What changes a site plan in Iowa
Five conditions specific to Iowa change how a site plan is drawn or approved here, before any city checklist comes into play.
1. Regulation is elective at both ends. County zoning applies only where the board of supervisors opts in (Iowa Code 335.1) [5]. The State Building Code applies in four situations only: buildings owned by the state, jurisdictions that adopt the code by ordinance, buildings paid for in part with state-appropriated money, and cities over 15,000 population that have not adopted a substantially equivalent local code (103A.10(2)) [6]. On top of that, county zoning does not reach land, farm buildings or other structures primarily adapted for agricultural purposes, and a county may not require an application, an approval or a fee to establish that the exemption applies (335.2) [7]. It never covers structures, dams, deposits or excavations in a river or stream floodplain [7]. On an unincorporated site, the characterization of each building is settled before the layout.
2. Cities review plats two miles past their limits. Under Iowa Code 354.9, a city that regulates land division may extend plat review up to two miles beyond its boundary by an ordinance recorded with the county recorder. In a zoning county, both bodies then review a subdivision inside that band, using the city's own standards or standards agreed under a chapter 28E agreement; either may waive review by recorded resolution, and where two cities' review areas overlap without agreement, the nearer city controls [2]. Johnson County publishes its fringe area agreements with its planning materials, which is where the governing standards for a metro-edge parcel are settled [8]. Woodbury County writes the same band into its subdivision regulations [9].
3. Two Iowa IBC amendments sit on the site sheet. Iowa adopted the 2024 IBC with amendments in IAC 481 Chapter 301, effective 9/10/25 [1]. New section 1003.8 requires frost protection at exterior door landings, and new section 1027.5.1 requires exit discharge pathways to be paved from all exits of the building to the public way [1]. The energy code is still IECC 2012, and any building over 100,000 cubic feet of heated or cooled space needs a signed and sealed energy compliance statement from a registered architect or licensed professional engineer, filed before any local permit (481-301.23(3)) [1]. The rules moved from 661 to 481 after 2023 Iowa Acts, SF 514 placed the building code under the Department of Inspections, Appeals, and Licensing (DIAL), so a checklist that cites 661 Chapter 301 is out of date [1].
4. Construction stormwater needs a newspaper notice and DNR issuance before grading. Iowa DNR NPDES General Permit No. 2 (GP2) covers land disturbance of one acre or more, including smaller sites within a larger common plan, and runs from 1 March 2023 to 29 February 2028 [3]. The SWPPP must be complete before the notice of intent; a public notice must be published at least one day in the newspaper with the largest circulation in the area under 567 IAC 64.6(1)"c"(1); proof of publication goes with the NOI and fee; and DNR must issue coverage before soil disturbance starts [3, 10, 11]. The SWPPP must also comply with Iowa Code 161A.64 on sediment control [3].
5. SUDAS is the drafting standard most Iowa cities adopt. The Statewide Urban Design and Specifications program is maintained by the Institute for Transportation at Iowa State University and revised once a year, usually in December; the 2026 editions are posted [12]. Its Design Manual has chapters for stormwater, sanitary sewers, water mains, roadway design and erosion control, and Chapter 8 covers parking lots, the chapter a site layout is drawn to [13]. Cities adopt SUDAS with local addenda: Urbandale keeps addenda to both the SUDAS manuals and the Iowa Stormwater Management Manual (ISWMM), so the addendum governs alongside the base manual [14, 15].

Approval layers: state, county and city
| Layer | Body | What it decides |
|---|---|---|
| State | DIAL Building Code Bureau | State Building Code where it applies; plan review fee minimum $200 under 481-300.4(2) [16] |
| State | Iowa DNR | GP2 stormwater; water use permits for withdrawals of at least 25,000 gallons in a 24-hour period; private well permits [3, 17] |
| State | Iowa DOT | Access to primary highways under Iowa Code 306A and 761 IAC Chapter 112 [18] |
| County | Board of supervisors | Zoning, only if elected (335.1), and never over exempt farm structures (335.2) [5, 7] |
| County | Board of health | Private sewage disposal under 567 Chapter 69 [1] |
| County | County engineer | Entrances onto county secondary roads [19] |
| City | Staff, plan and zoning commission, council | Zoning, site plan review, and plat review inside the city and up to two miles out [2] |
Inside a city, the site plan follows one of three tracks, and the trigger is usually adjacency or a requested deviation, not project size.
| Track | Decision maker | Typical trigger |
|---|---|---|
| Administrative | Planning or development services director, often with an interdepartmental review group | Compliant project, no requested exceptions, no residential adjacency |
| Commission | Plan and zoning commission or city planning commission | A design exception, adjacency to residential zoning or residential future land use, or a linked rezoning |
| Council or board | City council or county board of supervisors | Rezoning, planned development overlay, development agreement, some county conditional uses |
Des Moines sends any application with a Type 2 design exception to a public hearing site plan before the Plan and Zoning Commission [20]. Cedar Rapids requires a Preliminary Site Development Plan before the City Planning Commission when the site adjoins residentially zoned land or land shown for residential use on the Future Land Use map [21]. Johnson County requires an engineered site plan before a building permit in its RR, C, CH, AG-T, C-AG, ML, MH and SWDRR zones [8].
Who prepares and seals an Iowa site plan
Iowa's design boards and the Building Code Bureau publish the Iowa Building Code Official's Handbook, which states that site and plot plans may be sealed and certified by an Iowa licensed architect, professional engineer or landscape architect [4]. Cities can narrow that field. Cedar Rapids requires both its Administrative and its Preliminary Site Development Plan to be the engineered plan of improvements certified by a registered civil engineer licensed in Iowa [21]. A landscape architect's scope covers building location, parking, walks, grading and drainage, but excludes public streets, utilities, and storm and sanitary sewers (Iowa Code 544B.1) [4].
For buildings, Iowa Code 544A.18 lists the buildings that may be planned and designed by a person without an architect's license [22]:
| Building | Limit under 544A.18 |
|---|---|
| Warehouse or commercial, one story | Not exceeding 10,000 SF gross floor area |
| Commercial, two stories | Not exceeding 6,000 SF gross floor area |
| Light industrial | No stated size or height limit |
| Agricultural, including grain elevators and feed mills | Primarily agricultural use |
| Detached residential | Twelve or fewer dwelling units, not more than three stories |
| Factory-built | Not more than two stories and not exceeding 20,000 SF, or certified by a professional engineer |
| Churches and accessory buildings | Not more than two stories and not exceeding 2,000 SF |
The board reads these strictly: the height and the area limit must both be met, an addition is measured against the completed total, and a four-hour fire wall does not create two buildings [4]. Where an exception is relied on, Iowa Code 544A.28 bars the building official from accepting the submission unless the applicant certifies the specific exception on it, and the handbook's Appendix B supplies the form [4, 23]. A licensed professional may seal only documents prepared by them or under their responsible control, out-of-state seals do not carry, and non-final submissions must be labeled "preliminary" or "draft" (193C-6.1(4)) [4].
That sets the frame for a preliminary site plan in Iowa. It carries the layout, buildings, internal roads, drive aisles, parking and the site data table, labeled preliminary and drawn without the engineering layer. The engineer of record, or the architect or landscape architect of record, builds the sealed set on it. The guides on who prepares a site plan and preliminary versus final site plans set out that division, where unsealed site plans are accepted covers the stages that take a preliminary drawing, and the site plan architect page covers how the studio works with the design professionals of record.
Statewide overlays
| Overlay | Rule | Authority |
|---|---|---|
| Accessibility | New buildings open to the public comply with the 2010 ADA Standards for Accessible Design or IBC Chapter 11 (481-301.18); multiunit residential rules apply under 481-301.19, with an accessible elevator in apartment buildings of four or more stories | [1] |
| Primary highway access | A separate permit for each access connection; a traffic impact analysis by an Iowa licensed professional engineer where the department requires one; 20-year projected traffic volumes; the permit expires after one year if construction has not started | [18, 24] |
| Water use | Permit for withdrawals of at least 25,000 gallons in a 24-hour period; 10-year term with an annual report | [17] |
| Private sewage | 567 Chapter 69, incorporated into the State Building Code at 481-301.6(3) and 481-301.8(4); county boards of health administer | [1] |
| Frost and climate loads | No statewide frost depth: Table R301.2 values follow the project location (481-301.8(3)) | [1] |
| Radon | House File 2297, effective 1 July 2026, directs a passive radon rule for new one- and two-family homes; eleven jurisdictions already required it: Bremer, Johnson, Linn and Polk counties and Altoona, Bondurant, Carroll, Iowa City, North Liberty, Norwalk and Pella | [25] |
| Storm shelters | ICC 500-2014 governs where a shelter is required by other law or built voluntarily; the tornado provision controls (481-301.39) | [1] |
| Floodplain | The farm exemption does not reach floodplains; DNR Flood Plain Development Permits are a separate state permit; Iowa City's 14-5J floodplain standards cannot be adjusted by design review | [7, 26, 27] |
| Factory-built structures | An approved factory-built structure is exempt from other state or local building regulation as to manufacture and installation (103A.10(3)) | [6] |
| Code transition | A project commenced within 12 months after revised standards take effect may use either edition (481-301.10) | [1] |
The IBC and IECC adoption map places Iowa's 2024 structural and 2012 energy editions against other states, and the post on ADA compliance in commercial site plans covers the accessible-route layer.
Top jurisdictions: process, fees and clocks
| Jurisdiction | Instrument and body | What escalates it | Submittal points |
|---|---|---|---|
| Des Moines | Site plan under Chapter 135 (zoning in Chapter 134); community development director | A Type 2 design exception makes it a public hearing site plan before the Plan and Zoning Commission (135-6.2.3) | Required for industrial, commercial and multi-family of three or more units per lot; signed final traffic study or a no-study letter from Traffic Engineering; pre-application conference [20, 28] |
| West Des Moines | Staff approval, with a memo, plans and elevations sent to the Plan and Zoning Commission and City Council | Any two members of the Commission or Council can call the item forward to a regular meeting | One week for concerns, then lobby notice and approval as soon as 48 hours later; items are agendized only when ready [29] |
| Cedar Rapids | Administrative Site Development Plan through the Project Review Group (Chapter 32 zoning, Chapter 31 subdivision, Metro Area Design Standards) | Residential adjacency or residential future land use: Preliminary Site Development Plan to the City Planning Commission, or Council with a rezoning | Mandatory pre-application review; civil engineer certification; Customer Self Service e-submittal, with the city FTP site for files over 20 MB [21] |
| Linn County | Unified Development Code; data center ordinance adopted 18 February 2026 | Large data centers need a water study, a water-use agreement and an economic development agreement; reported 1,000-foot setback from residential zoning | 18-month moratorium on EU-3 Large-Scale Data Center rezoning applications from 1 July 2026 [30, 31] |
| Davenport | Planning and Zoning Commission, meeting twice monthly, reviews site and final development plans (Chapter 2.64) | 11-member Design Review Board in the C-D, C-V and C-E districts (Chapter 2.63) | E-Plan required for large or complex projects: unsecured vector PDFs, identical file names on revisions, names under 100 characters with no period [32, 33, 34] |
| Iowa City | Site plan under Title 18; zoning under Title 14 | Design review under 14-8B in the Central Planning District, PRM and form-based districts; Sensitive Areas review (14-5I) before any clearing or grading | 2024 IBC and IRC as amended; Customer Self-Service portal [27, 35] |
| Johnson County | Engineered site plan before building permit in listed zones | Board of Supervisors, or the Zoning Administrator for defined conditional uses and plan revisions | 7 to 10 business days once corrections and legal agreements are approved [8] |
| Woodbury County | Subdivision review with municipal review inside two miles, or as set by a 28E agreement | Concurrent city review | Final plats to Iowa Code 355.8 and 354.6 through 354.11 [9] |
| Body | Published fee or penalty |
|---|---|
| Johnson County | Rezoning to RS, RM, RR, RC, C, CH, C-AG, ML, MH or SWDRR: $400 plus $40 per acre. Rezoning to RE: $2,000 plus $100 per acre above 20 acres. Preliminary plat: $500 plus $40 per buildable lot and $20 per outlot. Republication after modification: $50 [36] |
| Cedar Rapids | Work without a permit, including work started while the permit is in review: double fee, minimum $250, possible $100 per hour investigation fee [37] |
| Des Moines | Tiered by project area with an over-one-acre band; due at submittal and non-refundable once staff review or public notice has begun [28] |
| DIAL state plan review | Minimum $200; $100 added for sustainable design review on projects subject to the state code, $250 where the project is approved by a local building department [16] |
Ankeny, Dubuque, Sioux City, Ames, Council Bluffs and Waterloo, and Polk, Scott and Story counties each run their own process; confirm the current checklist, fee schedule and portal with the city or county before the first submittal. Statewide coverage is on the service areas page.
Asset registries
Iowa licenses few of the asset classes the studio plans. Most run on the general path: zoning, site plan, GP2, an access permit and a building permit. These are the state layers that do exist.
| Asset | State rule | Effect on the site plan |
|---|---|---|
| RV parks, campgrounds and glamping | Iowa Code chapter 557B governs membership campgrounds as a consumer protection matter, enforced by the Attorney General; it does not apply to manufactured home communities or mobile home parks [38] | Water and wastewater run through DNR private well permits, 567 Chapter 69 and the county board of health [1, 26] |
| Gas stations and c-stores | E15 Access Standard (Iowa Code chapter 214A, enacted by HF 2128 in 2022): from 1 January 2026, E15 from at least one dispenser, and from at least 50 percent of qualified dispensers where there is more than one; IDALS may refuse to renew, suspend or revoke licenses [39, 40] | The plan shows the dispenser count and which dispensers carry E15 |
| Fuel storage tanks | Iowa holds EPA State Program Approval; the DNR UST Section registers tanks at $10 one-time per tank plus $65 per year for tanks of 1,100 gal or more, with a $250 late fee [41, 42, 43] | Registration on DNR Form 542-3266 [43] |
| Canopy lighting | Set locally; Waukee caps it at 35 fc average and 2 fc at property lines (160.06) [44] | Photometric limits shape canopy height and fixture count |
| Car washes | No licensing regime; a DNR water use permit applies at 25,000 gallons per day if self-supplied, and drought triggering events can bring allocation restrictions (567-52.10) [17] | A municipal connection avoids the permit but not the utility's capacity and pretreatment conditions |
| Hotels | Hotel license under Iowa Code chapter 137C from DIAL, covering hotels, motels, inns, motor inns and bed and breakfast inns; counties may contract to license and inspect, so the county can be the licensing contact [45, 46] | DIAL's SAFHER online licensing system launches in October 2026 [47] |
| Self storage, industrial and warehouse | No asset-specific state licensing identified | General path |
| Industrial outdoor storage | Set locally: Pella prohibits outdoor storage except in the M1 and M2 districts and listed incidental cases, screened per Code 165.31 (Code 165.28) [48] | Storage yards sit in M1 or M2, behind screening |
| Marinas and waterfront | No marina-specific state rule is set out here; floodplain work stays regulable even on farm land, and DNR Flood Plain Development Permits are a separate state permit [7, 26] | Confirm each waterfront permit with DNR before the layout is fixed |
| Data centers | A data center building is approved as sustainably designed if it achieves LEED Certified and complies with ASHRAE 90.1-2007 (481-301.34(3)) [1] | Linn County adds a water study, water-use agreement and setbacks |
The 50-state RV park site plan matrix sets the states' campground rules side by side, and the gas station permitting guide covers the tank and traffic layer.
Timelines and bottlenecks
| Step | Published timing | Source |
|---|---|---|
| Des Moines administrative site plan | Final decision or comments within 30 days of a complete submittal | [20] |
| West Des Moines staff approval | One week for Commission and Council concerns, then approval as soon as 48 hours after lobby notice | [29] |
| Johnson County engineered site plan | 7 to 10 business days after corrections and legal agreements | [8] |
| Iowa DOT access permit | Expires after 1 year if construction has not started | [24] |
| Individual NPDES permit | Apply 180 days before operation | [3] |
| State code transition | 12 months to use either the new or previous standards | [1] |
Five points hold Iowa schedules:
- GP2 sequencing. SWPPP, then newspaper notice, then the NOI with fee and proof of publication, then DNR issuance, all before ground disturbance [3].
- Dual review on the metro fringe. Inside a declared two-mile band in a zoning county, a subdivision goes to both bodies unless a 28E agreement sets one standard [2].
- The residential-adjacency escalation. One Type 2 design exception in Des Moines, or residential adjacency in Cedar Rapids, turns a staff approval into a commission hearing [20, 21].
- Gates that precede grading. Iowa City's 14-5I sensitive areas approval comes before woodland clearing, grading or any development activity, and neither 14-5I nor 14-5J standards can be relaxed through minor adjustments [27].
- Data center rezoning in Linn County. The EU-3 path is closed by the 18-month moratorium that began 1 July 2026 [31].
Common resubmittal causes: no proof of newspaper publication with the GP2 NOI; no sealed energy statement for a building over 100,000 cubic feet; exit discharge shown unpaved or door landings without frost protection; Davenport file naming; a late traffic study determination in Des Moines; and an unsealed submission without the certificate of exception [1, 3, 4, 28, 34].
Proof points
Linn County, 2025 to 2026. In October 2025 Google announced a third Linn County data center near Palo. On 18 February 2026 the Linn County Board of Supervisors unanimously adopted its data center ordinance, with a water study, water use agreement and economic development agreement for large projects. On 1 July 2026 the county imposed an 18-month moratorium on new EU-3 rezoning applications and stated an intention to ask the legislature for statewide standards [30, 31, 49]. The data center development post covers the wider power and incentive picture.
Where the preliminary plan fits
An Iowa project usually needs one drawing that answers four audiences before any engineering is ordered: the city at a pre-application conference (expected in Des Moines, mandatory in Cedar Rapids), the lender, the general contractor pricing the work, and the engineer of record who then builds the sealed set to SUDAS and ISWMM [12, 15, 21, 28]. The studio's site plan service draws that preliminary plan, and the site plan consultant page covers jurisdiction research and the approval path. Across the borders, the Illinois, Minnesota, Missouri, Nebraska, South Dakota and Wisconsin pages set out the neighboring regimes.
Frequently asked questions
Who can stamp a site plan in Iowa?
An Iowa licensed architect, professional engineer or landscape architect, under the Iowa Building Code Official's Handbook [4]. Some cities are narrower: Cedar Rapids requires its Site Development Plan to be certified by a registered civil engineer licensed in Iowa [21]. A preliminary site plan is the drawing that engineer of record builds the certified set on.
Do I need a licensed architect to design a small commercial building in Iowa?
Often not. Iowa Code 544A.18 exempts warehouses and commercial buildings of not more than one story and not exceeding 10,000 square feet, commercial buildings of not more than two stories and not exceeding 6,000 square feet, and light industrial buildings. Both the height and the area limit must be met, and the submission must carry a certification of the specific exception [4, 22].
Does county zoning apply to my rural Iowa parcel?
Only if the county has elected to zone (Iowa Code 335.1), and even then not to land or structures primarily adapted for agricultural purposes. A county may not require an application, an approval or a fee to establish that the exemption applies. Floodplain regulation still reaches exempt land (335.2) [5, 7].
My site is outside city limits. Why is the city reviewing my plat?
Iowa Code 354.9 lets a city extend plat review up to two miles beyond its boundaries by recorded ordinance. Inside that band both the city and a zoning county review, unless one waives by resolution or the two have agreed standards under a chapter 28E agreement [2].
When does a construction stormwater permit apply in Iowa?
At one acre of disturbance, or less if the site is part of a larger common plan. The notice of intent must be accompanied by proof that a public notice ran for at least one day in the newspaper with the largest circulation in the area, and DNR must issue coverage before soil disturbance begins [3, 11].
Which building code edition is Iowa on?
The 2024 IBC, IRC and IEBC, effective 10 September 2025, under IAC 481 Chapter 301. The energy code remains IECC 2012 for both residential and commercial work. The rules were renumbered from 661 Chapter 301 to 481 Chapter 301, published in the IAC Supplement of 26 November 2025 [1].
Do new Iowa homes need radon systems?
House File 2297, effective 1 July 2026, requires the State Building Code Commissioner to add a passive radon mitigation requirement for new single-family and two-family homes. DIAL has said the requirement becomes enforceable only once the commissioner adopts it, and applies to construction that commences after adoption. Eleven Iowa jurisdictions already required it [25, 50].
How do I get a driveway onto a state highway in Iowa?
Through the Iowa DOT electronic permitting system at eps.iowadot.gov, under Iowa Code 306A and 761 IAC Chapter 112. Each access connection needs its own permit, the highway segment's access category governs what is allowed, a traffic impact analysis by an Iowa licensed professional engineer may be required, and the permit expires after one year if construction has not begun [18, 24].
Sources
- 1)Iowa Administrative Code 481, Chapter 301, State Building Code, Iowa Legislature. Accessed 2026-08-30.
- 2)Iowa Code 354.9, Review of subdivision plats, Iowa Legislature. Accessed 2026-08-30.
- 3)NPDES General Permit No. 2, Storm Water Discharge Associated with Industrial Activity for Construction Activities, Iowa Department of Natural Resources. Accessed 2026-08-30.
- 4)Iowa Building Code Official's Handbook (September 2019 edition), Iowa Department of Inspections, Appeals, and Licensing. Accessed 2026-08-30.
- 5)Iowa Code chapter 335, County Zoning (335.1), Iowa Legislature. Accessed 2026-08-30.
- 6)Iowa Code 103A.10, State Building Code application, Iowa Legislature. Accessed 2026-08-30.
- 7)Iowa Code 335.2, Farms exempt, Iowa Legislature. Accessed 2026-08-30.
- 8)Planning and Development, Johnson County Planning, Development and Sustainability. Accessed 2026-08-30.
- 9)Subdivision Regulations, Woodbury County, Iowa. Accessed 2026-08-30.
- 10)Stormwater Permit Information, Iowa Department of Natural Resources. Accessed 2026-08-30.
- 11)Notice of Intent instructions, General Permit No. 2, Iowa Department of Natural Resources. Accessed 2026-08-30.
- 12)Statewide Urban Design and Specifications (SUDAS), Institute for Transportation, Iowa State University. Accessed 2026-08-30.
- 13)SUDAS Design Manual, Institute for Transportation, Iowa State University. Accessed 2026-08-30.
- 14)Urbandale addenda to the SUDAS manuals and ISWMM, City of Urbandale, Iowa. Accessed 2026-08-30.
- 15)Iowa Stormwater Management Manual, Iowa Department of Natural Resources. Accessed 2026-08-30.
- 16)Building Code Plan Review, Iowa Department of Inspections, Appeals, and Licensing. Accessed 2026-08-30.
- 17)Water Allocation and Use, Iowa Department of Natural Resources. Accessed 2026-08-30.
- 18)Access Management, Iowa Department of Transportation. Accessed 2026-08-30.
- 19)Driveways and Entrance Permits, Winnebago County, Iowa, Road Department. Accessed 2026-08-30.
- 20)Des Moines Planning and Design Ordinance, Chapter 135, City of Des Moines (encodeplus). Accessed 2026-08-30.
- 21)Site Development Plans, City of Cedar Rapids, Community Development. Accessed 2026-08-30.
- 22)Iowa Code 544A.18, Exceptions, Iowa Legislature. Accessed 2026-08-30.
- 23)Iowa Code chapter 544A, Architecture, Iowa Legislature. Accessed 2026-08-30.
- 24)Iowa Administrative Code 761-112.4, Access permitting, Iowa Legislature. Accessed 2026-08-30.
- 25)Radon Resources, Iowa Department of Health and Human Services. Accessed 2026-08-30.
- 26)Private Well Construction Permits, Iowa Department of Natural Resources. Accessed 2026-08-30.
- 27)Iowa City Code of Ordinances (Titles 14 and 18), City of Iowa City (American Legal Publishing). Accessed 2026-08-30.
- 28)Site Plan Review, City of Des Moines, Planning and Urban Design. Accessed 2026-08-30.
- 29)Development Applications, City of West Des Moines, Planning Division. Accessed 2026-08-30.
- 30)Data Centers in Unincorporated Linn County, Linn County, Iowa. Accessed 2026-08-30.
- 31)Linn County news release (CivicAlerts AID 4487), Linn County, Iowa. Accessed 2026-08-30.
- 32)Planning and Zoning Commission, City of Davenport. Accessed 2026-08-30.
- 33)Design Review Board, City of Davenport. Accessed 2026-08-30.
- 34)Electronic Plan Review (E-Plan), City of Davenport. Accessed 2026-08-30.
- 35)Building Inspection Services, City of Iowa City. Accessed 2026-08-30.
- 36)PDS Fee Schedule, Johnson County Planning, Development and Sustainability. Accessed 2026-08-30.
- 37)Building Services FAQs, City of Cedar Rapids. Accessed 2026-08-30.
- 38)Membership Campgrounds, Iowa Attorney General. Accessed 2026-08-30.
- 39)Iowa E15 Access Standard (law 12998), U.S. Department of Energy, Alternative Fuels Data Center. Accessed 2026-08-30.
- 40)HF 2128 (2022), Legislative Guide, Iowa Legislature. Accessed 2026-08-30.
- 41)List of States With Approved UST Programs and Respective Federal Register Notices, U.S. Environmental Protection Agency. Accessed 2026-10-09.
- 42)Underground Storage Tank FAQ (updated May 2025), Iowa Department of Natural Resources. Accessed 2026-10-09.
- 43)UST Section Registration Form, DNR Form 542-3266, Iowa Department of Natural Resources. Accessed 2026-10-09.
- 44)Waukee Code 160.06, Lighting Standards, Design Guidelines, City of Waukee, Iowa (American Legal Publishing). Accessed 2026-10-09.
- 45)Hotels and Motels, Iowa Department of Inspections, Appeals, and Licensing. Accessed 2026-08-30.
- 46)Iowa Code chapter 137C, Hotel Sanitation Code, Iowa Legislature. Accessed 2026-08-30.
- 47)Food Establishments and Hotels, Iowa Department of Inspections, Appeals, and Licensing. Accessed 2026-08-30.
- 48)Pella Code 165.28, Supplemental use regulations: outdoor storage outside of the industrial zoning districts, City of Pella, Iowa (American Legal Publishing). Accessed 2026-10-10.
- 49)Iowa county data center ordinance, Inside Climate News. Accessed 2026-08-30.
- 50)Gov. Reynolds signs bill requiring radon mitigation in all new Iowa homes, KCRG. Accessed 2026-08-30.