Pigeon Forge, Tennessee. Accessed 2026-10-09.
- 5)SB 1, 89th Legislature, 2nd Called Session: enrolled bill text (Health and Safety Code Chapter 762, Campground Safety), Texas Legislature Online. Accessed 2026-10-10.
- 6)Chapter 513, Florida Statutes, Mobile Home and Recreational Vehicle Parks (2025), Florida Legislature. Accessed 2026-10-09.
- 7)Chapter 64E-15, F.A.C., Mobile Home, Lodging, and Recreational Vehicle Parks and Recreational Camps (2018 version), Florida Department of Health. Accessed 2026-10-09.
- 8)NEC 551.71(A)(B)(C)(F), Receptacle Requirements at RV Parks (2023 NEC), Leviton Captain Code. Accessed 2026-10-09.
- 9)Municipal Code Chapter 17.50, RV Parks, City of Holtville, California (Code Publishing). Accessed 2026-10-10.
- 10)RG-499, RV parks compliance guide (revised February 2024), Texas Commission on Environmental Quality. Accessed 2026-10-09.
- 11)RV park wastewater guidance, On-Site Water Protection Branch (August 21, 2024), North Carolina Department of Health and Human Services. Accessed 2026-10-09.
- 12)Section 37.K, Establishment of Recreational Vehicles and Park Model Units, Mohave County, Arizona (elaws). Accessed 2026-10-09.
- 13)Town Code 10-11-16, Recreational Vehicle Parks, Town of Parker, Arizona (American Legal Publishing). Accessed 2026-10-09.
- 14)Environmental Health, Tennessee Department of Health. Accessed 2026-10-09.
- 15)Cabins and Park Models in Michigan Campgrounds, Michigan Department of Environment, Great Lakes, and Energy. Accessed 2026-10-09.
- 16)RV Park Construction and Development Guide for 2026, propertybuild.com. Accessed 2026-10-09.
- 17)NEC 551.73, calculated load for RV park feeders (training summary of the 2017 and later editions), JADE Learning.
- 18)County Subdivision Handbook (January 2026), Texas Association of Counties. Accessed 2026-10-09.
- 19)On-Site Sewage Facility rules compilation (RG-472, revised March 2013), Burnet County, Texas (TCEQ rule compilation). Accessed 2026-10-10.
- 20)TCEQ docket 2024-1985-MWD, The Village at Grape Creek, LLC, TPDES Permit WQ0016363001: responses and Notice of Hearing, Texas Commission on Environmental Quality.
- 21)Kerr County Engineer, Kerr County, Texas. Accessed 2026-10-09.
- 22)Texas wants to tighten RV park safety rules after Kerr County flood deaths, Houston Chronicle. Accessed 2026-10-10.
- 23)RV Park Safety, Kerr County Conscience (local advocacy site). Accessed 2026-10-09.
- 24)SWERP Training Overview, Applicant Handbook II and SWFWMD Specific Changes, Southwest Florida Water Management District. Accessed 2026-10-09.
- 25)Polk County Land Development Code, 2024 ordinances (Ord. 2024-032), Polk County, Florida (Municode). Accessed 2026-10-09.
- 26)Mohave County Zoning Ordinance (revised through August 3, 2026), Mohave County, Arizona. Accessed 2026-10-09.
- 27)How to Start an RV Park from Scratch: Complete Development Guide, rvpark.world. Accessed 2026-10-09.
- 28)Pigeon Forge Regional Planning Commission agenda, October 22, 2019, City of Pigeon Forge, Tennessee (no longer online; accessed 2026-10-09).
- 29)Rule 1200-01-05, Organized Camps (July 2002 revision), Tennessee Department of Health. Accessed 2026-10-09.
- 30)RV Park Cost 2025: Key Insights for Success, RoverPass (no longer online; accessed 2026-10-09).
- 31)Campground and RV Park Development: 2025 Investment Outlook, North Star Business Advisors. Accessed 2026-10-09.