Case studies / Marinas

Marina with dry stack, Lee County, Florida

A model project used to show how Lee County's rules shape a marina site plan: why every dry rack counts as a slip, which approvals the plan passes through, and what the Development Order submittal asks of it.

Last reviewed

Program
100 to 250 wet slips, 300 to 500 rack dry stack, fuel dock, ship store
Jurisdiction
Unincorporated Lee County: Hearing Examiner recommends, Board of County Commissioners decides [1]
Zoning route
Commercial Planned Development (CPD) rezoning, then a sealed county Development Order [2, 3]
Binding constraint
Manatee Protection Plan slip count, dry racks included (LDC 26-41) [4]
Planned development rezoning
9 months, county average [2]
Development Order fee
$3,000 + $60 per acre [5]

A model marina in unincorporated Lee County

This page works through a model project: a commercial marina with 100 to 250 wet slips, a 300 to 500 rack dry stack, a fuel dock and a ship store, placed in unincorporated Lee County, Florida. It is a model, not a built or permitted marina. It is used here to show how one county's rules shape a marina site plan before anyone engineers it.

Lee County is a sound test because its marina rules are current and on the record. Chapter 26 of the Land Development Code (LDC) was amended by Ordinance 22-24, adopted Sept. 6, 2022, 5-0, and it ties marina location and design to Lee Plan Objectives 128.4 and 128.5 [4]. The Manatee Protection Plan is dated June 17, 2004, was approved June 29, 2004 and was incorporated into the Lee Plan on May 16, 2007 through CPA 2005-41 [6], and Administrative Code AC-13-21 governs the transfer of slip credits [7]. The cities of Fort Myers and Fort Myers Beach run their own processes; the model sits in the unincorporated county, where the Hearing Examiner and the Board of County Commissioners decide [1].

The route is a Commercial Planned Development (CPD) rezoning or CPD amendment, heard first by the Hearing Examiner and decided by the Board, followed by a Development Order under LDC Chapter 10, where all plans are "signed and sealed" (LDC 10-102) [1, 3]. The binding constraint is the slip count set by the Manatee Protection Plan, and the code counts every dry rack in it [4]. Building height and land area come second. For the asset-wide view, see marina site plans, the statewide picture in marina site plans in Florida and site plans in Florida, and for upland racks without water, boat storage site plans.

At a glance

ItemModel project
AssetCommercial marina with dry stack, fuel dock and ship store
Program100 to 250 wet slips; 300 to 500 rack dry stack
Code definitionA facility "which provides a boat ramp with parking for vehicles and trailers, boat slips, dockage, or dry boat storage with a service to place boats in the water" [8]
JurisdictionUnincorporated Lee County: Department of Community Development (DCD), Hearing Examiner, Board of County Commissioners (BOCC) [1]
How the use is allowedA "Marina 34-1862" row in the use tables (Ord. 12-01) [9]; recent marina filings used CPD and MPD rezonings [10]; large projects need planned development zoning as "Developments of County Impact" [2]
Permit setCPD rezoning or amendment, Development Order, Ch. 26 dock permit; FDEP Environmental Resource Permit (ERP) and sovereignty submerged lands lease; USACE Section 10 and 404 permit [4, 2, 3]
Plan overlayLee Plan Policy 1.6.4, Water-Dependent Overlay, mapped on Lee Plan Map 12 [11, 12]; water-dependent policies 128.1.1 and 128.2.1 [6]
AcreageSet by the parcel and its shoreline; the marina filings in the county's review queue are 1.11 acres (Jug Creek) and 1.05 acres (Green Flash) [10]
Approval stagesConcept, zoning, Development Order, state and federal permits, building, close-out

The Lee Plan states the overlay's purpose in one line:

"The Water-Dependent Overlay zone designates shoreline areas where priority will be granted to water-dependent land uses." [11]

The two marina filings in the county's review queue are both planned development rezonings: Jug Creek from IM to MPD and Green Flash from C-1 and CM to CPD [10]. The CPD's master concept plan is where uses, access, buffers and open space are fixed [2], and it is drawn from the preliminary site plan.

Approval path

The county's own figure for the zoning stage is stated plainly: "The average time to complete a planned development rezoning is 9 months, depending on completeness of the application when submitted" [2]. The state and federal clocks are not published as fixed periods; where a source does not give a figure, the table says "not stated".

ApprovalBodyCodeStagePublished feeTimelineSealed, by whom
Pre-application meetingLee County Community DevelopmentDO Guide Sec. 2 [3]ConceptNot statedScheduled on request [3]No; "conceptual plan" accepted [3]
Manatee slip determination and GIS evaluationLee County Natural Resources (Marine Services), 239-533-8109 [13]LDC 26-45(b)(7), 26-71(a)(4), 26-78, 26-79 [4]Concept, before zoningNot statedNot statedNo; county analysis
Comprehensive plan amendment (only if needed)BOCCLee PlanBefore zoningMap amendment of 10 acres or less $1,500; over 10 and under 20 acres $2,000; text $2,500 [5]Not statedNot stated
CPD rezoning or amendment, with deviationsHearing Examiner recommends; BOCC decides [1]LDC 34-145, 34-202, 34-373ZoningRezoning fee not stated; administrative deviation $400 + $75 each additional; variance $700 [5]County average 9 months [2]Not stated; scaled architectural elevations required for dock departures, 34-202(b)(5)d.4 [4]
Development OrderLee County Development ServicesLDC Ch. 10; 10-102; 10-154Site plan$3,000 base + $60 per acre; amendment $775; resubmittal $435, first free [5]Not statedYes: PE, RLA, PSM, architect [3]
Plat (only if subdividing)Lee CountyLDC 10-154(4)Plat$775 + $12 per lot or tract [5]Not statedPSM
ERP and sovereignty submerged lands leaseFDEP, joint application on Form 62-330.060(1)Ch. 62-330, 62-4.050(4)(h), 18-21.011 F.A.C.; s. 253.0346 F.S.StateERP $14,000 for more than 30 new slips [14]; lease rent: greater of 6% of income, the base fee or the minimum fee [15]Lease: "Multi-level review", no fixed clock published [15]Engineer drawings customary
USACE Section 10 and Section 404 Standard PermitUSACE Jacksonville District, Fort Myers Permits SectionRivers and Harbors Act s. 10; Clean Water Act s. 404FederalNot statedNot statedEngineer drawings customary
Water and wastewaterLee County Utilities availability letter; FDEP and FDOH permitsDO Guide item 32 [3]Zoning and DONot statedNot statedLetter: no seal; utility permits: PE
AccessLee DOT, or FDOT driveway and right-of-way permitsDO Guide item 32 [3]DONot statedNot statedPE
Floodplain complianceLee County Floodplain AdministratorLDC Ch. 6 Art. IV (Ords. 15-09, 22-30, 25-09, 26-01) [16]BuildingNot statedNot statedElevation certificate by PSM
Dock and shoreline permitLee County DCDLDC 26-45Building"As established in the applicable county administrative code" [4]Not statedPE or architect (26-45(c)); PSM survey at the Director's discretion (26-45(d)) [4]
Building permit (dry stack, ship store)Lee County BuildingFlorida Building CodeBuildingPlan review $0.10 per sq ft, $525 minimum for a new building [5]; structural inspections $0.15 per sq ft, $500 minimum [5, 17]Not statedArchitect or PE
Fire protection plan; NFPA 303 reviewLocal fire districtLDC 10-154(20); 69A-60.005 F.A.C.DO and buildingNot statedNot statedFire protection engineer customary
Fuel storage tanksFDEPCh. 62-761 and 62-762 F.A.C.BuildingNot statedNot statedNot stated
Certificate of Compliance and certificate of occupancyLee CountyDO Guide Sec. 7 [3]Close-outNot statedNot statedAs-built survey by PSM, 26-45(d)(3) [4]

Four points about the order matter for the plan.

  • The county comes before the state lease. LDC 26-45(b)(7) requires copies of state and federal permits "unless a submerged lands lease is required from the state department of environmental protection, in which case county approval is required first" [4]. The site plan therefore carries the slip layout and riparian geometry through the county before the state looks at the lease area.
  • The Development Order collects the state and federal files. Its submittal lists the state and federal permit applications (USACE, ERP, FDEP fuel tanks, FDOT, FDOH) under LDC 10-154(22) [3]. The table above does not fix the order between the Development Order and those permits.
  • Who decides what. The Hearing Examiner "has final decision-making authority on conventional rezoning applications" and on "special exceptions, variances and administrative appeals." On a planned development rezoning the Examiner only recommends, and the Board holds a second hearing [1].
  • Community meetings. North Fort Myers and other community plan areas require a public information session before the Development Order [3].

The Florida layer over the county process

Chapter 2025-190, Laws of Florida (SB 180), created s. 252.422, F.S. For one year after a hurricane's landfall, it bars "impacted local governments" (counties in a federal disaster declaration wholly or partly within 100 miles of the storm track, plus their municipalities) from adopting moratoria, more restrictive comprehensive plan or land development regulation amendments, or "more restrictive or burdensome procedures concerning review, approval, or issuance of a site plan, development permit, or development order", and it bars raising building permit or inspection fees for 180 days after a hurricane emergency declaration [18]. The law is in litigation: 25 local governments sued in Leon County Circuit Court on September 29, 2025, and a second suit followed in October 2025 [19]. The same rule shapes site plan work across the Tampa and Miami metros.

Florida also sets decision clocks. SB 1080, ch. 2025-177, rewrote the timeframes and refunds in F.S. 125.022 for counties and F.S. 166.033 for municipalities [20, 21]. The schedule runs: completeness review in 30 days, then a decision 120 days after an application is deemed complete where no hearing is needed, or 180 days where a hearing is required, with refunds of 10% to 100% of the fee when the deadlines are missed [20]. "Development permit" and "development order" carry their F.S. 163.3164 meanings and "do not include building permits" [20].

Wind is the third layer. The High-Velocity Hurricane Zone provisions of Florida Building Code Sec. 1620, with their county-specific design wind speeds and Exposure C default, apply to Miami-Dade and Broward [22]. Lee County is not one of them; the envelope rules that bind this plan are the county's flood and freeboard rules below.

Design standards that shape the layout

Every numeric standard below binds the plan view. Lee County's manatee siting table sits in the 2004 Manatee Protection Plan and is applied to each site through the county's slip determination; it is not reproduced here [13].

StandardValueCode
Side setback, multi-slip and marina docks on natural waterbodies25 ft from adjoining side lot lines [4]LDC 26-71(d)(1)
Boat ramp side setback10 ft [4]LDC 26-71(d)(5)
Minimum water depthAt least 4 ft at mean low water in mooring areas, turning basins and the entry and exit paths, plus 1 ft below the deepest draft [4]LDC 26-71(f)(2)
Waterbody setbackCh. 26 structures exempt from the 25 ft waterbody setback [4]LDC 26-47
Benthic survey windowApril 1 to October 31 [4]LDC 26-41
Mangrove replacement3 planted for each 1 removed; 80% survival over 5 years; 3 ft on center [4]LDC 26-77(b)(2)
Seawalls on natural waterbodiesNew or expanded seawalls not allowed [4]LDC 26-75(b)(2)
RiprapMinimum average 12-inch diameter [4]LDC 26-75(d)(2)
Shoreline counted for the slip capOwned or controlled shoreline; shorelines created after Oct. 24, 1989 by dredge and fill excluded [4]LDC 26-41
Manatee siting ratio, Lee CountyNot stated; applied through the county slip determination [13]MPP; LDC 26-79
Slip credit transfersOn-site maximum rounded up; transferable slips rounded down [7]AC-13-21
Dry storage parking1 space per 5 unit stalls [23]LDC Table 34-2020(b), item d
Boat ramp parking10 spaces per boat ramp [23]LDC Table 34-2020(b)
Wet slip parkingGoverned by Note (1) of the table; ratio not stated [23]LDC Table 34-2020(b)
Director parking reductionUp to 10% administratively [23]LDC 34-2020
Outdoor storage screening8 ft facing a residential use or district; 6 ft facing a street [24]LDC 34-3005
Flood elevationBFE + 1 ft of freeboard [25]Lee flood page; Ord. 22-30
Substantial improvement50% of the market value of the structure [25, 26, 27]Ords. 15-09 and 22-30
Dry stack heightSet in the CPD; no by-right figure stated here [28]LDC 34-2174, 34-2175 (Ord. 23-22)
Fuel storageState tank rule applies to aboveground tanks over 550 gallons [29]62-762.301 F.A.C.
Marina sanitationLive-aboard moorage needs public restrooms with sewage disposal and bathing, and a county approved pump-out system [4]LDC 26-116(a)

Screening also binds the upland: commercial outdoor storage sits behind a continuous visual screen at least 8 ft high where a residential use or district can see it, and 6 ft high toward a street right-of-way or easement [24].

The provisions that bind the layout

Racks are slips, LDC 26-41.

"Slip or watercraft-slip means a space designed for the mooring or storage of a single watercraft, regardless of size, which includes wet or dry slips, anchorage, beached or blocked, hoist, parked on trailers, open or covered racks, seawall or the number of parking spaces for boat ramps." [4]

Every non-single-family slip is tested against the plan, LDC 26-71(a)(4).

"Determination of non-single-family slips must be in compliance with the Manatee Protection Plan as defined by section 26-41 and 26-79." [4]

Marina location and design, LDC 26-78.

"Marina locations must be consistent with Lee Plan Objective 128.4 and all of its implementing policies, including the Manatee Protection Plan and Lee County Administrative Code 13-21. Marinas must be designed and constructed in a manner consistent with Lee Plan Objective 128.5 and all of its implementing policies." [4]

Side setback, LDC 26-71(d)(1).

"All multi-slip and marina docking facilities, except boat davits, in or adjacent to natural waterbodies must be set back a minimum of 25 feet from all adjoining side lot lines." [4]

Water depth, LDC 26-71(f)(2). The ordinance requires that "there must be a minimum depth of one foot clearance between the deepest draft of a vessel (with the engine in the down position) and an unvegetated bottom or the top of submerged aquatic vegetation (e.g. seagrasses) at mean low water, with a minimum water depth of at least four feet within mooring areas, turning basins" and the paths into and out of the marina [4].

Shoreline that does not count, LDC 26-41.

"This definition does not apply to shorelines artificially created after October 24, 1989 through dredge and fill activities (such as boat basins or canals)." [4]

No reconfiguration outside the plan, LDC 26-45(i).

"Issuance of a permit for new construction, reconfiguration or the repair of an existing structure that changes the configuration in a manner not consistent with the terms and conditions of the Manatee Protection Plan is prohibited." [4]

Seagrass, LDC 26-77(a).

"All structures must be placed so as to provide the least possible impact to seagrass, aquatic, or wetland vegetation." [4]

Slip credit rounding, AC-13-21.

"Under the terms of the Plan, the calculation for the maximum number of Slips that can be constructed on site is rounded up to the nearest whole number, while the maximum number of Slips that can be transferred is rounded down." [7]

Plan consistency, Lee Plan Objective 8.2.

"All development approvals for marine-oriented land uses must also comply with requirements in the Ports, Aviation and Related Facilities sub-element and Objectives 128.4 and 128.5." [11]

Fire and fuel. The marina fire standard is NFPA 303, 2021 edition, adopted through the Florida Fire Prevention Code, 8th Edition, under Fla. Admin. Code 69A-3.012 and 69A-60.005 [30, 31, 32]. Fuel dispensers follow NFPA 30 and NFPA 30A (2021), Chapter 11, Marine Fueling, and aboveground tanks over 550 gallons fall under Fla. Admin. Code 62-762 [29, 33].

Diagram of a marina with wet slip docks, dock side setbacks, boat ramp, dry rack building and parking
Illustrative diagram, not to scale: the parts of the model marina and the dimensions this page cites from the sources listed below.

Determination: the program as proposed and as resized

As proposed, the model counts its program the way a developer does: 100 to 250 wet slips in the water and 300 to 500 racks in a building. As the code reads, it is one number. LDC 26-41 makes every rack a slip, and LDC 26-71(a)(4) tests every non-single-family slip against the Manatee Protection Plan [4]. Read that way, a building of 400 racks with 150 wet slips is a 550 slip facility for the manatee test [4]. The size of the dry stack is therefore a manatee question before it is a building question.

The county's slip determination sets the ceiling. Lee County Natural Resources runs the slip determination and GIS evaluation [13], against shoreline the applicant owns or controls, and shoreline created by dredge and fill after Oct. 24, 1989 does not count [4]. Slip credits move between sites under AC-13-21, and its rounding rule works against the buyer: the on-site maximum rounds up, the transferable number rounds down [7].

ElementAs proposedAs resized after code and site
Slip count100 to 250 wet slips plus 300 to 500 racksOne total, racks included, capped by the county slip determination; the resized number depends on the parcel's siting category and is not stated for the model [4, 13]
Shoreline basisThe parcel's frontageOwned or controlled shoreline only; dredge and fill shoreline created after Oct. 24, 1989 excluded [4]
Dry stackProgram height and rack countHeight fixed in the CPD [28]; outdoor storage screened 8 ft toward residential and 6 ft toward a street [24]; slab, ship store and fuel equipment raised for BFE + 1 ft [25]
Dock fieldSlip layout to the riparian lines25 ft side setbacks; 10 ft for a boat ramp; 4 ft at mean low water plus 1 ft clearance; least-impact placement over seagrass [4]
Shoreline edgeBulkheaded edgeNo new or expanded seawalls on natural waterbodies; riprap at a 12-inch minimum average [4]
ParkingSpaces for racks, slips and the store1 space per 5 dry storage stalls; 10 per boat ramp; wet slip ratio not stated; up to 10% administrative reduction [23]
FuelFuel dockAboveground tanks over 550 gallons under 62-762 [29]; NFPA 303 review by the fire district [3]

A rebuild in the county's beach town shows how a rack count moves once boat size and forklift geometry are fixed. The Fort Myers Beach Observer reported that the Town of Fort Myers Beach Council approved the Loggerhead Fish-Tale Marina plans on Aug. 18, 2025: dry storage reconfigured for larger boats, from 441 to 434 boats in 68,000 sq ft, with a wider center lane for forklifts, a deviation allowing a zero setback for the restaurant rehab, and temporary fueling stations during the dock buildout [34, 35].

Height is the other number settled in the hearing. No by-right dry stack height is stated here: the height sections of the code are LDC 34-2174 and 34-2175 (Ord. 23-22), and the dry stack height is set in the CPD [28]. Scaled architectural elevations above mean high water are a required hearing exhibit for dock departures, 34-202(b)(5)d.4 [4], and commercial architectural elevations, signed and sealed, are required for the Development Order (DO Guide item 28; LDC 10-604) [3]. 3D renderings of the stack are built on the same massing.

Site data table and yield

The site data table on the sheet carries these lines. Values marked "not stated" are set by the county determination or by the engineer of record, not by a published number.

Site data itemModel value or rule
Wet slips100 to 250 (program); each counts as a slip [4]
Dry racks300 to 500 (program); "open or covered racks" count as slips [4]
Slip total for the manatee testWet slips plus racks, per LDC 26-45(b)(7) and 26-79; 400 racks with 150 wet slips is 550 slips [4]
Shoreline basisOwned or controlled, measured per LDC 26-41 [4]
Lee siting ratioNot stated; county determination [13]
Dock side setbacks25 ft; boat ramp 10 ft [4]
Depth at mean low water4 ft minimum plus 1 ft keel clearance [4]
Dry stack heightSet in the CPD [28]
Parking1 per 5 dry storage stalls; 10 per boat ramp; wet slip ratio not stated; up to 10% administrative reduction [23]
Outdoor storage screening8 ft toward residential; 6 ft toward a street [24]
FloodBFE + 1 ft freeboard [25]
Protected speciesSurvey required for all PD rezonings and for large developments (over 10 acres or over 2 acres impervious) [3]
Mangroves3:1 replacement, 80% survival over 5 years [4]
Fuel storageAboveground tanks over 550 gallons under 62-762 [29]
HurricaneEmergency Preparedness Plan for marinas and multi-slip docks, 10-154(21) [3]

Yield. The model's yield is the slip determination, and it is not stated until the county runs it. The published records give the benchmarks a developer can hold a parcel against:

  • Jug Creek Marina MPD: 1.11 acres; Green Flash marina and restaurant CPD: 1.05 acres [10].
  • Loggerhead Fish-Tale Marina, as reported: 434 boats in 68,000 sq ft of dry storage [35].
  • Legacy Harbour Marina, per the operator's press release: 131 slips of 40 to 150 ft [36].
  • Port Phoenix: WINK News reported in 2022 that the marina "can store up to 239 boats up to 50 feet in length" [37], and the Cape Coral Breeze reported that the original 2021 county proposal was "dry storage for 200 boats" [38].

Comparable approvals and denials, 2021 to 2026

Each row names its source type. A county hearing outcome appears only where a primary record or a named report states it.

ProjectJurisdictionProgramStatusSource type
Loggerhead Fish-Tale Marina rebuildTown of Fort Myers BeachPost-Ian rebuild; dry storage 434 boats (from 441); 68,000 sq ft dry storage [35]Approved by the Town Council, Aug. 18, 2025, as reported [34]Local news (secondary)
Legacy Harbour Marina rebuildCity of Fort Myers131 slips, 40 to 150 ft; operated under lease with the City [36]Construction began early 2025, per the operator's press release [36]Operator press release
Moss Marina / The ArchesTown of Fort Myers BeachAbout 5 acres, three resort structures, 263 hotel rooms, upgraded marina, as reported [39]First hearing approved, as reported; final adoption not stated [39]Lifestyle publication (secondary)
Jug Creek Marina MPD (DCI2026-00010)Unincorporated Lee1.11 acres, IM to MPD [10]Under review (received Mar. 6, 2026) [10]County DCI report
Green Flash Restaurant CPD (DCI2022-00058)Unincorporated Lee1.05 acres, C-1 and CM to CPD; restaurant and marina [10]Under review since Nov. 21, 2022 [10]County DCI report
Safe Harbor Port Phoenix Marina (Lee County's Waterway Estates Marina)Unincorporated LeeLessee capital: "approximately $9,000,000 in Capital Improvements are planned and funded by the lessee" (SH Marinas, LLC) [40]; federal files SERO-2024-01619 and SAJ-2005-08448 [41]County zoning outcome not stated hereLee County marina page; NOAA record

At Loggerhead, as reported, the rack count fell from 441 to 434 as the racks were reconfigured for larger boats, and the restaurant rehab needed a zero setback deviation [34]. At Port Phoenix the county marina page carries the lessee's capital commitment and the NOAA record carries the federal file numbers [40, 41]. The two unincorporated filings in review, Jug Creek and Green Flash, both use planned development districts [10].

Cost and phasing benchmarks

The published figures are state lease terms, state and county fees, and one operator's capital commitment.

ItemFigureSource date
Submerged lands lease base rate$0.156623 per sq ft per year, a five-year CPI average updated each March 1 [15]Page modified Feb. 20, 2026
Lease rentGreater of 6% of annual income, the base fee or the minimum annual fee [42]Rule 18-21.011(1)(a)1.
Minimum annual fee$423.89 effective March 1, 2007, adjusted annually [43]Rule 18-21.011(1)(b)4.
First-year surcharge, new leases25% [42, 44]18-21.011(1)(b)3.; Dec. 17, 2024 Board of Trustees agenda
Annual rent increase cap10% [42]Rule 18-21.011
Lease discounts10% Clean Marina [45]; 30% if 90% or more open to the public first come, first served [15]2026
Lease term5 years standard; 10 years if 90% public; up to 25 years under 18-21.008(2)(a) [15]2026
Sovereign material severance$1.25 per cubic yard, 18-21.011(3)(a)3. [44]Dec. 17, 2024
FDEP individual ERP, marina this size$14,000 [14]Rule 62-4.050(4)(h)
FDEP ERP, 10 to 29 slips$1,500 [14]Same page
FDEP general permit determination$250 [14]Same page
County Development Order$3,000 + $60 per acre [5]Fee manual, May 2026
Building plan review$0.10 per sq ft ($525 min for a new building); structural inspections $0.15 per sq ft ($500 min) [5]Effective Apr. 15, 2026 (Reso 26-03-20)
Port Phoenix lessee capital"approximately $9,000,000 in Capital Improvements are planned and funded by the lessee" [40]Lee County Waterway Estates page
Dry stack rent, 30 ft boat, Miami (market evidence, secondary)$950 to $1,350 per month (2026) [46]Boat repair blog

Phasing. Lee CPD rules deem the unbuilt balance of a planned development vacated if a phase "was not commenced within one year of its programmed date" [47]. A phased marina therefore commits to a phase schedule it can meet, and county approval before the state lease sets the earliest start for any work over sovereign submerged lands [4]. At Loggerhead, temporary fueling stations operate during the dock buildout, as reported [34]. On Port Phoenix, the North Fort Myers Neighbor reported a 30-year lease term with two 10-year extension options [48].

Submittal anatomy: preliminary plan and engineer of record

The pre-application meeting accepts a conceptual plan; the Development Order requires every plan signed and sealed [3]. The table splits each submittal item between what the preliminary site plan carries and what the engineer or architect of record adds.

Stage and itemPreliminary site planEngineer or architect of record
Pre-application: conceptual plan [3]YesNo
CPD: master concept plan with uses, access, buffers, open space [2]YesRefines at the DO
CPD, dock departures: dimensioned plan view, scaled elevations above MHW, benthic survey, 34-202(b)(5)d.4 [4]Plan view, elevations, slip tableBenthic survey (consultant)
Slip location and quantity; riparian lines; channel width, LDC 26-45(b)(6) [4]YesSurveyed riparian lines (PSM)
Manatee watercraft-slip determination, LDC 26-45(b)(7) [4]Slip tabulation with racks countedCounty determination
DO: cover letter, fee, notarized affidavit, 10-153 [3]NoNo
DO: legal description and sealed sketch, 10-154(1); title, 10-154(2); boundary survey, 10-154(3) [3]NoPSM
DO: existing conditions, 10-154(6); location map, 10-154(6)(a) [3]Location mapPSM or PE
DO: site plan with buildings, travel ways, parking, cross sections and Lee Plan consistency, 10-154(7) and (27) [3]Layout, parking, yield tablesSealed final by PE
DO: traffic impact statement, 10-154(10) [3]Trip inputsTraffic engineer
DO: FLUCCS map; protected species survey and plan, 10-154(6)(f), (14), (15) [3]NoEnvironmental consultant
DO: utility plan, 10-154(7)(j); drainage plan, 10-154(7)(k) [3]Footprints onlyPE
DO: landscape plan, 10-154(7)(l) and 10-416 [3]Concept planting and buffersRLA
DO: exterior lighting and photometric plan, 10-154(8) and 34-625 [3]Fixture locationsPE or lighting designer
DO: Tall Structures Permit, 10-154(13) [3]Height dataApplicant or PE
DO: fire protection plan, 10-154(20) [3]Fire lanesFire protection engineer
DO: Emergency Preparedness Plan for marinas and multi-slip docks, 10-154(21); hurricane mitigation, 2-482 [3]NoOperator or consultant
DO: commercial architectural elevations, 10-604 and 10-620 [3]3D views and elevationsArchitect (sealed)
DO: SWP3 at 1 acre or more of disturbance, 14-477 [3]NoPE
DO: community meeting notes (North Fort Myers and others; Ch. 33) [3]Presentation graphicsApplicant
DO: state and federal permit applications, 10-154(22) [3]NoPE and consultants
Construction drawings, LDC 26-45(c) [4]NoPE or registered architect, sealed
As-built survey, LDC 26-45(d)(3) [4]NoPSM, sealed

The sealing rule for dock work is written into Chapter 26:

"Work relating to industrial, commercial or multi-family projects may require a development order in accordance with Chapter 10 and construction drawings sealed by a professional engineer (P.E.) or registered architect." [4]

The preliminary plan is what the engineer of record builds the sealed Development Order set on. For how the two stages divide nationally, see preliminary versus final site plans.

Conditions and handoff

The conditions a Lee County marina plan inherits come from the code and the county's flood and environmental rules.

  • Floodplain. Substantially damaged or improved buildings must comply, "including elevating not just to BFE but also to Freeboard" [25]. Lee defines substantial improvement as work "the cost of which equals or exceeds 50% of the market value of the structure" [16]. The flood ordinances include 15-09, 22-30, 25-09 and 26-01 [16], and Ord. 22-30 repealed local definition amendments [27].
  • Manatee zones. The county slip cap sits alongside the FWC state manatee zones (68C-22.005) and the federal areas under 50 CFR 17.108(c) [49].
  • Hurricane readiness. The Development Order requires an Emergency Preparedness Plan for marinas and multi-slip docks under 10-154(21), with hurricane mitigation under 2-482 [3].
  • Stormwater and surveys. A SWP3 applies at 1 acre or more of disturbance (LDC 14-477), and sites over 10 acres or with more than 2 acres of impervious area need a FLUCCS map and a protected species survey (LDC 10-154(14), 10-473) [3].
  • Tall buildings. A Tall Structures Permit from the Lee County Port Authority sits in the Development Order submittal, 10-154(13) [3].
  • Clean Marina. The designation is voluntary, requires 100% of regulatory requirements and at least 60% of best management practices, and has a "Clean and Resilient" tier [50, 51]; a designated Clean Marina earns the 10% lease discount under s. 253.0346(3)(a)1. and Rule 18-21.011(1)(b)15a. [15].

At handoff, the engineer of record takes the slip tabulation, the riparian geometry, the dry stack footprint and height, the buffers and the parking count from the preliminary plan and builds the sealed set: surveyed riparian lines and as-built survey by a PSM, construction drawings by a PE or registered architect, and the stormwater, utility and tank design [3, 4]. For the wider permitting stack, see marina development in America and USACE, coastal zone and municipal overlay requirements. Developers weighing a dry stack against an upland storage yard can compare RV and boat storage site plans and the RV and boat storage model in Montgomery County, Texas. Other Florida model projects are the express car wash in Hillsborough County and the RV park in Polk County; the full set is in case studies.

Frequently asked questions

Do dry racks count against the manatee slip limit in Lee County?

Yes. Lee County LDC 26-41 defines a slip to include "open or covered racks", so every rack in a dry stack building counts toward the Manatee Protection Plan slip determination, alongside the wet slips [4].

Can I get the state submerged lands lease before county approval?

No. LDC 26-45(b)(7) requires county approval first wherever a submerged lands lease is required from the Florida Department of Environmental Protection [4].

How much parking does a dry stack need in Lee County?

Table 34-2020(b) of the Land Development Code sets 1 space per 5 dry storage stalls and 10 spaces per boat ramp. The wet slip ratio sits in Note (1) of the same table and is not stated here [23].

What does the state charge for a marina?

The FDEP individual Environmental Resource Permit fee for a marina with more than 30 new slips is $14,000 [14]. Sovereignty submerged lands lease rent is the greater of 6% of annual income, the base fee or the minimum annual fee [42].

How long does a planned development rezoning take in Lee County?

The county states that the average time to complete a planned development rezoning is 9 months, depending on completeness of the application when submitted [2].

Is a hurricane plan required for a Lee County marina?

Yes. The Development Order submittal requires an Emergency Preparedness Plan for marinas and multi-slip docks under LDC 10-154(21) [3].

Which fire standard governs a marina in Florida?

NFPA 303, 2021 edition, adopted through the Florida Fire Prevention Code, 8th Edition, under Fla. Admin. Code 69A-3.012 and 69A-60.005 [30, 31, 32].

What triggers flood upgrades on a marina rebuild?

Work costing 50% or more of the market value of the structure is a substantial improvement, and the building must then be elevated to the base flood elevation plus 1 ft of freeboard [25].

Sources

  1. 1)Hearing Examiner, Lee County. Accessed 2026-10-09.
  2. 2)Planned Development, Lee County Department of Community Development. Accessed 2026-10-09.
  3. 3)Development Order: Application and Approval Guide (updated 8/3/2021), Lee County Department of Community Development. Accessed 2026-10-09.
  4. 4)Lee County Ordinance No. 22-24, amending the Land Development Code (Chapter 26 docks, seawalls and marinas; Chapter 34), Lee County Board of County Commissioners. Accessed 2026-10-09.
  5. 5)External Fees and Charges Manual (AC 3-10, May 2026), Lee County Board of County Commissioners. Accessed 2026-10-09.
  6. 6)Ordinance No. 09-23, amending the Lee County Land Development Code (Manatee Protection Plan), Lee County. Accessed 2026-10-09.
  7. 7)Administrative Code AC-13-21 (slip credit transfer), Lee County Board of County Commissioners. Accessed 2026-10-09.
  8. 8)The Lee County Land Development Code, Ordinance No. 94-24, Lee County. Accessed 2026-10-09.
  9. 9)Ordinance No. 12-01, amending the Lee County Land Development Code, Lee County. Accessed 2026-10-09.
  10. 10)DCI Cases Under Review (report of Oct. 4, 2026), Lee County Department of Community Development. Accessed 2026-10-09.
  11. 11)The Lee Plan, as amended through December 2025, Lee County. Accessed 2026-10-09.
  12. 12)Lee Plan Map 12, Water-Dependent Overlay Zones, Lee County. Accessed 2026-10-09.
  13. 13)Manatee Protection Plan, Lee County Natural Resources. Accessed 2026-10-09.
  14. 14)BIPP Fees (JCP and ERP), Florida Department of Environmental Protection. Accessed 2026-10-10.
  15. 15)FAQ: Use of State-Owned Land, Florida Department of Environmental Protection. Accessed 2026-10-09.
  16. 16)Floodplain Management (Flood Protection Information), Lee County Department of Community Development. Accessed 2026-10-09.
  17. 17)Building Permit Fee Schedule, Lee County Department of Community Development. Accessed 2026-10-10.
  18. 18)SB 180, 2025 Bill Summaries, The Florida Senate. Accessed 2026-10-09.
  19. 19)Reports on the SB 180 lawsuits, Sept. 30 and Oct. 8, 2025 (secondary), Central Florida Public Media. Accessed 2026-10-09.
  20. 20)Chapter 166 Section 033, 2025 Florida Statutes, The Florida Senate. Accessed 2026-10-10.
  21. 21)Bill Analysis and Fiscal Impact Statement, SB 1080 (2025), The Florida Senate. Accessed 2026-10-10.
  22. 22)High-Velocity Hurricane Zones, Florida Building Code, Building, Sec. 1620, Florida Building Commission. Accessed 2026-10-09.
  23. 23)Lee County Land Development Code Sec. 34-2020, Required parking spaces (code mirror), Lee County (via elaws). Accessed 2026-10-09.
  24. 24)Lee County Land Development Code Sec. 34-3005, Storage facilities (code mirror), Lee County (via elaws). Accessed 2026-10-10.
  25. 25)Substantial Improvement/Substantial Damage, Lee County Department of Community Development. Accessed 2026-10-09.
  26. 26)Lee County Ordinance No. 15-09 (flood), Lee County. Accessed 2026-10-10.
  27. 27)Lee County Ordinance No. 22-30 (flood), Lee County. Accessed 2026-10-09.
  28. 28)Lee County Ordinance No. 23-22 (height, Secs. 34-2174 and 34-2175), Lee County. Accessed 2026-10-10.
  29. 29)Fla. Admin. Code R. 62-762.301, Applicability (Florida Department of Environmental Protection rule, via Cornell LII), Cornell Legal Information Institute. Accessed 2026-10-09.
  30. 30)Florida Fire Prevention Code (FFPC), Florida Department of Financial Services, Division of State Fire Marshal. Accessed 2026-10-10.
  31. 31)Fla. Admin. Code R. 69A-60.005, Publications referenced in the Florida Fire Prevention Code (State Fire Marshal rule, via elaws), elaws. Accessed 2026-10-10.
  32. 32)Fla. Admin. Code R. 69A-3.012, NFPA and other standards adopted (State Fire Marshal rule, via Cornell LII), Cornell Legal Information Institute. Accessed 2026-10-10.
  33. 33)Fla. Admin. Code R. 62-762.501, Shop fabricated storage tanks (Florida Department of Environmental Protection rule, via Cornell LII), Cornell Legal Information Institute. Accessed 2026-10-09.
  34. 34)Loggerhead Fish-Tale Marina gets approvals for rehabilitation work (Fort Myers Beach Observer, Aug. 19, 2025; secondary), Fort Myers Beach Observer. Accessed 2026-10-10.
  35. 35)Fort Myers Marina Approved for Repairs, Upgrades (secondary), Toy Storage Nation. Accessed 2026-10-10.
  36. 36)Legacy Harbour Marina Redevelopment After Hurricane Ian (operator press release), Legacy Harbour Marina. Accessed 2026-10-10.
  37. 37)WINK News, Nov. 1, 2022 (Port Phoenix dry storage capacity; secondary), WINK News. Accessed 2026-10-09.
  38. 38)Cape Coral Breeze, Nov. 8, 2021 (Port Phoenix dry storage proposal; secondary), Cape Coral Breeze. Accessed 2026-10-09.
  39. 39)The New Face of Fort Myers Beach (lifestyle publication; secondary), SWFL Life. Accessed 2026-10-10.
  40. 40)Waterway Estates Marina, Lee County. Accessed 2026-10-09.
  41. 41)SERO-2024-01619, Safe Harbor Port Phoenix Marina, NOAA Fisheries, Southeast Regional Office (NOAA Institutional Repository). Accessed 2026-10-09.
  42. 42)Fla. Admin. Code R. 18-21.011, Payments and Fees (Board of Trustees of the Internal Improvement Trust Fund rule, via Cornell LII), Cornell Legal Information Institute. Accessed 2026-10-09.
  43. 43)Fla. Admin. Code R. 18-21.011, Payments and Fees (Board of Trustees of the Internal Improvement Trust Fund rule, via elaws), elaws. Accessed 2026-10-10.
  44. 44)Agenda, Board of Trustees of the Internal Improvement Trust Fund, Dec. 17, 2024, Florida Department of Environmental Protection. Accessed 2026-10-09.
  45. 45)Clean Marina: Steps to Designation, Florida Department of Environmental Protection. Accessed 2026-10-09.
  46. 46)Slip vs Dry Stack vs Trailer: Miami Boat Storage Costs (secondary), Boat Repair Miami. Accessed 2026-10-10.
  47. 47)Lee County Ordinance No. 01-03, Lee County. Accessed 2026-10-09.
  48. 48)North Fort Myers Neighbor, July 19, 2022 (Port Phoenix lease term; secondary), North Fort Myers Neighbor. Accessed 2026-10-09.
  49. 49)Manatee Data and Maps, Florida Fish and Wildlife Conservation Commission. Accessed 2026-10-09.
  50. 50)Clean Marina Program, Florida Department of Environmental Protection. Accessed 2026-10-09.
  51. 51)Florida Clean Marina Guide to Designation, Florida Department of Environmental Protection. Accessed 2026-10-10.

All case studies

Start a project

Bring us the site. We draw the first plan.

Send the parcel, the program and anything you already have: a survey, a sketch, a zoning letter. The studio returns a preliminary site plan your engineer of record can build on.

Start a project