Site plans / Hotels / Tennessee

Hotel site plans in Tennessee

In Tennessee, the state sets the seal line, the stormwater and access permits and the building code; the city sets everything that shapes the hotel layout. This page sets out the state layer, then Murfreesboro, Nashville and Franklin, the documented local layers for a select-service hotel.

Last reviewed

Seal threshold, TCA 62-2-102(b)
Architect or engineer plans at 3 stories or 5,000 sq ft gross [1]
TDEC construction stormwater permit
1 acre of disturbance or more [2]; NOI at least 30 days before land disturbance [3]
Murfreesboro site plan trigger
1 or more acres, or 5,000 sq ft of floor area, in a nonresidential district [4]
Aerial fire apparatus access (IFC D105)
26 ft wide, 15 to 30 ft from one entire side, where the roof is more than 30 ft above grade plane [5]
Recent Murfreesboro hotel votes
Fairfield by Marriott 5-0 (December 18, 2024); 124-room hotel 6-0 (July 15, 2026) [6, 7]

What is statewide in Tennessee, and what is local

Tennessee's planning law is enabling. TCA 13-3-413 (regional) and 13-4-310 (municipal) let planning commissions write site plan review and approval powers into their subdivision regulations [8]. So the rules that shape a hotel layout (permitted districts, overlays, setbacks, parking geometry, design review) are local. What is statewide is the seal line, the state permits, the building code and two planning rules that reach any project.

Under TCA 13-4-104 (municipal) and 13-3-404 (regional), no street, park, public way, public building or public utility, whether publicly or privately owned, may be built or authorized until its location and extent have been submitted to and approved by the planning commission, and the local legislative body can overrule a disapproval [9]. Under TCA 13-3-401, a subdivision in a regional planning area includes any division of a tract of less than five acres for sale or building development [10], so a hotel pad of that size split from a larger tract outside a city goes through plat approval.

LayerRuleApplies to a hotel when
Seal thresholdTCA 62-2-102(b): plans and specifications by a registered architect or engineer, except listed occupancies both under three stories and under 5,000 sq ft gross; amended by 2022 Tenn. Acts ch. 904, effective July 1, 2022 [1]The building is 3 stories or more, or 5,000 sq ft or more
Seal on each sheetTCA 62-2-306: the registrant's seal on every original sheet of a bound set of plans and on the first sheet of the specifications [11]The permit set
Plat sealTCA 66-24-116: no recording of a map, plat or survey without the signature and seal of a registered land surveyor or engineer [12]A lot split or new easements
Construction stormwaterTDEC Construction General Permit TNR100000: 1 acre or more of disturbance, or less if part of a larger common plan of 1 acre or more [2]; NOI at least 30 days before land disturbance [3]Disturbance reaches the threshold
Streams and wetlandsAquatic Resource Alteration Permit, which also serves as the Section 401 certification [13]Any alteration to waters of the state; stormwater coverage waits on the ARAP decision [14]
State route accessTDOT Highway Entrance Permit before any driveway on state right-of-way [15]; a Traffic Impact Study by a licensed professional engineer when TDOT requires one [16]Frontage on a state route
Building codeState Fire Marshal adoption of the 2021 International Codes, with the 2018 IRC [17]The statewide baseline

The building code is a floor with a clock. State law requires adopted codes to be no more than seven years older than the latest published edition [17]. Under TCA 68-120-101, the State Fire Marshal has final enforcement power where a city does not adopt and enforce codes, and the statewide code applies in a city whose local code is not current within seven years or whose enforcement the fire marshal finds inadequate [18].

The seal line, and where the preliminary plan sits

A four-story hotel is above the 3-story line, so a registered architect or engineer prepares and seals its building plans and specifications [1]. TCA 62-2-306 requires the registrant's seal on every original sheet of a bound set of plans and on the first sheet of the specifications, and it forbids a registrant to seal a document that was not prepared by the registrant or under the registrant's responsibility [11]. Board Rule 0120-02-.08 requires the signature across the face of the seal [19], and the Board's conduct rules bar a registrant from taking over, signing or sealing drawings "when such plans are begun by persons not properly registered and qualified" [20].

The same Board rule also says how early drawings are handled. Rule 0120-02-.08(2)(a), effective October 23, 2018, puts the seal on all original sheets of any bound or unbound set of working drawings or plans, and Rule 0120-02-.08(9) requires working or partially completed plans, and any drawings that are not construction documents, to be marked as preliminary and not for construction, for review only, draft, or with another label showing that they are not complete [19]. The land surveyors' Rule 0820-04-.08(2) applies the same principle: working drawings and preliminary documents need no seal and signature when they carry a large bold statement that they are preliminary and not for construction, recording or implementation [21].

That sets the handoff. The preliminary site plan is a labelled concept drawing: the kind of dimensioned plan Murfreesboro asks for at its due diligence meeting, the drawing a lender or general contractor prices, and the program for the design team. The engineer and architect of record take it as the program and layout brief and draw the sealed set under their own responsible charge. Local rules add their own seals: in Murfreesboro the site plan must carry drainage areas "with engineered stamped calculations" [22], and Metro Nashville's permit drawing requirements state "A licensed Tennessee land surveyor or engineer must seal all site plans" [23]. The Metro sheet also requires building plans sealed by an architect or engineer licensed in Tennessee when, among other triggers, the building is 3 stories or more in height [24]. Both are Metro Nashville permit requirements, not lines of state statute [24]. The general answer is in do I need an architect for a site plan.

State permits and site factors that move the schedule

ARAP before stormwater. Construction stormwater permits are not issued until the ARAP/401 decision is made [14]. A stream or wetland touch found late therefore holds up the whole stormwater track, and compensatory stream and wetland mitigation is required for certain impacts under rules the Water Quality Control Board revised in October 2018 [25]. The preliminary plan maps the water features first and keeps the building, parking and detention areas clear of them where the site allows.

The 2026 Construction General Permit. TDEC's page states the 2026 permit took effect "October 1, 2026" and expires "September 30, 2031" [26].

State route frontage. No driveway may be built or changed on state highway right-of-way without the Highway Entrance Permit, and a Traffic Impact Study is required when TDOT determines it necessary, with applicants notified during initial review [15, 16]. A hotel on a state route should show the driveway location on the concept plan early, so the access permit runs in parallel.

Karst in Middle Tennessee. Murfreesboro's Stormwater Management Code (Chapter 27.5) defines karst, karst windows and closed depressions, in a landscape "characterized by sinkholes, springs, conduits, caves" [27]. USGS documented sinkhole flooding in Murfreesboro and Rutherford County, with three focus areas (Shiloh, Hooper Bottom, Manson Pike) where sinkhole flooding has overtopped roadways [28]. Rutherford County's Engineering Department reviews site development plans for stormwater and karst-area compliance, and the county adopted an updated stormwater ordinance in 2024 [29]. Closed depressions go on the preliminary plan as constraints; the geotechnical investigation and their treatment belong to the engineer of record.

Fire access, by edition. In every IFC edition, Section 503.2.1 sets the base fire apparatus access road at 20 ft of unobstructed width and 13 ft 6 in of vertical clearance [30]. Appendix D applies only where a jurisdiction adopts it [31]. In the 2018 edition the aerial access requirement sits in Appendix D (D105); in the 2024 edition it sits in Section 503.1.4 [32, 33]. The 30 ft trigger, the 26 ft width and the 15 to 30 ft offset are the same in both forms, so the layout consequence does not change, but the citation must be confirmed with the fire marshal [32, 33].

Murfreesboro: the documented local layer

Murfreesboro publishes its zoning ordinance, site plan checklist, fees and Planning Commission minutes, and those minutes record recent hotel approvals that match a select-service program. The points that shape the plan:

  • Use. Chart 1 shows "Hotel" as permitted by right in six district columns; approvals confirm CH and MU [34]. The Chart 1 endnotes make an "X" use one "permitted by right subject to site plan review and approval and the issuance of building permits" [35]. The city's definition of a hotel requires ingress and egress to and from all rooms through an inside lobby or office supervised by a person in charge at all hours [36], and an exterior-corridor product would be a "Motel", a separately listed use [37]. "Extended Stay Hotel/Motel" applies where at least 5% of rooms are offered for extended stays, and it is permitted in only two columns, so brand choice can change the district screen [34, 36].
  • Due diligence. A zoning verification letter costs $25 for the basic letter (5 to 7 business days) or $50 expedited (3 business days) [38].
  • Who approves. "Any development of one or more acres or five thousand square feet of floor area to be located in a nonresidential district shall require a site plan approval by the Murfreesboro Planning Commission" [4]. Staff indicate whether a site plan goes to the Commission or is reviewed administratively [39].
  • The concept stage. The due diligence meeting requires "A dimensioned conceptual site plan ... depicting all proposed and existing structures, vehicle and pedestrian access, parking, landscaping, potential drainage area(s) and a site data table." At the pre-application meeting, plans "should be 90-95% complete" [40].
  • Gateway Design Overlay. Hotels in the overlay go through initial design review, then final design review with the site plan. As applied, the overlay asks for masonry on 50 percent of fronts and 35 percent of sides and rear [41], and the Hyatt House approval reduced EIFS to 15 percent or less [42]. In July 2021 the Commission refused a ground-level glass curtain wall without a 24-inch base, and the same minutes record the Design Guidelines' 20 percent open space against a PUD request to reduce it to 15 percent [43]. An October 18, 2023 approval conditioned a brand sculpture to "be brought back to Planning Commission for review" [44].
  • Facade changes. A facade change after approval goes back to the Commission as a separate exterior architecture modification review: the Fairfield by Marriott returned and was approved 6-0 on October 15, 2025, with the site stated as 2.68 acres [45].
  • Overlays to map. The checklist requires the site plan to show "airport zones, flood zones, battlefield protection districts, gateway design overlay districts, and historic districts" [22], and the Chart 1 endnotes add that "no structure shall exceed the maximum height requirements denoted in the Airport Overlay District" [35].
  • Fire access. Above 30 feet, the IFC requires an aerial apparatus road 26 feet wide, 15 to 30 feet from one entire side of the building, in D105 of the 2018 edition [5] and Section 503.1.4 of the 2024 edition [32]. Overhead utility and power lines may not sit over that road or between it and the building [5].
  • Parking. On September 18, 2024 the Commission required "the construction of all parking areas depicted on the site plan with the initial development" [46], so the plan shows only the parking the first phase builds.
  • Sewer. A 2022 approval was conditioned so that no building permits would issue "until sanitary sewer upgrades were constructed and completed in this area" [47].
  • Stormwater notes. The checklist's standard notes require a Stormwater Fee Credit Application before the building permit, and an engineer's certification of the stormwater facilities, given to the Director of the Murfreesboro Water Resources Department, before the certificate of occupancy [22].
  • Record. A 65,000 sq ft, 4-story Fairfield by Marriott on 2.69 acres (MU and GDO-1) cleared initial design review 5-0 on December 18, 2024 [6]. A 124-room, 5-story hotel at North Church Lot 21 (CH and GDO-1), developed by Vision Hospitality Group, cleared initial design review 6-0 on July 15, 2026, and the minutes record that "no one had signed up to speak" [7]. The Commission meets on the third Wednesday at 1:00 pm [48].
  • Outside the city limits. The Rutherford County Regional Planning Commission's 2014 site plan checklist asks for the "Stamp and name of the registered engineer, architect, or surveyor preparing the plan", and for an erosion and sediment control plan, SWPPP and water quality and quantity calculations "If over 15,000 sq ft of impervious area or over 1 acre of disturbance"; it does not govern parcels inside the city [49].

The Murfreesboro select-service hotel model project carries the full approval path, standards, comparable approvals, cost benchmarks and submittal anatomy. This page does not repeat them.

Nashville: Specific Plan zoning

Nashville is a consolidated city-county. Its primary site plan process is Specific Plan (SP) rezoning followed by a Final Site Plan, and in an SP district the plan is the zoning:

ItemMetro Nashville
Specific PlanThe site plan is the zoning; all preliminary SP conditions must be satisfied before a building permit [50]
Who decidesSPs are adopted by Metro Council and reviewed by the Planning Commission [51]; the Final Site Plan is approved by the Planning Department [50]
OverlaysThe Downtown Code and the UZO overlays apply in their areas [51]
Final site plan10 copies; "A capacity study/permit will be required with the final site plan application" (Metro Water Services); landscape plan at permit [50]
Review portalePlans since September 8, 2025: "one set of plans that will be reviewed concurrently by all permitting departments" [52]
Planning CommissionApproves, conditions or disapproves subdivisions after staff recommendation and public hearing; advises Metro Council on zoning [53]
Subdivision regulationsCounty-wide except Belle Meade, Berry Hill, Forest Hills, Goodlettsville and Oak Hill [54]
Code editionMetro Code Supplement 53, codified through BL2025-1141 (December 17, 2025) [55]
Permit site plansSealed by a licensed Tennessee land surveyor or engineer [23]

We cite no Nashville hotel-specific dimensional standard. In an SP district the site plan is the zoning [50], so the layout and site data table of the preliminary plan carry the standards the Council acts on. The market behind it: the Nashville-Davidson-Murfreesboro-Franklin metro reached 2,197,416 residents in July 2025, up 34,658 from 2,162,758 in 2024, on Census Bureau data republished by FRED [56]. The Nashville-Davidson balance counted 721,074 residents, up 9,244 [57]. Davidson County posted the state's largest population gain in 2025, 9,821 people (1.3%), with Rutherford, home to Murfreesboro, second at +6,266 and Wilson third at +4,693 [58]. Statewide, Tennessee added 63,785 residents in 2025 after a record single-year gain of more than 98,200 in 2024 [59].

Franklin and Williamson County

Franklin, named in the metro's title, publishes its fees and review steps, which makes it the third documented local layer for a hotel in Middle Tennessee:

ItemFranklin and Williamson County
Site plan review fee$500 base plus $0.02 per sq ft of nonresidential floor area, on the schedule effective 5/1/2019 [60]
Before filingA staff meeting is required before an application is accepted [61]
Site plan attachmentsOwner Affidavit, fire flow test and Water/Sewer Availability Determination [62]
PUD timelineA Development Plan (PUD) typically takes 4.5 to 5 months through BOMA if all steps are met on time [61]
Williamson CountyElectronic plan review through IDT Plans for all Regional Planning Commission applications; TCA 5-1-137 requires county departments to justify development fees exceeding $250 [63]

The Tennessee hotel record

ProjectProgramStatus
Fairfield by Marriott, Murfreesboro65,000 sq ft, 4 stories, 2.69 acresInitial design review approved 5-0, December 18, 2024 [6]
Fairfield by Marriott, exterior architecture modification65,000 sq ft, 4 stories, 2.68 acresApproved 6-0, October 15, 2025 [45]
North Church Lot 21, Murfreesboro (Vision Hospitality Group)124 rooms, 5 storiesInitial design review approved 6-0, July 15, 2026 [7]
Caption by Hyatt Chattanooga Downtown (3H Group)123 roomsOpened end of March 2026 [64]
Embassy Suites downtown Chattanooga (Vision Hospitality Group)184 rooms, $54MOpened September 2025 [65]

For how these programs compare with brand prototypes, see hotel site size by prototype.

What the preliminary plan carries, and what the engineer of record adds

Item (Murfreesboro checklists)Preliminary site planEngineer or architect of record
Name, address and telephone number of the person who prepared the site plan [22]YesReplaced at formal submittal
Location and arrangement of proposed structures, and their height in stories and feet [22]YesDimensions to the surveyed boundary; architect confirms height
Present and proposed zoning, adjoining zoning, overlays, proposed use [22]YesCertified flood data
Table of required minimum setbacks per Chart 2, with its footnotes [22]Yes, in the site data tableVerifies
Parking and loading per Section 26 [22]Yes, with yield and parking tableFinal striping
EV Capable, EV Ready and installed spaces [22]Count and locationElectrical design
Curbs [22]ConceptDetailed geometry
Drainage retention or detention areas [22]Area reservation onlySealed calculations and inverts
Standard stormwater notes: fee credit application, engineer's certification [22]Placeholder notesEngineer of record
Planting, irrigation with a spigot within 300 ft, tree save zones [66]Concept landscape zonesLandscape architect
Gateway overlay elevationsElevations and a materials percentage tableArchitect of record finalizes

The plans are preliminary, and engineering is done by your engineer of record. For overlay review, the hotel rendering service produces the four-sided elevations and street views the Commission reads alongside the plan. The hotel site plan hub covers the program and layout archetypes; the Tennessee state page covers the other asset classes. Related Tennessee work: the Sevier County RV resort model project and RV park site plans in Tennessee. Background reading: where unsealed site plans are accepted, hotel and motel site plan requirements across the top 30 growth markets and room sizes in newly built hotels. To start a Tennessee hotel plan, send the site.

Frequently asked questions

Do I need an architect or engineer to design a hotel in Tennessee?

Yes, for any hotel of 3 stories or more, or 5,000 sq ft or more gross. TCA 62-2-102(b) exempts only listed occupancies that are both under three stories and under 5,000 square feet [1].

Does a preliminary hotel site plan need a seal in Tennessee?

Board Rule 0120-02-.08 puts the seal on working drawings and plans, and Rule 0120-02-.08(9) requires plans that are not construction documents to be marked as preliminary and not for construction, for review only or draft [19]. The land surveyors' Rule 0820-04-.08(2) excuses preliminary documents from the seal and signature when they carry that statement in large bold letters [21]. Murfreesboro still wants stamped drainage calculations with the formal site plan [22].

Can my engineer simply stamp the preliminary site plan?

No. TCA 62-2-306 bars a registrant from sealing any document not prepared by the registrant or under the registrant's responsibility [11], and the Board's conduct rules bar sealing plans begun by persons not properly registered [20]. The engineer and architect of record take the preliminary plan as the program and layout brief and draw the sealed set under their own responsible charge.

Is a hotel allowed by right in Murfreesboro?

Yes, in the six Chart 1 district columns marked "X" for Hotel; recent approvals confirm CH and MU [34]. Chart 1 makes an "X" use permitted by right subject to site plan review and building permits [35]. An extended-stay brand falls in a narrower row permitted in only two columns [34].

When does a Tennessee hotel site need a state stormwater permit?

When construction disturbs 1 acre or more, or less if it is part of a larger common plan of 1 acre or more [2]. The NOI goes in at least 30 days before land disturbance [3].

What is a Specific Plan in Nashville?

A plan-based zoning district adopted by Metro Council after Planning Commission review. The site plan is the zoning, and all preliminary SP conditions must be satisfied before a building permit [50, 51].

Will a four-story hotel trigger aerial fire apparatus access?

Where the highest roof surface is more than 30 feet above the grade plane, IFC D105 requires an aerial access road 26 feet wide, 15 to 30 feet from the building, parallel to one entire side [5]. The 2024 IFC carries the same values in Section 503.1.4 [32, 33].

Can sewer capacity stop a hotel in Murfreesboro?

Yes. A 2022 approval was conditioned so that the applicant could not obtain building permits until sanitary sewer upgrades in the area were constructed and completed [47].

Sources

  1. 1)Tennessee Code Annotated 62-2-102 (law.justia.com/codes/tennessee/title-62/chapter-2/part-1/section-62-2-102/), Justia. Accessed 2026-08-02.
  2. 2)TDEC Construction General Permit TNR100000 (tnepsc.org/tnr100000.pdf), Tennessee Department of Environment and Conservation. Accessed 2026-08-02.
  3. 3)TDEC Notice of Intent form CN-0940, Tennessee Department of Environment and Conservation. Accessed 2026-10-09.
  4. 4)Appendix A, Zoning, Chart 1 (updated February 28, 2019), City of Murfreesboro. Accessed 2026-10-09.
  5. 5)D105 Aerial Fire Apparatus Access Roads (International Fire Code Appendix D, as adopted in the Lincolnton, NC code), American Legal Publishing. Accessed 2026-10-09.
  6. 6)Minutes of the Murfreesboro Planning Commission, December 18, 2024, City of Murfreesboro. Accessed 2026-10-09.
  7. 7)Minutes of the Murfreesboro Planning Commission, July 15, 2026, City of Murfreesboro. Accessed 2026-10-09.
  8. 8)Tennessee Code Annotated 13-3-413 (law.justia.com/codes/tennessee/title-13/chapter-3/part-4/section-13-3-413/), Justia. Accessed 2026-08-02.
  9. 9)Municipal Planning Commissions (mtas.tennessee.edu/reference/municipal-planning-commissions), University of Tennessee Municipal Technical Advisory Service. Accessed 2026-08-02.
  10. 10)Specific Rules: Plats (ctas.tennessee.edu/eli/specific-rules-plats), University of Tennessee County Technical Assistance Service. Accessed 2026-08-02.
  11. 11)Tennessee Code Annotated ยง 62-2-306 (Tennessee General Assembly), FindLaw. Accessed 2026-10-09.
  12. 12)Tennessee Code Annotated 66-24-116 (law.justia.com/codes/tennessee/title-66/chapter-24/part-1/section-66-24-116/), Justia. Accessed 2026-08-02.
  13. 13)Aquatic Resource Alteration Permit (ARAP) (tn.gov/environment/permits/water/aquatic-resource-alteration-permit--arap-.html), Tennessee Department of Environment and Conservation. Accessed 2026-08-02.
  14. 14)Tennessee 401 certification case study (nawm.org/pdf_lib/401_cert/tennessee_case_study.pdf), National Association of Wetland Managers. Accessed 2026-08-02.
  15. 15)TDOT 2016 Driveway Rules Manual (tn.gov/content/dam/tn/tdot/traffic-engineering/2016_Driveway_Rules_Manual.pdf), Tennessee Department of Transportation. Accessed 2026-08-02.
  16. 16)Highway Entrance Permits (tn.gov/tdot/traffic-design/highway-entrance-permits.html), Tennessee Department of Transportation. Accessed 2026-08-02.
  17. 17)10 Simple Questions: Code Adoption (mtas.tennessee.edu/reference/10-simple-questions-code-adoption), University of Tennessee Municipal Technical Advisory Service. Accessed 2026-08-02.
  18. 18)Statewide Building Standards (mtas.tennessee.edu/reference/statewide-building-standards), University of Tennessee Municipal Technical Advisory Service. Accessed 2026-08-02.
  19. 19)Tenn. Comp. R. & Regs. 0120-02-.08, Seals (Tennessee Board of Architectural and Engineering Examiners), Cornell Legal Information Institute. Accessed 2026-10-10.
  20. 20)Rules of the State Board of Architectural and Engineering Examiners, Chapter 0120-02 (January 2017 revision), Tennessee Secretary of State. Accessed 2026-10-09.
  21. 21)Tenn. Comp. R. & Regs. 0820-04-.08, Seals (Tennessee land surveyor rules), Cornell Legal Information Institute. Accessed 2026-10-10.
  22. 22)Planning Commission Site Plan Review Checklist, Appendix A:44 to 45 (updated February 12, 2026), City of Murfreesboro. Accessed 2026-10-09.
  23. 23)Metro Drawing Requirements for Permits, Metropolitan Government of Nashville and Davidson County. Accessed 2026-10-09.
  24. 24)Metro Drawing Requirements for Permits (February 2025 posting), Metropolitan Government of Nashville and Davidson County. Accessed 2026-10-10.
  25. 25)ARAP compensatory mitigation (tn.gov/environment/permit-permits/water-permits1/aquatic-resource-alteration-permit--arap-/permit-water-arap-compensatory-mitigation.html), Tennessee Department of Environment and Conservation. Accessed 2026-08-02.
  26. 26)NPDES Stormwater Construction Permit, Tennessee Department of Environment and Conservation. Accessed 2026-10-09.
  27. 27)Stormwater Management Code, Chapter 27.5 (murfreesborotn.gov/DocumentCenter/View/429/Stormwater-Management-Code), City of Murfreesboro. Accessed 2026-08-02.
  28. 28)USGS Scientific Investigations Report 2005-5281 (pubs.usgs.gov/sir/2005/5281/PDF/SIR20055281.pdf), U.S. Geological Survey. Accessed 2026-08-02.
  29. 29)Stormwater (rutherfordcountytn.gov/stormwater), Rutherford County, Tennessee. Accessed 2026-08-02.
  30. 30)The Ins and Outs of Fire Department Access, TERP Consulting. Accessed 2026-10-10.
  31. 31)Appendix D, Fire Apparatus Access Roads, 2003 International Fire Code, International Code Council. Accessed 2026-10-10.
  32. 32)Aerial Fire Apparatus Access Roads (International Code Council text), UpCodes. Accessed 2026-10-10.
  33. 33)Oregon Fire Code Applications Guide, Oregon Fire Code Metro Code Committee (City of Forest Grove). Accessed 2026-10-10.
  34. 34)Ordinance 24-O-40 amending Murfreesboro City Code Appendix A, Chart 1, City of Murfreesboro. Accessed 2026-10-09.
  35. 35)Appendix A, Zoning, Chart 1 (updated February 12, 2026), City of Murfreesboro. Accessed 2026-10-10.
  36. 36)Appendix A: Zoning Ordinance, 2026 edition, City of Murfreesboro. Accessed 2026-10-09.
  37. 37)Zoning Ordinance, 2019 edition, City of Murfreesboro Planning Department. Accessed 2026-10-10.
  38. 38)Zoning Inquiries, City of Murfreesboro. Accessed 2026-10-10.
  39. 39)Current Planning Process, City of Murfreesboro. Accessed 2026-10-09.
  40. 40)Current Planning, City of Murfreesboro. Accessed 2026-10-09.
  41. 41)Minutes of the Murfreesboro Planning Commission, January 14, 2020, City of Murfreesboro. Accessed 2026-10-09.
  42. 42)Minutes of the Murfreesboro Planning Commission, September 18, 2019, City of Murfreesboro. Accessed 2026-10-09.
  43. 43)Minutes of the Murfreesboro Planning Commission, July 21, 2021, City of Murfreesboro. Accessed 2026-10-09.
  44. 44)Minutes of the Murfreesboro Planning Commission, October 18, 2023, City of Murfreesboro. Accessed 2026-10-09.
  45. 45)Minutes of the Murfreesboro Planning Commission, October 15, 2025, City of Murfreesboro. Accessed 2026-10-10.
  46. 46)Minutes of the Murfreesboro Planning Commission, September 18, 2024, City of Murfreesboro. Accessed 2026-10-09.
  47. 47)Murfreesboro Planning Commission agenda, March 2, 2022, City of Murfreesboro. Accessed 2026-10-09.
  48. 48)Planning Commission, City of Murfreesboro. Accessed 2026-10-09.
  49. 49)Rutherford County Regional Planning Commission site plan review checklist (2014), Rutherford County, Tennessee. Accessed 2026-10-10.
  50. 50)Specific Plan Application (form dated 11/05/2019), Metro Nashville Planning Department. Accessed 2026-10-09.
  51. 51)Understanding the Zoning Code, Metro Nashville Codes. Accessed 2026-10-10.
  52. 52)Apply for Electronic Submission of Project Plans Review, Metro Nashville Codes. Accessed 2026-10-09.
  53. 53)Planning Commission (nashville.gov/departments/planning/boards/planning-commission), Metropolitan Government of Nashville and Davidson County. Accessed 2026-08-02.
  54. 54)Subdivision Regulations (nashville.gov/departments/planning/land-development/subdivision-regulations), Metro Nashville Planning Department. Accessed 2026-08-02.
  55. 55)Code of Ordinances, Metropolitan Government of Nashville and Davidson County, Municode. Accessed 2026-10-09.
  56. 56)Resident Population in Nashville-Davidson-Murfreesboro-Franklin, TN (MSA), FRED series NVLPOP, U.S. Census Bureau via Federal Reserve Bank of St. Louis. Accessed 2026-10-10.
  57. 57)Population Growth Holds Steady in Midsized Cities Amid Widespread Slowdown (Vintage 2025 city and town estimates), U.S. Census Bureau. Accessed 2026-10-10.
  58. 58)Davidson holds as Tennessee's fastest-growing county in 2025 (tnsdc.utk.edu/2026/03/30/davidson-holds-as-tennessees-fastest-growing-county-in-2025/), Tennessee State Data Center, University of Tennessee. Accessed 2026-08-02.
  59. 59)TSDC: Tennessee's biggest growth story may be Cookeville (ttc.tml1.org/2026/04/08/tsdc-tennessees-biggest-growth-story-may-be-cookeville), Tennessee Town and City, Tennessee Municipal League. Accessed 2026-08-02.
  60. 60)Application fees (franklintn.gov/government/departments-k-z/planning-and-sustainability/submit-an-application/application-fees), City of Franklin, Tennessee. Accessed 2026-08-02.
  61. 61)Development review (franklintn.gov/government/departments-k-z/planning-and-sustainability/development-review), City of Franklin, Tennessee. Accessed 2026-08-02.
  62. 62)Application user guide: site plan (franklintn.gov/government/departments-k-z/planning-and-sustainability/application-user-guide/site-plan), City of Franklin, Tennessee. Accessed 2026-08-02.
  63. 63)Planning and Zoning (williamsoncounty-tn.gov/103/Planning-Zoning), Williamson County, Tennessee. Accessed 2026-08-02.
  64. 64)Hyatt opens first Caption hotel in Chattanooga, Tennessee (hoteldive.com/news/hyatt-opens-first-caption-hotel-chattanooga-tennessee/816306/), Hotel Dive. Accessed 2026-08-02.
  65. 65)Hotel Dive report on Embassy Suites downtown Chattanooga (hoteldive.com), Hotel Dive. Accessed 2026-08-02.
  66. 66)Appendix 2, Murfreesboro Landscape Ordinance Site Plan Review Checklist, City of Murfreesboro. Accessed 2026-10-10.

All states and metros

Start a project

Bring us the site. We draw the first plan.

Send the parcel, the program and anything you already have: a survey, a sketch, a zoning letter. The studio returns a preliminary site plan your engineer of record can build on.

Start a project