Georgia permits an RV park as a tourist accommodation under Department of Public Health rules that fix separations, driveway widths and bathhouse distances but leave density to the county. This page sets out that rule, the state approval layers and seal statutes, and the county, coastal and metro Atlanta layers on top.

Last reviewed

State permit
DPH tourist accommodation permit under Rule 511-6-2, effective January 1, 2014 [1]
Separations
15 ft trailer to buildings; 10 ft trailer to internal driveways [1]
Internal driveways
All-weather, at least 20 ft wide, unobstructed [1]
Density and site size
Not in the state rule; set by county or city zoning [1]
Plans to DPH
Due 14 days before construction [1]
Land disturbance permit
At 1.0 acre disturbed, or under 1 acre within 200 ft of state waters [2]

The state regime: a DPH tourist accommodation permit

Georgia permits an RV park as a tourist accommodation. Department of Public Health (DPH) Rule 511-6-2, under O.C.G.A. 31-28 and effective January 1, 2014, treats recreational vehicle parks and campgrounds as tourist accommodations [1]. Plans are due 14 days before construction [1]. The plan review covers the site plan, floor plan, elevation and cross section, and a new facility must score 100% on its permitting inspection [3, 4]. Inspections then happen at least twice a year [1, 5].

The rule sets distances and services, not yield. Each line below carries the rule section the site plan is checked against:

Rule elementGeorgia standard
Trailer to buildings15 ft (.18(4)) [1]
Trailer to internal driveways10 ft (.18(4)) [1]
Internal drivewaysAll-weather, at least 20 ft wide, unobstructed (.18(5)) [1]
Bathhouses1 commode, lavatory and shower per sex for every 10 dependent spaces, within 200 ft (.08(14)) [1]
Public water systemRequired at an average of 25 spaces daily for 60 days a year (.07(1)(a)) [1]
Sewer and dump station3 in. sewer connection per space (.09(2)); dump station sized to the sites on a 6 ft by 6 ft pad (.09(5)); potable water outlet 50 ft away [1]
ElectricalA 115 V outlet at each space (.18(6)) [1]
OccupancyNot for permanent residence (.03(ll)) [1]
Density and site sizeNot in the rule [1]

Density and site size are left to the county or city, so the yield of a Georgia park is set by local zoning and by the distances above, not by a state cap [1]. Those distances still decide the geometry: every trailer sits 15 ft from any building and 10 ft from the internal driveway, the driveway itself is at least 20 ft wide, and the dependent spaces sit within 200 ft of a bathhouse [1]. The RV sites per acre guide shows how distances like these turn into yield.

Georgia's state minimum codes include the 2023 NEC with 2026 Georgia Amendments, effective January 1, 2026, alongside the 2024 ICC family [6]. In the 2023 text, NEC 551.71 requires at least one 20 A, 125 V receptacle at every site with electrical supply, a 30 A receptacle at no fewer than 70 percent of sites, and a 50 A, 125/250 V receptacle at no fewer than 40 percent of new sites [7]. The plan counts the 30 A and 50 A sites in its site data table; the engineer of record designs the service.

Approval layers in Georgia

Counties govern unincorporated land and cities govern inside their limits, and annexation changes which code applies [8]. Rezonings are legislative decisions under the Zoning Procedures Law, O.C.G.A. 36-66 [9]; since the 2022 amendments (HB 1405), variances, special administrative permits, special exceptions and conditional use permits are quasi-judicial and need a hearing with at least 30 days' notice [10].

LayerWho decidesWhat it controls for an RV park
Tourist accommodation permitDPHSeparations, driveways, bathhouses, water, sewer and dump station [1]
Zoning: rezoning, special use or conditional useCounty or cityWhere the use is allowed, density, buffers, stay limits [9, 10]
Land disturbance permit and NPDES coverageLocal Issuing Authority or EPDDisturbance of 1.0 acre or more [2, 11]
Stream and river buffersEPD and DNR; the Chattahoochee corridor under the Metropolitan River Protection Act25 ft along state waters; 50 ft along trout streams; corridor buffers [12, 13]
State highway accessGDOT District Access ManagementDriveway permit on a state route [14]
Building permitsCounty or city2024 ICC codes with Georgia Amendments; 2023 NEC [6]

A Land Disturbance Permit is required at 1.0 acre of disturbance, for any disturbance in a common development (a subdivision platted after 1/1/2000), or for disturbance under 1 acre within 200 ft of state waters [2]. The construction stormwater permits GAR100001, GAR100002 and GAR100003 were reissued effective August 1, 2023 and run through July 31, 2028 [11]. The Notice of Intent is filed at least 14 days before construction with an ES&PC Plan, and no more than 50 acres may be actively disturbed at once without EPD district authorization [15]. The fee is $80.00 per disturbed acre, split $40 to EPD and $40 to the Local Issuing Authority where a certified one exists, otherwise the full $80 to EPD [16]. For a phased park, the disturbed area of each phase is a line in the site data table.

The buffers come next. O.C.G.A. 12-7-6 sets a 25 ft buffer along state waters, measured from wrested vegetation, a 50 ft buffer along trout streams and a 25 ft buffer along coastal marshlands [12]. Within 2,000 ft of the Chattahoochee between Buford Dam and the Fulton and Douglas county limits, the Metropolitan River Protection Act adds a 50 ft undisturbed buffer and a 150 ft impervious setback along the river and a 35 ft buffer along tributaries [13]. In water supply watersheds, DNR's Part 5 criteria (Rules 391-3-16) require 100 ft buffers on tributaries within 7 miles of an intake plus a 150 ft impervious setback, and septic tanks and drainfields are prohibited in the setback [17]. For a park sited on a creek or a lake, these lines are drawn before the pads.

Crossing a buffer is its own approval. Buffer variances follow the procedures and criteria of DNR Rule 391-3-7-.05, and some enumerated activities need no application, such as specified perpendicular utility crossings with under 50 ft of disturbance and roadway drainage structures [18]. Wetlands and other waters of the U.S. are regulated under Section 404 of the Clean Water Act by the U.S. Army Corps of Engineers, whose Savannah District covers Georgia [19]. On-site sewage systems are regulated by DPH, and private wells and groundwater or surface water withdrawal permits by EPD; around Savannah, withdrawal caps on the Floridan aquifer, imposed in 2013 because of saltwater intrusion, constrain new supply [20]. A park that will cross the public water system trigger plans its water source with that in mind.

Who prepares and seals what

Georgia ties seals to the work. O.C.G.A. 43-15-24 requires works that involve professional or structural engineering and could, by their function or existence, endanger public health, safety or welfare to be prepared under the seal of a professional engineer, architect or professional structural engineer [21]. The section does not apply where the completed cost is less than $100,000.00 or the use is exclusively private or farm, but a 1987 Attorney General opinion holds that schools, auditoriums, buildings for mass assemblage and group housing projects are not exempt at any cost [21, 22]. Under O.C.G.A. 43-4-14, single-story buildings not exceeding 5,000 sq ft need no architect's seal, except assembly, educational, health care, detention, hotel, lodging, multifamily and care occupancies [23]. Boundary surveys and recordable plats are sealed by a Georgia-registered land surveyor under the Plat Act, O.C.G.A. 15-6-67, and Board Rule Chapter 180-7 [24], and the ES&PC Plan is prepared by a design professional certified through a Georgia Soil and Water Conservation Commission course under O.C.G.A. 12-7-9 [25].

Two survey rules shape the base sheet. A topographic survey carries a note that the surveyor's certification extends only to its topographic aspects, sealing of topographic surveys and non-boundary drawings falls under Rule 180-12, and the Plat Act was updated in 2017 and again in 2024 [24]. O.C.G.A. 43-15-13.1 gives land surveyors a limited pathway into the design of stormwater management plans, water distribution lines and sanitary sewer collection systems [26].

A seal goes only on work the professional controls. Under O.C.G.A. 43-15-22(d), sealing work that another person prepared outside the licensee's daily direct supervisory control, without a thorough review of that work, is a fraudulent act of misconduct [27]. The engineer of record therefore does not stamp the studio's sheet. The engineer takes the preliminary plan as the layout brief and draws the sealed civil set (grading, stormwater, water and sewer, the ES&PC Plan) under their own responsible charge, and the architect of record does the same for any building that needs a seal.

County zoning sets density and stay limits

The state rule leaves yield to local codes, and Georgia counties write their own RV and campground standards. Cherokee County requires a 10-acre minimum lot, a 50 ft buffer and a 30-day maximum stay for lodge and campground uses [28]. Savannah's zoning caps RV park stays at 90 days and sets a 5 acre minimum [29]. Gwinnett County allows RV parks and campgrounds only in its RA-200 district, as a special use in the Sec. 210-130 use table, through a Special Use Permit under UDO Sec. 270-30 [30]. The gas station and c-store model project in Gwinnett County walks a site through that county's special use path.

The coast runs its own intake. In Chatham County the Metropolitan Planning Commission takes applications and Engineering issues permits, site plan review meetings are encouraged, and MPC fees run by acres or lots; Bryan County may require a traffic impact analysis before review and sends final plats and easements to its Board of Commissioners; Effingham County's review includes a flood plain engineer approval [31]. A park on the coast around Savannah therefore meets a different first gate in each county.

Review time depends on the approval type. Administrative reviews move in weeks: an initial civil or land disturbance review in Gainesville runs about 2 to 3 weeks, and Hall County reviews building plans in 14-day cycles [32]. A park that needs a rezoning, special use permit or variance runs longer, because those decisions go to public hearings, with at least 30 days' notice for quasi-judicial matters [10].

Metro Atlanta

Metro Atlanta splits by jurisdiction. Inside Atlanta's city limits, the Department of City Planning requires a Special Administrative Permit ahead of any building permit in the SPI and BeltLine districts and in LW, MR, MRC, NC, I-Mix and Unified Development Plan districts [33]. For SPI-16 Midtown, Chapter 16-18P asks for a site plan, a landscape plan and facade elevations [34], and the SAP forms send tree preservation, the riparian buffers ordinance, land disturbance regulations, drainage and sewer capacity to separate reviews [35]. Unincorporated Gwinnett confines RV parks to RA-200 by special use permit [30], and any parcel within 2,000 ft of the Chattahoochee carries the corridor buffers [13]. The Atlanta-Sandy Springs-Roswell metro grew from 6,106,816 residents in April 2020 to 6,482,182 in July 2025 and added 61,953 from 2024 to 2025, third in the nation by numeric gain [36]. The Atlanta page covers the city and county processes in more depth.

Coast, mountains and floodplains

The coastal counties (Chatham, Bryan, Liberty, Glynn, Camden and McIntosh) face hurricane wind and surge exposure, with higher design wind pressures and, in flood and surge zones, elevated finished-floor and foundation requirements; after Hurricane Helene, DNR's Coastal Resources Division issued emergency permitting orders from October 2, 2024 through March 31, 2025 to speed repair and reconstruction [37]. Coastal marshlands carry the 25 ft buffer and trout streams the 50 ft buffer set out above [12]. Work in the marshes or on the shore is permitted separately by the Coastal Resources Division under the Coastal Marshlands Protection Act (O.C.G.A. 12-5-280 et seq.), the Shore Protection Act (O.C.G.A. 12-5-230 et seq.) and its Revocable License Authority [38]. In Bryan County, the Hyundai Metaplant at Ellabell is a $7.59 billion investment on 2,284 acres; it held its grand opening on March 26, 2025 and will use up to 6.6 million gallons of water a day [39]. Across the state, an RV in a special flood hazard area must meet manufactured home elevation and anchoring under 44 CFR 60.3(c)(14) unless it is on site fewer than 180 consecutive days, or is fully licensed and ready for highway use [40]; a Georgia park is already defined as not for permanent residence [1].

How Georgia's rule compares

ItemGeorgiaFloridaTennessee
Density in the state ruleNone; local zoning [1]25 units per gross acre [41]None; local zoning [42]
Minimum site in the state ruleNone [1]1,200 sq ft [41]None; plans must show dimensions [42]
Separation15 ft trailer to building; 10 ft to driveway [1]Fixed at initial approval [43]15 ft or more between units [42]
Internal road widthAt least 20 ft [1]Not specified; maneuvering may not use the right-of-way [41]Plans must show width; no minimum found [42]
Bathhouse ratioPer 10 dependent spaces, within 200 ft [1]One set per 25 non self-contained spaces [44]Fixture table by site count [42]

Of the three, only Georgia writes an internal driveway width and a numeric public water system trigger into the park rule itself [1, 41, 42, 44]. As in Tennessee, there is no state density cap and no minimum site, so the local code and the distance rules together set the count.

What the preliminary plan carries for a Georgia park

A preliminary site plan for a Georgia park is drawn to the DPH rule and the local code together. Its site data table carries the gross acreage and the local density limit, the closest trailer-to-building and trailer-to-driveway distances against 15 ft and 10 ft, driveway widths against 20 ft, dependent spaces and bathhouse distances against the 10-space and 200 ft rule, the occupancy check against the public water system trigger, disturbed acreage against the 1.0 acre threshold, and the state waters, trout stream or corridor buffers drawn in place [1, 2, 12, 13]. It goes to the county at concept and pre-application, to a lender, and to a general contractor for pricing, and the same layout drives the RV park and resort rendering views.

The engineering layer belongs to the engineer of record: the ES&PC Plan, grading and stormwater, the water supply, sewer or septic design and the electrical service sized to NEC Article 551. The Georgia site plan page covers the statewide approval layers for every asset, and the RV park site plan hub sets out the layout method; resort and tent-led programs are on the RV resort and campground pages. Other state pages: RV park site plans in Florida and Tennessee RV parks. The model projects are listed under case studies, and the RV park design standards post compares the numbers across states.

Frequently asked questions

How far apart must RVs be in Georgia?

The DPH rule sets 15 ft between trailers and buildings and 10 ft between trailers and internal driveways. It sets no density or site size; those come from county or city zoning [1].

How wide must RV park driveways be in Georgia?

All-weather and at least 20 ft wide, unobstructed, under DPH Rule 511-6-2 [1].

When does a Georgia RV park need a public water system?

When it averages 25 spaces daily for 60 days a year [1].

How much land does a Georgia RV park need?

The state rule sets no minimum, so the county or city does: Savannah's zoning sets a 5 acre minimum [29], and Cherokee County requires a 10-acre minimum lot for lodge and campground uses [28].

Can guests live in a Georgia RV park full-time?

The DPH rule defines these parks as not for permanent residence [1]. Local codes add stay limits: Savannah caps stays at 90 days [29], and Cherokee County sets a 30-day maximum stay for lodge and campground uses [28].

Do I need a land disturbance permit in Georgia?

Yes, if you disturb 1.0 acre or more, if the lot is within a common development (a subdivision platted after 1/1/2000), or if you disturb less than 1 acre within 200 ft of state waters [2].

Can I open an RV park in Gwinnett County?

Only in the RA-200 district, and only with a Special Use Permit [30].

Can a site plan be prepared without an engineer in Georgia?

Drafting is permitted, but recordable plats, engineered site infrastructure and non-exempt building documents must be prepared under the responsible charge of, and sealed by, a Georgia-licensed professional (O.C.G.A. 43-15-22; 43-4-16) [27]. The engineer of record takes the preliminary plan as the layout brief for that sealed set.

Sources

  1. 1)Rules and Regulations for Tourist Accommodations, Chapter 511-6-2, Georgia Department of Public Health. Accessed 2026-10-09.
  2. 2)Land disturbance permit thresholds (gaswcc.georgia.gov; dawsoncountyga.gov; whitfieldcountyga.com), Georgia Soil and Water Conservation Commission; Dawson County; Whitfield County. Accessed 2026-08-02.
  3. 3)Tourist Accommodations Rules and Plan Review Checklist (dph.georgia.gov), Georgia Department of Public Health. Accessed 2026-08-02.
  4. 4)Tourist Accommodations, District 4 Public Health, Georgia Department of Public Health. Accessed 2026-10-10.
  5. 5)Inspection Guidance and Instructions, Environmental Health Section, Georgia Department of Public Health. Accessed 2026-10-09.
  6. 6)New Codes, Effective January 1, 2026 (dca.georgia.gov), Georgia Department of Community Affairs. Accessed 2026-08-02.
  7. 7)551.71(A)(B)(C)(F) Receptacle Requirements at RV Parks (NEC 2023 text), Leviton Captain Code. Accessed 2026-10-09.
  8. 8)O.C.G.A. Title 36, county and municipal authority and annexation, State of Georgia. Accessed 2026-08-02.
  9. 9)O.C.G.A. 36-66-5.1, Zoning Procedures Law (law.justia.com), State of Georgia (via Justia). Accessed 2026-08-02.
  10. 10)Analysis of the 2022 amendments to the Zoning Procedures Law, HB 1405 (readingroom.law.gsu.edu), Georgia State University Law Review. Accessed 2026-08-02.
  11. 11)NPDES construction stormwater permits page (epd.georgia.gov), Georgia Environmental Protection Division. Accessed 2026-08-02.
  12. 12)O.C.G.A. 12-7-6, state waters buffers (kmcllaw.com; gaenvlaw.wordpress.com), State of Georgia (quoted by secondary hosts). Accessed 2026-08-02.
  13. 13)Metropolitan River Protection Act and the Chattahoochee corridor (atlantaregional.org), Atlanta Regional Commission. Accessed 2026-08-02.
  14. 14)Access Management Resources; Regulations for Driveway and Encroachment Control (dot.ga.gov), Georgia Department of Transportation. Accessed 2026-08-02.
  15. 15)Erosion and Sedimentation Act and NPDES construction permit guidance (epd.georgia.gov; mack-engineering.com), Georgia Environmental Protection Division; Mack Engineering (secondary). Accessed 2026-08-02.
  16. 16)EPD Fee Fact Sheet, Georgia Environmental Protection Division. Accessed 2026-08-02.
  17. 17)DNR Part 5 Environmental Planning Criteria, Rules 391-3-16 (gaenvlaw.wordpress.com), Georgia Department of Natural Resources (via a secondary host). Accessed 2026-08-02.
  18. 18)DNR Rule 391-3-7-.05, buffer variance procedures and criteria (regulations.justia.com), Georgia Department of Natural Resources, Environmental Protection Division (via Justia). Accessed 2026-08-02.
  19. 19)Section 404 permitting, U.S. Army Corps of Engineers Savannah District (coastalgadnr.org), Georgia DNR Coastal Resources Division. Accessed 2026-08-02.
  20. 20)Savannah-area Floridan aquifer withdrawal caps; wells, septic and withdrawal permitting (wsav.com; thecurrentga.org), WSAV; The Current GA. Accessed 2026-08-02.
  21. 21)O.C.G.A. 43-15-24, engineered works and the cost exemption (Georgia General Assembly; text read via findlaw.com and law.justia.com), Georgia General Assembly (via FindLaw and Justia). Accessed 2026-08-02.
  22. 22)O.C.G.A. 43-15-24 annotation, 1987 Op. Att'y Gen. No. 87-31 (syfert.com), Office of the Attorney General of Georgia (annotation). Accessed 2026-08-02.
  23. 23)O.C.G.A. 43-4-14 (2024), architect seal exemptions (law.justia.com), State of Georgia (via Justia). Accessed 2026-08-02.
  24. 24)Board Rule Chapter 180-7 (Rule 180-7-.07) and the Georgia Plat Act, O.C.G.A. 15-6-67 (rules.sos.ga.gov; law.justia.com), Georgia Secretary of State; State of Georgia. Accessed 2026-08-02.
  25. 25)NPDES construction permits Fact Sheet (March 2023) and Urban Erosion and Sediment Control certification (epd.georgia.gov; gaswcc.georgia.gov), Georgia EPD; Georgia Soil and Water Conservation Commission. Accessed 2026-08-02.
  26. 26)O.C.G.A. Title 43, Chapter 15 index, including 43-15-13.1 (law.justia.com), State of Georgia (via Justia). Accessed 2026-08-02.
  27. 27)O.C.G.A. 43-15-22(d) and 43-4-16, responsible charge and sealing (Georgia General Assembly; text read via law.justia.com and findlaw.com), Georgia General Assembly (via Justia and FindLaw). Accessed 2026-08-02.
  28. 28)Recreational Vehicles, Zoning Frequently Asked Questions; lodge and campground standards, Cherokee County, Georgia. Accessed 2026-10-10.
  29. 29)City of Savannah zoning ordinance of June 22, 2017, City of Savannah, Georgia (enCodePlus). Accessed 2026-10-10.
  30. 30)Unified Development Ordinance, Title 2: Land Use and Zoning (amended October 2025), Gwinnett County. Accessed 2026-10-09.
  31. 31)Development review and permitting pages of Chatham County, Bryan County and Effingham County, Chatham County; Bryan County; Effingham County. Accessed 2026-08-02.
  32. 32)Civil and land disturbance review; building plan review cycles (gainesville.org; hallcounty.org), City of Gainesville; Hall County. Accessed 2026-08-02.
  33. 33)Special Administrative Permit, City of Atlanta Department of City Planning. Accessed 2026-10-10.
  34. 34)Chapter 16-18P, SPI-16 Midtown Special Public Interest District Regulations, City of Atlanta (via Municode). Accessed 2026-10-09.
  35. 35)Application for a Special Administrative Permit (SAP), draft, City of Atlanta. Accessed 2026-10-09.
  36. 36)Slow Growth Impacts Nation's Largest Counties Hardest (CB26-56), U.S. Census Bureau. Accessed 2026-10-09.
  37. 37)Hurricane Helene emergency permitting orders (coastalgadnr.org), Georgia DNR Coastal Resources Division. Accessed 2026-08-02.
  38. 38)Marsh and shore permits: Coastal Marshlands Protection Act, Shore Protection Act and Revocable License Authority (coastalgadnr.org/MarshShore), Georgia DNR Coastal Resources Division. Accessed 2026-08-02.
  39. 39)Hyundai Motor Group Metaplant America, Ellabell (Newsweek, March 26, 2025; AP via MarketBeat, April 10, 2025), Newsweek; Associated Press. Accessed 2026-08-02.
  40. 40)Recreational Vehicle (glossary, 44 CFR 59.1 and 60.3), FEMA. Accessed 2026-10-09.
  41. 41)Fla. Admin. Code R. 64E-15.002, Sites: Mobile Home, Lodging, and Recreational Vehicle Parks, Florida Department of Health (via Cornell LII). Accessed 2026-10-09.
  42. 42)Rules of the Tennessee Department of Health, Chapter 1200-01-05 (July 2002 revision), Tennessee Department of Health. Accessed 2026-10-09.
  43. 43)2025 Florida Statutes, 513.1115, Placement of Recreational Vehicles on Lots in Permitted Parks, Florida Legislature (via Justia). Accessed 2026-10-09.
  44. 44)Chapter 64E-15, Florida Administrative Code (2018 version), Florida Department of Health. Accessed 2026-10-09.