Site plans / Car washes / Texas

Car wash site plans in Texas

Texas reaches a car wash through a short state layer (TCEQ for construction stormwater and fuel tanks, TxDOT for frontage access, the Legislature for plats and moratoria) and leaves use, stacking and separation to each city. This page sets out both layers for a developer drawing a Texas site.

Last reviewed

Frisco residential separation (DFW benchmark)
250 ft from residential zoning for vacuums, pump islands and other automotive structures [1]
Frisco stacking (DFW benchmark)
6 per full-service bay, 3 per self-service automated bay [2]
Texas tank registration fee
$0 since September 1, 2007 [3]
TCEQ construction stormwater
TXR150000 coverage when construction disturbs an acre or more [4]
Moratorium notice (HB 2559)
Not later than the 30th day before a hearing; final adoption by a three-fourths vote [5]

A thin state layer and decisive cities

Texas counties have no general zoning power: Local Government Code § 232.101(b) bars a commissioners court from regulating the use of buildings or property for business purposes, so an unincorporated site answers to county platting and infrastructure rules under Chapter 232 rather than to a use table [6]. Inside city limits, use permission, stacking, separation and noise are written city by city, and in the DFW suburbs most of them are settled through a Specific Use Permit heard by a planning commission and a city council. A Texas car wash site plan therefore starts with two questions: which state permits the site triggers, and which city code governs the parcel. The Texas state page covers the wider approval system.

State layerRuleWhat it means on the plan
Construction stormwaterTCEQ renewed TXR150000 effective March 5, 2023; coverage applies where construction discharges stormwater to surface water and disturbs an acre or more; small construction is 1 to less than 5 acres, large is 5 acres or more; the permit expires March 5, 2028 [4, 7]The engineer of record prepares the stormwater plan; the site data table carries the acreage
Coverage screeningTCEQ guidance RG-434 points builders to construction general permit screening before construction [8]Screening happens before grading starts
Fuel tanks, if fuel is addedTCEQ Petroleum Storage Tank program under 30 TAC Ch. 334; Texas runs an EPA-approved program (40 CFR §282.93) [3, 9]Tank field, fill and vent locations on the layout
Driveways on frontage roadsTxDOT Access Management Manual Table 2-1 sets spacing by posted speed [10]Fixes how many driveways the frontage can hold
PlatsA city approves, approves with conditions or disapproves a plat within 30 days after filing, with extensions of up to 30 days each on the applicant's written request (LGC 212.009) [11]; HB 3699 (2023) removed "plan," including site plans, from that approval clock [12]The plat runs on the statutory clock; the SUP and site plan run on the city calendar
CompletenessHB 3699 added LGC 212.0081: a city publishes a checklist, and an application containing every listed item is considered complete [13]Draw to the published list
MoratoriaHB 2559 (2025) amends Local Government Code § 212.134: notice not later than the 30th day before a hearing, two public hearings, final adoption by a three-fourths vote [5, 14, 15]A city pause needs notice and hearings
AccessibilityProjects with estimated construction cost of $50,000 or more register with TDLR and get Registered Accessibility Specialist review of the construction documents (16 TAC 68.50) [16, 17]A separate review track beside the building permit

Wash water is a city utility question

The International Carwash Association's industry research reports that "Greater than 99 percent of professional car washes discharge effluent to a sanitary sewer" [18], so the city's sewer use or plumbing rules set the pretreatment device. Aubrey (Ch. 13, Art. 13.06) shows the Texas form: grit interceptors and oil-water separators "installed and inspected prior to issuance of a certificate of occupancy," a 90-day default pumping interval, full evacuation at least every 180 days, and pump-out manifests [19]. Mansfield writes the waste side into its utility rules: a car wash "must have all liquid waste material removed by a liquid waste transporter who holds a valid permit from the City of Mansfield," and each grease or grit trap pumped "must be fully evacuated in accordance with 30 Texas Administrative Code § 312.143" [20]. For how reclaim systems change the equipment room and the budget, see the post on water conservation in car wash design.

Fuel add-ons: the Texas tank layer

A wash with fuel, or a c-store with a wash bay, adds the TCEQ Petroleum Storage Tank program, and Texas charges no annual registration fee for it [3].

ItemTexas rule
Annual registration fee$0: "As of September 1, 2007, petroleum storage tank owners no longer get charged registration fees" [3]
Construction noticeAt least 30 days before UST construction (30 TAC 334.6) [3]
RegistrationWithin 30 days of initial delivery [21]
Delivery certificateRenewed annually, at least 30 days before it expires [21]
Edwards Aquifer zones$650 per tank facility plan fee [22]
Installer licensingContractor registration $232; On-site Supervisor License $111 [23]; the installer or on-site supervisor license number goes on Form TCEQ-00724 [24]

San Antonio adds a local tank layer over the aquifer: a SAWS fee applies to USTs in the recharge and transition zones (UDC Sec. 35-521) [25], and the ERZD overlay restricts uses with production or storage of hazardous materials (UDC Sec. 35-332) [26].

Dispenser setbacks come from the fire code a city has adopted, and island spacing from brand prototypes. The gas station site plan hub sets out the model code distances, the gas station site plans in Texas page covers the state fuel layer, and the Waller County truck stop model project covers diesel programs on Texas frontage roads.

Frontage access is a Texas-specific layout driver. TxDOT's Table 2-1 sets driveway spacing by speed, rising to 425 / 510 ft (one-way / two-way) at 50 mph or more [10]. Near an interchange, the Roadway Design Manual recommends a minimum of 1,750 ft (urban) or 925 ft (rural) from an exit ramp to the downstream intersection [27]. On a short frontage, that spacing often decides whether the stacking lane and the exit share one driveway or get two.

DFW city standards

Across the DFW suburbs a tunnel wash is usually a discretionary use, and the Dallas-Fort Worth metro page maps the jurisdictions. The Mansfield express car wash model project walks through one Specific Use Permit (SUP) in full, including the seven findings in §155.080(F) [28]. The table sets the neighboring rules side by side.

CityHow the use is allowedStackingResidential separation and orientation
Frisco (DFW benchmark)SUP, completed "in the same manner as an application for rezoning" (Ch. 63 §2.05.02) [29]Benchmark: 6 per full-service bay and 3 per self-service automated bay (§4.04) [2]; all stacking contained on the site (§6.15.01) [30]Benchmark: 250 feet from any residential zoning district for buildings, pump islands, vacuums, outdoor speakers and fuel tanks (§4.21) [1]
Fort WorthCUP for automated washes within 200 feet of residential (Fort Worth Ord. 25514-05-2022) [31]Not statedFort Worth §5.108: no drying or vacuuming within 25 feet of a residential district; no dryer facing residential uses; 6 ft screening wall along residential lines [31, 32]
Dallas"SUP may be required" in several districts; residential adjacency review in many planned development districts (Sec. 51A-4.210(b); PD 535, PD 369) [33, 34, 35]Not statedResidential adjacency review
Mansfield"S" use in the §155.054 use table [36]Tested under SUP finding (4), driveways and parking [28]No "obnoxious conditions perceptible at the abutting property lines" (§155.099(B)(17)) [37]
McKinneySUP required in "C1" Commercial Neighborhood [38]; in BN, an SUP "only in connection with an auto fuel sales facility" for a "fully automated facility, which will accommodate only one vehicle at a time" [39]Not statedNot stated
Celina"Auto wash, full-service" is S in C, MU and the PRO/CCO overlay (Art. 14.03, Table 2) [40]Not statedNot stated
Cedar HillNot stated3 per automated bay plus 1 exit space; full-service 4 per vacuum or gas lane (Zoning Art. 5) [41]Not stated

Frisco has four rules to read before a plan is drawn. Council may impose conditions "which shall be complied with by the owner or grantee before a certificate of occupancy may be issued," and the Board of Adjustment "shall not have jurisdiction to hear, review, reverse, or modify any decision" on an SUP land use, so a variance is no route around a condition (§6.15.01) [30]. SUP requirements are "attached to the Preliminary Site Plan or Site Plan drawing(s)" that the commission and council approve, so the plan is the binding exhibit [30], and a significant enlargement or modification without a separate SUP is grounds to rescind it [42]. A Planned Development controls where one exists: "For any property zoned Planned Development (PD), the PD takes precedence over the zoning ordinance" [43]. And the code moves: Ordinance 2026-07-44 (adopted July 7, 2026) amended Ch. 63 §3 Land Uses and §7 Definitions, and the Preston Road and Tollway overlays can prohibit uses outright [44]. Corridor sites also check the US 380 Overlay Design District, adopted by Ord. 2022-01-01 [45].

One Frisco filing shows the pad-site pattern. On May 27, 2025, P&Z reviewed PSP25-0014, an HEB with "accessory gas pumps with a car wash on one lot on 22.8± acres" in PD-254-Retail [46].

Fort Worth writes orientation into code: "No car wash dryer shall face a residential district or use" [31]. Mansfield states its rule as a performance test at the abutting property lines [37], which applicants answer with screen walls and vacuum placement drawn on the plan.

Mansfield's own numbers frame the model project. The SUP fee is $2,500 plus $100 per acre, capped at $7,500 (OR-2379-24) [47]. An SUP lapses unless construction or use is substantially underway within 2 years (§155.080(H)) [28]. The South Mansfield Form-Based District lists "Car wash" among the uses not allowed in any transect zone (§155.073) [48]. The council denied SUP25-004, a 2.6-acre tunnel site at 1561 E. Broad St, on April 13, 2026 [49]. In ZC#24-013 (1850 E. Broad St), a self-service wash beside an elementary school and day care, the staff report called the uses "considered noxious when adjacent to school type uses based on noise and traffic" [50].

Houston, San Antonio, Austin and the rest of Texas

Houston has no use zoning; the entitlement is a development plat, required for new construction or an exterior enlargement in the city and its ETJ (Sec. 42-22) [51]. The Houston Permitting Center's development plat application (PDD1003) calls for a detailed site plan in 2 copies [51]. The city's parking table, Sec. 26-492 (Class 9), sets 2.5 spaces per bay or stall for automated washes and 1.0 per bay for other washes [52]. Under the Chapter 42 building line rules, a retail center on a major thoroughfare of 80 feet or less of right-of-way may get a 5 foot or zero building line (Sec. 42-150) [53]. Flood elevation is the Houston site factor: under Chapter 19, effective September 1, 2018, new structures in the 100-year or 500-year floodplain sit at the 500-year elevation plus 2 feet [54], and 31% of the city lies in the 100-year floodplain [55]. The Houston metro page carries the wider process.

North San Antonio sits over the Edwards Aquifer recharge zone, where the ERZD overlay applies to all base zones and is appended to the district name as a suffix (UDC Sec. 35-521) [25]. SAWS caps impervious cover at 15% for single-family, multifamily and commercial sites in Category 3 of the ETJ recharge zone, and its Category 2 example allows 65% for commercial [56]. The aquifer protection site development plan must show scale, north point, floodplain preservation areas, recharge features, an erosion control plan and the impervious cover percentage (UDC Sec. 35-B105) [57]. City Code Ch. 34 allows no impervious cover in floodplain buffer zones and a 10% maximum in the drainage area buffer zone [58]. TCEQ reviews an administratively complete Edwards application in 90 days (30 TAC 213.4(e)) [59]. The San Antonio metro page sets out the city process.

The 30 TAC Chapter 213 program reaches beyond San Antonio: it requires a Water Pollution Abatement Plan in the recharge zone and a Contributing Zone Plan upstream, in Medina, Bexar, Comal, Kinney, Uvalde, Hays, Travis and Williamson counties [60]. In the Austin metro's Travis, Williamson and Hays counties, regulated activities need TCEQ approval before soil is disturbed [60, 61]. The Austin metro page covers the city's own review.

Outside the big four metros, the codes are just as specific. Tyler (UDC Sec. 10-389) sets automatic wash stacking at 3 per service position plus 1 after and attendant washes at 10 per wash line plus 6, in 9 x 20 ft spaces, and keeps service points and stacking lanes 80 ft from residential districts and 30 ft from office and mixed use, with a "B" bufferyard [62]. Corpus Christi (UDC Table 7.2.6.A) requires 4 spaces per automated stall, measured from the entrance to the wash bay, and 3 for hand-operated stalls, and the city's TRC may require more [63].

How the Texas numbers compare

Texas codes count car wash spaces in different units: Houston's parking table 2.5 per automated bay or stall [52], Cedar Hill 3 per automated bay plus 1 exit space [41], Tyler 3 per service position plus 1 [62], Corpus Christi 4 per automated stall [63], and Frisco, the regional benchmark, 6 per full-service bay [2]. Read the wording before counting lanes: a per-lane or per-position rule grows with a second pay lane, a per-bay rule does not. Outside Texas the units shift again: Mayfield Heights, Ohio counts 8 per vehicle entrance (§1171.09(e)) [64], and Tallmadge, Ohio counts 10 per lane at 8 x 20 ft (Ord. 2023-82) [65].

On separation, the Texas figures measure different things. Frisco's 250 ft benchmark runs from residential zoning to every automotive structure [1]; Tyler's 80 ft runs to service points and stacking lanes [62]; Fort Worth's 25 feet governs drying and vacuuming only, and its 200 feet is a permit trigger rather than a setback [31, 32]. Tallmadge sets 500 ft from residential use, parks, trails, schools and places of worship [65].

The moratorium wave reaches Texas

Car wash moratoria have spread across Alabama, Ohio and California, and the car wash hub tracks that national record; the car wash and gas station regulations by state guide compares the state layers. In Texas, The Monitor reported that Mission's council unanimously approved Ord. 5794 on March 24, 2026: a 180-day moratorium, retroactive to pending applications, that cited drought [66].

The Legislature now sets the procedure. HB 2559 (2025), effective September 1, 2025, amends Local Government Code § 212.134 to require notice "not later than the 30th day before the date of a hearing, rather than on the fourth day," and requires the governing body "to hold two public hearings" [14]. Per the enrolled bill text, final adoption requires a three-fourths vote [5], and the Texas Municipal League reads it as "a three-fourths vote of all council members on second reading" [15].

In DFW the pressure shows up as denials. In Richardson, Clearwater Express (about 5,000 sf, one tunnel, 20 outdoor vacuum bays) sat behind an existing fuel center and beside a child care facility; the City Plan Commission approved it 3-2, and the council denied it on Oct 9, 2023, by 6-1, with noise, neighborhood opposition and water use cited; at the hearing the applicant cited 16 gal per vehicle [67, 68]. In Red Oak, the Waxahachie Daily Light reported a 4-0 council denial at the Aug. 10 meeting of a detail car wash SUP (ordinance 26-020), after a 2-3 Planning and Zoning Commission vote on April 27, with traffic, noise, light, parking, fire access and sales-tax corridor goals cited [69]. Mansfield's council denied SUP25-004 on April 13, 2026 [49]; the model project sets out the record. Two layout answers recur, and both are written into nearby codes: point the dryer away from homes, as Fort Worth requires [31], and hold the whole queue on the site, as Frisco requires [30].

What the preliminary plan carries, and what the engineer of record adds

On the preliminary site planAdded by the engineer of record
Tunnel position and dryer exit orientationGrit trap and interceptor sizing, sewer connection
Stacking lanes counted to the city rule, bypass, pay stationsGrading, drainage and detention design
Vacuum field, equipment room, screen wallsConstruction stormwater coverage and plan
Driveways placed against TxDOT or city spacingTxDOT access permit design
Separation lines from residential zoningUST system design and TCEQ notices through a licensed installer
Site data table: acreage, zoning, impervious cover, parking and stacking required against providedSealed civil, structural and MEP sets

In Mansfield the metes and bounds description must be "signed and sealed by a registered surveyor" (§155.080(D)(3)) [28]. Texas exempts a privately owned commercial building of no more than 2 stories or 20,000 sq ft from the architect requirement (Occupations Code 1051.606(a)(4)) [70, 71], and the TDLR accessibility review runs on its own track [16]. The preliminary site plan is the exhibit the hearing reads and the base the engineer of record builds the sealed set on. The preliminary vs final site plan guide explains that handoff, and car wash renderings show a council the dryer side and the screen wall from the nearest home.

For the Florida rules, see car wash site plans in Florida. For market context, read car wash development in 2026. To start a Texas site, send the parcel.

Frequently asked questions

Who sets the grit trap rules for a Texas car wash?

The city's sewer and plumbing rules. Aubrey requires grit interceptors and oil-water separators "installed and inspected prior to issuance of a certificate of occupancy," with a 90-day default pumping interval and full evacuation at least every 180 days [19]. Mansfield requires car wash liquid waste to be removed by a transporter holding a city permit, with each trap pumped "fully evacuated in accordance with 30 Texas Administrative Code § 312.143" [20].

Is there a Texas fee to register fuel tanks at a car wash?

No annual registration fee: "As of September 1, 2007, petroleum storage tank owners no longer get charged registration fees." TCEQ must be notified at least 30 days before UST construction (30 TAC 334.6) [3], and tanks are registered within 30 days of initial delivery [21]. Edwards Aquifer zones add a $650 per tank facility plan fee [22].

Is a car wash allowed by right in Frisco?

No. Uses marked "S" need a Specific Use Permit, which "shall be completed in the same manner as an application for rezoning" (Ch. 63 §2.05.02) [29]. The Board of Adjustment has no jurisdiction to modify an SUP land use decision (§6.15.01) [30].

How far from homes must a Frisco car wash be?

Frisco's code is the DFW benchmark for separation: buildings, gasoline pump islands, vacuums, outdoor speakers, fuel storage tanks and other automotive structures must sit a minimum of 250 feet from any residential zoning district (§4.21) [1].

Can a Texas city pass a car wash moratorium?

Yes, by the HB 2559 procedure: notice "not later than the 30th day before" a hearing, two public hearings, and final adoption by a three-fourths vote [5, 14, 15]. The Monitor reported that Mission's council unanimously approved Ord. 5794, a 180-day moratorium retroactive to pending applications, on March 24, 2026 [66].

Does Houston need a site plan for a car wash?

Houston has no use zoning, but it requires a development plat, which the Permitting Center defines as a site plan approved under Sec. 42-22, for new construction in the city and its ETJ [51]. Parking follows Sec. 26-492: 2.5 spaces per bay or stall for automated washes [52].

Sources

  1. 1)Frisco Zoning Ordinance, Subsection 4.21: Supplementary Regulations, City of Frisco, Texas (eCode360). Accessed 2026-10-09.
  2. 2)Frisco Zoning Ordinance, Subsection 4.04: Off-Street Parking and Loading Requirements, City of Frisco, Texas (eCode360). Accessed 2026-10-09.
  3. 3)Petroleum Storage Tanks Registrations: Am I Regulated?, Texas Commission on Environmental Quality. Accessed 2026-10-09.
  4. 4)Stormwater General Permit for Construction Activities (TXR150000), Texas Commission on Environmental Quality. Accessed 2026-10-10.
  5. 5)H.B. 2559 (2025), enrolled bill text, Texas Legislature.
  6. 6)Local Government Code § 232.101(b), county regulatory authority (statute text quoted via millercreekrvpark.com, secondary), Texas Legislature. Accessed 2026-10-10.
  7. 7)Stormwater TPDES Construction General Permit (CGP, TXR150000) Overview, Texas Commission on Environmental Quality. Accessed 2026-10-10.
  8. 8)Regulatory Guidance RG-434, Texas Commission on Environmental Quality. Accessed 2026-10-09.
  9. 9)40 CFR Part 282, Approved Underground Storage Tank Programs, eCFR. Accessed 2026-10-09.
  10. 10)Access Management Manual, Chapter 2, Section 3: Frontage Roads (Table 2-1), Texas Department of Transportation. Accessed 2026-10-09.
  11. 11)Local Government Code § 212.009 (Texas Legislature, via FindLaw), Texas Legislature. Accessed 2026-10-10.
  12. 12)Legislative update, September 1, 2023, Number 35 (HB 3699), Texas Municipal League. Accessed 2026-10-10.
  13. 13)House Bill 3699, Senate Amendments Section-by-Section Analysis, Texas Legislature. Accessed 2026-10-10.
  14. 14)Senate bill analysis, H.B. 2559 (2025), amending Local Government Code § 212.134, Texas Legislature.
  15. 15)Summary of H.B. 2559 (Aug 29, 2025), Texas Municipal League.
  16. 16)Elimination of Architectural Barriers at a glance, Texas Department of Licensing and Regulation (via Issuu). Accessed 2026-10-10.
  17. 17)16 TAC Chapter 68, Elimination of Architectural Barriers (rule text via corada.com, secondary mirror), Texas Department of Licensing and Regulation. Accessed 2026-10-10.
  18. 18)Water Effluent and Solid Waste Characteristics in the Professional Car Wash Industry, International Carwash Association. Accessed 2026-10-09.
  19. 19)Aubrey Code Ch. 13, Art. 13.06: Grease Traps/Interceptors, Grit Interceptors and Oil/Water Separators, City of Aubrey, Texas (eCode360). Accessed 2026-10-09.
  20. 20)Liquid Waste Transportation and Disposal, City of Mansfield, Texas. Accessed 2026-10-10.
  21. 21)RG-475b, Installing a New or Replacement Underground Storage Tank, Texas Commission on Environmental Quality. Accessed 2026-10-09.
  22. 22)Underground Storage Tank Facility Plan (Edwards Aquifer), Texas Commission on Environmental Quality. Accessed 2026-10-09.
  23. 23)UST contractor registration and on-site supervisor licensing, Texas Commission on Environmental Quality. Accessed 2026-10-09.
  24. 24)Form TCEQ-00724, Underground Storage Tank Registration and Self-Certification, Texas Commission on Environmental Quality. Accessed 2026-10-10.
  25. 25)San Antonio Unified Development Code § 35-521, Edwards Aquifer Recharge Protection (via elaws.us), City of San Antonio, Texas. Accessed 2026-10-10.
  26. 26)San Antonio Unified Development Code § 35-332, ERZD Edwards Recharge Zone District (via elaws.us), City of San Antonio, Texas. Accessed 2026-10-10.
  27. 27)Roadway Design Manual § 15.8, Frontage Road Turnarounds and Intersection Approaches, Texas Department of Transportation. Accessed 2026-10-09.
  28. 28)Mansfield Code § 155.080, Specific Use Permit, City of Mansfield, Texas (American Legal Publishing). Accessed 2026-10-09.
  29. 29)Frisco Zoning Ordinance, Subsection 2.05: Special Zoning Districts, City of Frisco, Texas (eCode360). Accessed 2026-10-09.
  30. 30)Frisco Zoning Ordinance § 6.15.01, Specific Use Permit (SUP) Application and Review, City of Frisco, Texas (eCode360). Accessed 2026-10-09.
  31. 31)Ordinance No. 25514-05-2022, amending the Zoning Ordinance (car washes), City of Fort Worth, Texas. Accessed 2026-10-09.
  32. 32)Fort Worth Zoning Ordinance § 5.108, Car Wash, City of Fort Worth, Texas (American Legal Publishing). Accessed 2026-10-09.
  33. 33)Dallas Development Code, Chapter 51A (use regulations excerpt), City of Dallas, Texas. Accessed 2026-10-10.
  34. 34)Article 535, PD 535, C.F. Hawn Special Purpose District No. 3, City of Dallas, Texas. Accessed 2026-10-10.
  35. 35)Article 369, PD 369, City of Dallas, Texas. Accessed 2026-10-10.
  36. 36)Mansfield Code § 155.054, Permitted Uses, City of Mansfield, Texas (American Legal Publishing). Accessed 2026-10-09.
  37. 37)Mansfield Code § 155.099, Special Conditions, City of Mansfield, Texas (American Legal Publishing). Accessed 2026-10-09.
  38. 38)File 20-0012SUP2, Oasis Car Wash Specific Use Permit, City of McKinney, Texas (Legistar). Accessed 2026-10-09.
  39. 39)Chapter 146, Zoning Regulations, City of McKinney, Texas. Accessed 2026-10-10.
  40. 40)Celina Zoning, Part 1: Schedule of Uses (Art. 14.03, Table 2), City of Celina, Texas (eCode360). Accessed 2026-10-09.
  41. 41)Cedar Hill Zoning Ordinance, Article 5, Development Standards (via Municode), City of Cedar Hill, Texas. Accessed 2026-10-10.
  42. 42)Frisco Zoning Ordinance, Subsection 6.15: Specific Use Permit (SUP) Application and Review, City of Frisco, Texas (eCode360). Accessed 2026-10-09.
  43. 43)Zoning Verification & Event Letters, City of Frisco, Texas. Accessed 2026-10-09.
  44. 44)Frisco Zoning Ordinance: Conditional Development Standards (use chart, as amended by Ordinance 2026-07-44), City of Frisco, Texas (eCode360). Accessed 2026-10-09.
  45. 45)Ordinance No. 2022-01-01, US 380 Overlay Design District, City of Frisco, Texas. Accessed 2026-10-09.
  46. 46)Planning & Zoning Commission meeting agenda, May 27, 2025, City of Frisco, Texas. Accessed 2026-10-09.
  47. 47)Ordinance No. OR-2379-24, Master Fee Schedule, City of Mansfield, Texas. Accessed 2026-10-09.
  48. 48)Mansfield Code § 155.073, S, South Mansfield Form-Based Development District, City of Mansfield, Texas (American Legal Publishing). Accessed 2026-10-10.
  49. 49)Mayor Evans recaps the April 13 City Council meeting, City of Mansfield, Texas. Accessed 2026-10-09.
  50. 50)File 24-6285, ZC#24-013 (1850 E. Broad St), City of Mansfield, Texas (Legistar). Accessed 2026-10-10.
  51. 51)Approval of a development plat, Houston Permitting Center. Accessed 2026-10-10.
  52. 52)Houston Code Sec. 26-492, Parking spaces for certain types of use classifications, City of Houston, Planning and Development. Accessed 2026-10-10.
  53. 53)Houston Code § 42-150, Building line requirement (via elaws.us), City of Houston, Texas. Accessed 2026-10-10.
  54. 54)Floodplain Rules and No Zoning: What Houston Contractors Must Account for in Their Estimates (summarizing Houston Chapter 19), rawmags.com (secondary). Accessed 2026-10-10.
  55. 55)Houston Public Works Chapter 19 Floodplain Ordinance Summary, City of Houston. Accessed 2026-10-10.
  56. 56)Aquifer Protection Ordinance, San Antonio Water System. Accessed 2026-10-10.
  57. 57)San Antonio Unified Development Code § 35-B105, ERZD Documentation (via elaws.us), City of San Antonio, Texas. Accessed 2026-10-10.
  58. 58)San Antonio City Code Ch. 34, Art. VI, Div. 6, Aquifer Recharge Zone and Watershed Protection (via Municode), City of San Antonio, Texas. Accessed 2026-10-10.
  59. 59)Edwards Aquifer application cover page (30 TAC 213.4(e) review time), Texas Commission on Environmental Quality. Accessed 2026-10-10.
  60. 60)Commission work session marked agenda (Edwards Aquifer rules, 30 TAC Chapter 213), Texas Commission on Environmental Quality. Accessed 2026-10-10.
  61. 61)Edwards Aquifer Protection Plans, Texas Commission on Environmental Quality. Accessed 2026-10-10.
  62. 62)Tyler Unified Development Code Sec. 10-389, Drive-Through Stacking Requirements, City of Tyler, Texas (American Legal Publishing). Accessed 2026-10-10.
  63. 63)Corpus Christi Unified Development Code (Table 7.2.6.A), City of Corpus Christi, Texas (encodeplus). Accessed 2026-10-10.
  64. 64)Mayfield Heights Codified Ordinances § 1171.09, Car Washes, City of Mayfield Heights, Ohio (American Legal Publishing). Accessed 2026-10-09.
  65. 65)Ordinance 2023-82, Exhibit A (car wash standards), City of Tallmadge, Ohio. Accessed 2026-10-09.
  66. 66)Mission establishes six-month moratorium on new car wash facilities, The Monitor (myrgv.com). Accessed 2026-10-09.
  67. 67)Richardson car wash project put on hold by City Council, Community Impact (secondary). Accessed 2026-10-09.
  68. 68)Richardson City Council Work Session, October 9th, 2023, Council notes on Substack (secondary). Accessed 2026-10-09.
  69. 69)Red Oak City Council denies Wash Masters specific use permit (ordinance 26-020), Waxahachie Daily Light (secondary).
  70. 70)When to Engage an Architect or Excepted Engineer (flow chart), City of Abilene, Texas. Accessed 2026-10-10.
  71. 71)Occupations Code § 1051.606 (Texas Legislature, via texas.public.law), Texas Legislature. Accessed 2026-10-10.