Commercial Site Plan Process: A Comprehensive Guide for Developers and Investors

  • Writer: Alketa
    Alketa
  • 1 day ago
  • 44 min read

Overview of the Commercial Site Planning Process


Successfully developing a commercial site involves multiple phases and stakeholders. At a high level, the land development process includes a thorough site assessment (feasibility and due diligence), conceptual site design and programming, entitlement approvals (planning and permitting), and finally construction. Each phase builds on the last, and overlooking early-stage issues can cause costly delays later.


Key Phases of the Commercial Site Plan Process:

  1. Initial Feasibility & Due Diligence: Research zoning, environmental constraints, utilities, and market viability.

  2. Site Surveys (Boundary & Topographic): Obtain detailed surveys to map property lines, elevations, and features.

  3. Preliminary Site Planning & Programming: Layout site components (building, parking, etc.) considering codes (parking ratios, setbacks, stormwater, fire access, FAR).

  4. Site Plan Drafting & Consultant Coordination: Develop the formal site plan with civil, architectural, traffic, and landscape inputs.

  5. Permitting & Planning Submissions: Submit plans to authorities having jurisdiction (AHJs) for approval; address review comments and public hearings as needed.

  6. Pre-Construction (Final Design & Bidding): Complete detailed design, secure building permits, finalize budgets, prepare the site, and select contractors.


To set the stage, the table below summarizes key consultants typically involved at each phase of the commercial site planning process:


Table 1: Key Consultants by Phase in the Commercial Site Plan Process

Phase

Key Consultants Involved

Initial Feasibility & Due Diligence

Land use/zoning attorney or consultant; Civil engineer (site feasibility); Environmental consultant (Phase I ESA); Market analyst (demographics, traffic counts); Geotechnical engineer (preliminary soil review).

Site Surveys (Boundary/Topo)

Licensed land surveyor (boundary survey, ALTA survey, topographic mapping).

Preliminary Site Planning & Programming

Architect or site planner (site layout, building concept); Civil engineer (grading and stormwater strategy); Traffic engineer (initial traffic impact insight); Landscape architect (conceptual landscape/open space).

Site Plan Drafting & Design Coordination

Civil engineer (site plan, utilities, grading design); Architect (building plans integrating with site); MEP engineers (utility connections, site lighting); Traffic engineer (traffic impact study, driveway design); Landscape architect (landscaping plan); Fire protection engineer (fire lane and hydrant layout compliance).

Permitting & Planning Approvals

Civil/architect (responding to city plan review comments); Zoning attorney or expediter (navigating hearings or variances if needed); Environmental engineers (special permits for fuel tanks, floodplain, etc.); Community outreach specialist (for public meetings if controversial).

Pre-Construction & Bidding

Architect/engineers (final construction documents); Cost estimator; General contractor (bidding phase); Geotechnical engineer (detailed soil report); Environmental remediation contractor (if needed for site prep, e.g. tank removal).

With the team in place, let’s delve into each phase in detail – including actionable best practices and special considerations for gas stations vs. multifamily projects.


Phase 1: Initial Feasibility & Zoning Due Diligence in the Commercial Site Plan Process


Before committing to a site, a developer must conduct exhaustive feasibility studies and due diligence. This phase confirms whether the land can support the intended project both physically and legally. Zoning due diligence is paramount: verify the property’s zoning classification and what it allows “by right” (uses, building height, density) versus what may require a special use permit or rezoning. Early research should uncover any “deal killers” – factors that could make the project unviable. Key feasibility items to investigate include:

  • Zoning & Entitlements: Is the intended use permitted under current zoning? What are the density or unit count limits, floor-area-ratio (FAR) caps, height limits, and required setbacks? Identify if variances, a conditional use permit, or rezoning would be needed and gauge the complexity of obtaining them. For example, a multifamily apartment may require a density bonus or rezoning if current zoning is lower-density; a gas station might only be allowed in certain commercial zones or on corner lots per local code.

  • Title and Legal Constraints: Perform a title review for any easements, deed restrictions, or covenants affecting the site. An access easement or utility easement cutting through the parcel could restrict building placement. Ensure there are no encroachments or liens. It’s wise to order an ALTA survey – a detailed land title survey – to map boundaries and all easements or encroachments. An ALTA survey shows property improvements, utilities, and boundary relations to title records, helping reveal any discrepancies or restrictions that need resolution.

  • Environmental Constraints: Evaluate whether any portion of the site lies in regulated wetlands, protected habitats, or a floodplain. If so, development may require special permits or design accommodations (e.g. elevating structures). Check FEMA flood maps and state environmental databases. A Phase I Environmental Site Assessment (ESA) should be commissioned to identify any potential contamination from prior uses. This is especially critical for fuel station projects – you must verify soil and groundwater are clean or can be remediated, and that a new gas station won’t endanger sensitive environments (e.g. it’s typically discouraged to site fuel tanks near drinking water wells or in certain aquifer protection zones). If the Phase I flags issues, a Phase II ESA with soil/groundwater testing may be needed before proceeding. Environmental due diligence also includes checking for any required environmental impact assessments; for large projects, authorities might mandate an environmental impact report (EIR) examining traffic, air quality, noise, etc..

  • Utility Availability: Determine if the site has access to sufficient utilities – water, sanitary sewer, storm sewer, electricity, gas, telecommunications. Lack of utilities can be a major cost and timeline factor. Confirm locations and capacities of nearest utility connections. For instance, can the sewer system handle a 200-unit apartment’s flow, or a truck stop’s wastewater? If not, off-site utility upgrades or extensions might be required, affecting feasibility. Early conversations with utility providers can clarify capacity and any upgrade costs. Gas station developments have particular utility needs as well: ensure adequate power for pumps and canopy lighting, and confirm a sanitary sewer connection (or plan for on-site septic if remote). Some rural sites may not have gas infrastructure; this is less crucial for a gas station’s operation but might affect convenience store heating or other uses.

  • Access and Traffic: Analyze how the site can be accessed from public roads. Does it have sufficient frontage and existing curb cuts (driveways)? High traffic counts and good visibility are vital for gas station success, but the same traffic can introduce challenges: you may need traffic impact studies and road improvements. Early on, estimate trip generation for the proposed use (e.g. a convenience store gas station has a high vehicular trip count; a 100-unit apartment generates commuter trips) and assess whether nearby intersections can handle it. If a significant traffic impact is expected, budget and timeline for a formal Traffic Impact Analysis (TIA) and potential mitigation (like adding turn lanes or signals) during the entitlement phase. Also verify any access restrictions – for example, some highways disallow new driveways, or a median might prevent left turns into your site. For multifamily projects, consider proximity to transit and walkability as well; insufficient access or poor traffic conditions could affect project appeal and permit approvals.

  • Site Physical Characteristics: Study topography, soils, and drainage. A steep or irregularly shaped site can constrain site layout or require costly earthwork and retaining walls. Unstable or weak soils might necessitate specialized foundation design (identified via a geotechnical study). Check for rock outcrops or high water table which could complicate excavation. Also, identify any natural features to preserve (large heritage trees, waterways) or hazards to mitigate. For example, if the site is adjacent to a gas pipeline easement or high-voltage power lines, those are red flags for site planning and safety. An undesirable adjacency (e.g. backing onto a busy freeway or active railroad) might affect residential project marketability or require noise mitigation measures.

  • Demographics & Market Feasibility: Beyond physical and regulatory factors, developers should assess market conditions and demographics as part of feasibility. For a gas station, analyze traffic volumes and local population density to estimate fuel and convenience store demand. Check competition: how many other fuel stations are in a 1-2 mile radius, and are they well-positioned? A new station needs enough drive-by traffic and population to be profitable. For an apartment project, study local demographics (population growth, employment centers, etc.) and the housing market (rents, vacancy rates, absorption) to ensure there is sufficient demand. This might involve a formal market study. From an investor perspective, demographics and location quality heavily influence a project’s financial feasibility, so this due diligence is as important as the site’s physical suitability.

  • Political and Community Factors: Especially for projects requiring zoning changes or for potentially sensitive uses (like a gas station with 24-hour operation or a high-density apartment in a suburban neighborhood), gauge the community sentiment and political landscape early. Research if similar projects have faced opposition in the area. A project can meet all technical requirements and still be derailed by public opposition during hearings. Identify local stakeholders – neighbors, community groups, elected officials – who might support or object. For example, a new fuel station might raise community concerns about traffic, noise, or environmental risks. A multifamily development might trigger worries about school capacity or changing neighborhood character. Proactively planning for community outreach (or at least not underestimating its impact) is part of feasibility. Also, confirm which jurisdictions and agencies have authority (city, county, state DOT, environmental agencies, etc.) and anticipate their requirements.


Best Practices – Phase 1 (Due Diligence):

  • Engage Local Officials Early: Schedule an informal meeting or call with the local planning department to discuss the site’s zoning and get initial feedback. Early collaboration with planning staff can clarify zoning interpretations and potential hurdles. If a rezoning or special permit is needed, understanding the process (timelines, submittal requirements, political support) upfront is critical.

  • Use Checklists to Cover All Bases: Employ a comprehensive due diligence checklist so no major item is overlooked. This should include zoning, utilities, environmental, access, title, and more. Professional consultants (land use planners, engineers, attorneys) can help ensure all the “right questions” are asked.

  • Identify Deal-Killers First: As QES Inc. advises, start with a 30,000-foot view to find any “deal killers” before spending too much time or money. For instance, if initial research shows the site has no sewer access and is 5 miles from the nearest line, that could be a show-stopper for a high-density project. Likewise, if zoning absolutely prohibits the intended use (and a change is unlikely), it may be wise to walk away.

  • Commission Preliminary Studies: If potential issues are found, consider preliminary studies before closing on land. For example, do a geotechnical soil boring or two if steep slopes or fill dirt are suspected; conduct a Phase II environmental test if Phase I flags a likely contamination. A modest upfront cost can save huge expense later if an issue is confirmed, allowing you to reconsider or renegotiate the land deal.

  • Assess Financial Feasibility in Parallel: Due diligence isn’t just technical – ensure you run pro forma financial models factoring in any special costs (e.g. off-site utility extensions, environmental remediation, extra fees). If the numbers don’t pencil out with those costs, you either must acquire the site cheaper or find cost reductions. Sometimes, due diligence discoveries can be used to negotiate a better land price.

  • Fuel Station Specific: Verify state-level requirements for new gas stations. Some states or cities have limits (for example, a city might ban new gas stations within X distance of an existing one). Check if underground storage tank permits are handled by a state environmental agency and what their process entails. Plan for a Phase I ESA even if none is required by lenders – gas stations face heavy environmental scrutiny and any hint of soil issues should be resolved before purchase.

  • Multifamily Specific: Examine entitlement requirements like affordable housing mandates or school impact studies. Many jurisdictions require multifamily developments to either include a percentage of affordable units or pay fees. Understand these policies now to factor into feasibility. Also, neighborhood support can be crucial – consider engaging a zoning attorney or land use consultant who knows the local political climate if a rezoning or variance is needed for added density.


Phase 2: Site Surveys and Topographic Mapping – Establishing the Site Base


Once initial feasibility checks out and you’re moving forward with the property, the next step is to obtain detailed land surveys. A professional survey provides the accurate framework on which all site planning will rely. There are two main survey components needed for site development: a boundary survey and a topographic survey. Often these are combined (and for commercial projects, done to ALTA/NSPS Land Title Survey standards).

  • Boundary Survey (ALTA Survey): This survey confirms the exact property lines and any easements or encroachments on the land. An ALTA/NSPS Land Title Survey is the gold standard for commercial development – it maps the boundaries with a high degree of precision and includes all easements, rights-of-way, and other exceptions from the title report. It may also show zoning information like building setback lines and height or floor area limits if requested. Essentially, it ensures that you know what land you truly control and any legal limitations on it. For example, the ALTA survey might reveal a utility easement running through what you thought was buildable area – a critical insight for the site plan. Lenders typically require an ALTA survey for financing, and title insurers use it to clear exceptions. From a developer standpoint, investing in a quality ALTA survey early is a risk mitigation move: “An ALTA survey can reveal critical discrepancies that need to be resolved, lowering risk for future owners.”. It also prevents nasty surprises like discovering after design that part of your parking lot was actually on a neighbor’s land – the ALTA will catch boundary overlaps or gaps before you build.

  • Topographic Survey: Along with boundary lines, you need to understand the site’s topography (ground elevations and contours) and existing natural and man-made features. A topo survey will map the elevation contours, high and low points, and often existing structures, fences, trees, and utilities at or above grade. This is essential for designing grading, drainage, and utility plans. If the site has significant grade change, the survey helps calculate how much earthwork (cut/fill) will be needed to create level building pads or parking areas. The topo should extend out to adjacent road centerlines and a bit onto neighboring properties to show how your site will tie in. Many survey crews will also locate visible evidence of utilities (manholes, hydrants, utility poles) and may perform a subsurface utility locate (marking underground lines) as part of the survey. Accurate topo and utility information upfront prevents design conflicts and change orders later. For instance, knowing that there’s a 24-inch storm sewer line crossing the site (and its depth) will allow your civil engineer to plan around it or design a tie-in point.

  • Survey Precision & Benchmarks: Ensure the survey is tied to known benchmarks and a coordinate system (often state plane coordinates), so that all consultants (civil, architect, etc.) work off the same data. The surveyor will provide an electronic CAD file of the survey – this becomes the base map on which the site plan is developed. Quality matters: a missed boundary marker or a half-foot error in elevation can cause big headaches. Always have the surveyor include a few key spot elevations (e.g. street gutters, crown, adjacent grades) and any floodplain elevation if applicable.

  • Floodplain and Wetland Delineation: If initial research showed any flood zones or potential wetlands on site, you may need specialized surveys for those. A floodplain survey can confirm ground elevations relative to the Base Flood Elevation (100-year flood level) to see what portions of the site are buildable or require floodproofing. A wetland delineation by an environmental consultant would flag the exact boundaries of any wetlands, which then the surveyor can locate and plot on the site base map. These constraints must be known early as they significantly impact site layout (you typically must avoid or mitigate building in these areas).

  • Property Corners and Stakeout: After the survey, you will have marked property corners and possibly flagged offsets. It’s good practice to walk the site with the survey in hand, observing where the boundaries and significant features lie on the ground. This can reveal practical issues – e.g., the neighbor’s fence might encroach over the line, or there is a steeper slope at the back than the topo indicates (surveys sometimes miss hidden ravines under thick brush). Field-walking the site with survey data in mind helps connect paper to reality.


Best Practices – Phase 2 (Surveying):

  • Specify ALTA/NSPS Standards: For commercial projects, explicitly request an ALTA Land Title Survey in your surveyor’s scope. It ensures a comprehensive product that meets lender and title requirements. This will include locating all improvements and utilities and showing easements, which a simple boundary survey might omit.

  • Include “Table A” Items: ALTA surveys have optional items (Table A) – coordinate with your surveyor and title company to include important ones like item 6 (zoning information on the survey), item 7(a) and (b) (building height or number of stories if any structure on site), item 8 (substantial features like parking, if existing), etc., as needed for your project. Having zoning setbacks graphically shown on the survey (item 6(b)) can be very useful.

  • Obtain Utility Maps and One-Call Locate: Have the surveyor coordinate a utility “one-call” locate before doing the topo, so that underground utilities are marked and can be surveyed. Also request record utility maps from local jurisdictions (many cities will provide water/sewer as-builts or GIS data). Combine this info with the survey so your base map shows known utility lines – your engineers will thank you later.

  • Accuracy in Vertical Datum: Ensure the survey vertical elevations are on a known datum (NAVD88 or similar) and not an arbitrary datum. This allows cross-checking with floodplain data (which is published in NAVD88 typically) and helps if future construction requires elevation certificates.

  • Survey the Entire Parcel and Access Points: Sounds obvious, but make sure the survey covers all areas needed, including any off-site areas that will be involved in development (e.g. an off-site septic drain field, or an off-site road improvement area if known). If your project depends on access from an adjacent property or across a shared driveway, survey that connection point too.

  • Use Survey for Stakeholder Discussions: A detailed survey (with topo and constraints) is a great visual to discuss the project with stakeholders (city or community) early on. It shows you’ve done your homework and provides a common reference. In contentious cases, being able to point out property lines, buffers, etc., on a survey can clarify misconceptions with neighbors or officials.


Phase 3: Preliminary Site Planning & Programming in Commercial Development Projects


With a clear picture of site conditions from the survey and due diligence, the next step is preliminary site planning and programming. This is a creative and analytical phase where you determine how the project’s requirements can fit on the site in compliance with regulations and good design practice. Essentially, you’re creating a conceptual site plan: placing the building(s), parking, driveways, open spaces, stormwater facilities, etc., to test what the site can accommodate.


Key considerations and tasks during preliminary site planning:

  • Site Layout & Building Placement: Decide where the building or buildings will sit on the lot, considering setbacks from property lines, separation from other structures, and optimal orientation. Zoning setbacks (e.g. a 25-foot front yard, 10-foot sides) create a buildable envelope on the site that you must work within. If it’s a gas station, the canopy and pump islands must also respect setbacks and often have additional distance requirements from street frontages for safety. For an apartment complex, multiple buildings might need spacing to meet fire code and provide attractive courtyards or amenity areas. Try a few test fits of different configurations (this is often done with bubble diagrams or rough sketches initially).

  • Parking and Circulation: Determine the parking needs based on zoning parking ratios and project requirements. A convenience store might need, say, 1 parking space per 200 square feet of store, plus sufficient space at each pump lane. Multifamily housing might require 1.5 to 2 spaces per unit (unless reduced for transit-accessible locations or via shared parking strategies). Lay out parking lots or garages to meet those counts, while also paying attention to efficient circulation for vehicles and pedestrians. Ensure there is safe fire truck access: typically a fire lane of at least 20 feet width must reach within a certain distance of all points of a building. This can dictate drive aisle locations or require turnarounds (like a cul-de-sac or hammerhead for fire trucks) if the site is long or buildings are in the rear. Include loading zones or service access in the plan if needed (e.g. for dumpsters, delivery trucks). For gas stations, circulation is critical – the layout must allow fuel delivery trucks to enter, reach the tank fill points, and exit without difficult maneuvers, all while not blocking customer vehicles. Early use of vehicle turning templates can verify a tanker truck path and adequate turning radii.

  • Stormwater Management Planning: Modern developments must handle stormwater runoff on-site to prevent flooding and protect water quality. At the preliminary stage, identify space for stormwater facilities such as detention basins, retention ponds, or underground chambers. Many jurisdictions require a certain volume of stormwater storage for a given amount of new impervious surface. Set aside a low area of the site for a surface pond or determine if an underground system under a parking lot is feasible. The site grading concept will revolve around directing runoff to these facilities. Additionally, plan for stormwater quality measures (sometimes called BMPs) like oil-water separators (especially important for gas stations to capture fuel spills from runoff), bio-retention swales, or filter strips. Get a preliminary handle on how you’ll manage the first flush of runoff – this is both a regulatory and environmental best practice. If the site is large, preserving some green open space as a dual-use for stormwater (parks that detain water, etc.) could satisfy landscaping and drainage needs simultaneously. Early consultation with a civil engineer on approximate sizing of detention (using rules of thumb or prior projects) is valuable to avoid underestimating land needed for this – you don’t want a nasty surprise later that you must eliminate a row of parking to fit a stormwater pond.

  • Utility Service Planning: Outline how utilities will serve the site. On the preliminary plan, mark likely routes for water lines, sewer lines (gravity flow toward existing mains, which dictates where your building pad elevation might need to be), underground electric, etc. This doesn’t need fine detail yet, but do verify things like where sewer can connect (e.g. perhaps on the west street, so you’ll route sewer across the site that way). If a lift station or septic system is needed (say the site is lower than the sewer main or no sewer is available), plan where that would go. Also consider storm sewer outfall locations – where will you release detained stormwater? If there’s a city storm drain nearby, great; if not, maybe a drainage swale at the property edge. For fuel stations, plan where underground storage tanks (USTs) will be buried. They should be located away from property lines (often regulated minimum distances) and in an area accessible for refilling (usually near the pumps, but not under where structures will go). Many designers place USTs under drive aisles or parking, keeping them out of future building footprints and providing enough clearance for excavation and maintenance.

  • Fire and Safety Considerations: Loop in fire safety early. Large multifamily buildings may need onsite fire hydrants if public ones aren’t within a certain distance. Determine if you’ll need to add a hydrant on-site or along the frontage (fire marshal can advise on this early). Ensure a fire apparatus route can navigate the site – no dead-ends longer than code allows without a turnaround, adequate vertical clearance, etc. If the project will be gated (common in some apartment complexes), plan gates to meet fire department criteria (e.g. typically 20 ft clear opening for emergency access). For fuel stations, there are specific safety standards (often NFPA codes) that dictate things like distance between fuel dispensers and buildings, canopy height, vent pipe locations for tanks, etc.. During preliminary design, at least be aware of these (engage a fuel system specialist if needed) so you don’t propose something that violates safety regs (like placing a propane tank cage too close to a building exit, etc.).

  • Building Size and FAR: Calculate the preliminary Floor Area Ratio (FAR) to ensure you are within the allowed limit. FAR is the ratio of total building floor area to the site area, and it’s a key zoning control on development intensity. For example, on a 2-acre (87,120 sf) site zoned with FAR 0.5, you can only build up to 43,560 sf of building floor area. Make sure your building footprints and number of stories stay under that. FAR will be especially relevant in multifamily projects where you might be trying to maximize unit count – it will tell you if you can add another floor or need to reduce footprint. Also verify lot coverage limits (some zones limit the percent of land that can be covered by buildings). At this stage, you might find you need to adjust: e.g., the desired unit count yields too much square footage, so perhaps structured parking (which often doesn’t count toward FAR fully, or at all, depending on code) could allow more units compared to surface parking with large building footprints. These code-driven calculations are a big part of site programming.

  • Open Space and Landscaping: Identify areas for required open space, buffers, or amenities. Many zoning codes require a certain percentage of the site to be landscaped or open. Multifamily projects often must provide common recreational areas or playgrounds if family-oriented. Sketch out where these can go so they complement the site (e.g. a corner pocket park, a central green courtyard, etc.) rather than being left-over scraps after building and parking placement. For gas stations, landscaping is usually required along street frontages and at property edges to screen from residential neighbors. It’s good to note where you’ll preserve existing trees or add new planting beds in concept – not only to meet code but to create a more attractive site that might face less neighbor resistance.

  • Preliminary Grading Concept: Although fine grading comes later, at least conceptually think about how the site will be graded. Is the building pad roughly at street level, or does it need to be raised/lowered? Will you have retaining walls along property lines due to elevation differences? A quick cut/fill equilibrium analysis might be done if large earthmoving is expected (to see if you balance on-site or need export/import of soil). If the site is in a floodplain, at this stage plan how you’ll get the building at the required elevation (which might mean bringing in fill and thus digging a compensatory flood storage pond elsewhere on-site).

  • Special Features by Project Type:

    • Gas Station Example: Include space for underground tanks and consider vapor recovery systems (some areas require an area on site for vapor recovery equipment for fueling). Plan the canopy coverage – typically you want the fueling area fully covered by a canopy for weather, but the canopy must also meet height and setback requirements (and not conflict with power lines, etc.). Decide if you will include a car wash or quick-serve restaurant as part of the station – those add needs for additional water/sewer and more parking/queue space, which must be accounted for now. Also consider pedestrian access – will there be walk-in customers from the street or is it all vehicular? If near a residential area, providing a sidewalk connection might be favorable.

    • Multifamily Example: Think about building typology (garden apartments vs. a single large building, etc.). A larger single building might require features like a centrally located lobby, elevators, and fire sprinkler risers – plan space for those. If it’s a multi-story building, outline where the fire truck ladder access would be (they typically need to get within 30-50 feet of upper-floor windows). Amenities like pools, dog parks, or clubhouses should find a logical spot on the site plan early. And consider phasing if it’s a big development – maybe you can carve the site into phases with their own parking and access, which can influence the initial layout.


At this preliminary planning stage, it’s wise to engage key consultants for early input. A civil engineer can do a sanity check on stormwater and grading feasibility. An architect or experienced site planner can help optimize building placement and parking efficiency. The goal is to produce a preliminary site plan that is both ambitious (meeting the project’s program to make the investment worthwhile) and realistic (meeting major code requirements and site constraints). Often this results in a few iterations and trade-offs, like reducing building square footage to fit more stormwater area, or adding a parking deck to meet parking count on a tight site, etc.


Best Practices – Phase 3 (Preliminary Planning):

  • Check Regulations Early and Often: Constantly reference the zoning ordinance and development standards during this phase. Create a “zoning summary” for quick reference – listing allowed uses, setbacks, height limit, FAR, open space %, parking ratios, etc. – and check your concept against it. This prevents going too far with a plan that violates basics.

  • Use Conceptual Sketches and Diagrams: Start with rough sketches to explore ideas without getting bogged down in CAD. Hand-drawn bubble diagrams or massing studies can quickly vet what might work. Once a promising concept emerges, then move to a more scaled drawing.

  • Stake Out on Site (if possible): For small sites, an effective tactic is to physically stake out the outline of the building or other key features on the ground. This helps visualize scale, see if that 50’ setback is actually leaving usable space, etc. It can sometimes reveal issues (like a big slope or tree exactly where you thought a building corner could go) that aren’t obvious on paper.

  • Iterate with Stakeholder Input: If you have a friendly planning staff or known community concerns, consider sharing a sketch early to gather feedback. For instance, a quick review by the city’s development review team on a concept plan can highlight major issues (e.g. “your driveway is too close to the intersection per code” or “we would require a second access point for emergency vehicles”). It’s easier to adjust now than after you’ve detailed out a full site plan.

  • Parallel Market Considerations: Ensure the preliminary plan still aligns with market needs. Don’t, for example, design an apartment complex with insufficient parking if the local market expects ample parking (even if code allows less) – that could hurt leasing. Or for retail, consider if the layout has good visibility and traffic flow to attract tenants and customers. These qualitative factors are important to eventual project success.

  • Document Assumptions: Keep notes on any assumptions made (like “assuming stormwater detention volume ~15,000 cf based on 1” runoff over site”) so that when engineers get on board they understand the basis. This also helps quickly identify if an assumption was wrong – e.g., if detailed calcs later show you need 30,000 cf (double) for detention, you know your initial plan might need significant revision.

  • Think Ahead to Phase 4: Use this stage to flag any studies you’ll likely need. If the preliminary plan is pushing some limits – say, a lot of traffic – go ahead and plan for a full traffic study to be commissioned in the next phase. Or if you anticipate a need for a shadow study (for a tall building casting shadows in a neighborhood) or other special analysis, note it. Early recognition of these needs keeps the project timeline on track by initiating them sooner.


Phase 4: Site Plan Drafting and Consultant Coordination in Commercial Projects


After refining a workable concept in preliminary planning, the project moves into formal site plan drafting and design coordination. At this phase, the developer’s team of consultants comes together to produce the detailed site plan documents required for permitting and construction. It’s an intensive coordination stage where architecture, engineering, and landscape design are integrated into a coherent plan set. A well-coordinated site plan not only meets all codes but also reflects input from various technical studies (traffic, environmental, etc.) so that approval can be obtained with minimal delays.


Key aspects of Phase 4 include:

  • Civil Engineering Site Plan: The civil engineer will take the lead on drafting the site plan to scale, showing all site improvements. This includes the dimensioned layout of buildings, parking stalls (count and ADA accessible spaces), drive aisles, curbs, sidewalks, and property lines with setbacks annotated. They will also prepare grading plans (existing and proposed contours), drainage plans (with stormwater structures and piping), utility plans (water, sewer, storm, electric/telecom routes), and erosion control plans for construction. Close coordination is needed to ensure the civil plans align with the architectural plans – for instance, the civil must use the exact building footprint from the architect, and the architect must be aware of civil constraints like where stormwater facilities or utility lines are running. Regular cross-checks between civil and architectural drawings are essential to avoid conflicts (e.g. an outdoor stair from the building that lands where civil had a drainage swale).

  • Architectural and MEP Coordination: The project architect focuses on the building design (floor plans, elevations, etc.), but they also contribute to site planning elements like placement of doors, service areas, and aesthetic guidelines (façade setbacks, site lighting look, etc.). Mechanical/Electrical/Plumbing (MEP) engineers contribute designs for site lighting, exterior electrical (e.g. transformers, panel locations), fire suppression (fire hydrant flow requirements or fire department connections on buildings), and any site piping that connects to building systems (like a fire sprinkler line from the underground water main). All these elements must be shown on the site plan or related sheets. For example, if the electrical engineer decides the site needs a pad-mounted transformer in the back corner, the civil site plan should mark that location and ensure it’s accessible (and meets utility company clearance requirements). Early meetings between civil, architect, and MEP engineers prevent design silos. They can agree on things like where the building will route its roof drainage (ties into storm system?), where water and sewer will stub out of the building, how the grading will meet building entrances (slopes for ADA access), etc.

  • Landscape Design: The landscape architect or designer will create a landscape plan as part of the site plan package. This shows proposed planting (trees, shrubs, groundcover) and sometimes hardscape or site furnishings. Coordination here ensures the landscape plan doesn’t conflict with utilities or visibility needs. For instance, large shade trees shouldn’t be placed directly above water lines or under power lines; sight distance triangles at driveways must remain clear of tall shrubs for safety. Many cities have stringent landscaping requirements (number of street trees, parking lot shading, buffer plantings), so the landscape plan must meet those and ideally enhance the project’s appearance to help in approvals. In projects like multifamily, landscape architects also design amenity spaces, which need coordination with grading and drainage (nobody wants a flooded playground because the civil plan and landscape plan didn’t sync elevations). For gas stations, landscaping is often one of the only aesthetic contributions – adding perimeter trees or planters at the pump islands can improve public perception. But care: landscaping must not block views of the fueling area for security, and root systems shouldn’t interfere with underground tanks or lines.

  • Traffic and Access Engineering: If a Traffic Impact Analysis (TIA) was required (often for gas stations or large developments), its recommendations must be integrated into the site plan. This might include road widening, dedicated turn lanes, new traffic signals, signage, or other off-site improvements. The site plan set should have a traffic/access plan or notes that depict these: e.g., showing an added right-turn deceleration lane into the driveway, or marking “By Others: traffic signal to be installed by developer at intersection per TIA.” Often, civil engineers incorporate these details, but sometimes a traffic engineer will provide a separate drawing for off-site improvements that gets appended. Additionally, vehicle turning templates should be run at this stage using software (AutoTURN or similar) to refine driveway widths and curb radii. The fire department might require a turning path exhibit to demonstrate a fire truck can reach all parts of the site. Ensure any conditions from city traffic engineers (like “driveway must be aligned with the shopping center across the street” or “installation of a pedestrian crosswalk”) are clearly noted on plans.

  • Specialty Consultants: Depending on the project, other consultants may need to feed into the site plan. For example, a stormwater management consultant might design an underground detention system – providing civil with detailed specs to include. An environmental consultant may design a remediation plan if, say, an old fuel tank is being removed – that could necessitate showing an excavation area on plan or notes about handling contaminated soil. For a fuel station, a petroleum equipment specialist will design the fuel system (tank sizes, pump specs, piping, vents). While their detailed plans might be separate, the site plan should reserve space for those components (tank pit and fill ports, dispenser locations, a vapor recovery unit, etc.). Ensure all specialties are looped in and their requirements reflected. For multifamily, if doing a large project, sometimes a phasing plan is needed – showing how construction might be split. This should be coordinated so that each phase stands on its own for access, fire lanes, etc., which affects the site plan design.

  • Ensuring Code Compliance: At this point, you should double-check that the evolving detailed plan still meets all development regulations. Are you still within FAR and lot coverage limits after finalizing building size? Is the parking count meeting or exceeding minimums (and not far exceeding maximums, where applicable)? Does the site lighting plan meet dark sky or light trespass rules? Are the refuse enclosures placed per code and sized for required dumpsters? Use a site plan review checklist (many cities publish one) to self-audit before official submission. For instance, Rockingham County’s checklist might remind you to show fire lanes and hydrants; others ensure ADA parking is correctly located, etc. Proactively catching any omissions now will speed up the approval later.

  • Drafting Quality and Clarity: The site plan drawings will be scrutinized by plan reviewers, so clarity is key. Dimension critical elements (building setbacks, drive aisle widths, parking stall dimensions). Provide clear labels and legends. Separate overly busy drawings into multiple sheets if needed (e.g., don’t clutter a grading plan with utility lines if it becomes unreadable – split them). Reviewers and approving commissions can be frustrated by hard-to-read plans, which can slow down the process with more comments. Also, incorporate any standard details required by the jurisdiction (they often have standard utility trench details, etc., that need to be on the plan set).

  • Internal Team Reviews: Before submitting formally, it’s wise for the consulting team to conduct an internal “pin-up” or peer review of the site plan set. For example, have the architect review the civil drawings and vice versa. They may catch inconsistencies (architect shows a back door on west side, but civil doesn’t have a sidewalk to it – add one; landscape shows a tree that conflicts with a light pole on electrical plan – adjust spacing, etc.). This internal QA/QC can significantly reduce the number of official review comments you’ll get.


A critical mindset in this phase is coordination. Poor coordination can lead to situations like permitting failures or construction change orders – both costly. As one development blog noted, “Permitting rarely fails because an application was missing a box check. It fails because the project didn’t do the groundwork: traffic, stormwater, environmental constraints, site layout, community impacts, and stakeholder coordination.”. In other words, success comes from integrating all these pieces early and completely.


It’s also prudent at this stage to engage the Authority Having Jurisdiction (AHJ) in a pre-application meeting if you have not already. Many jurisdictions offer (or even mandate) a pre-submittal meeting where you present your draft site plan to staff from planning, zoning, engineering, fire, etc., for feedback. This can be golden: “A typical pre-application meeting includes representatives from several city departments... Each department reviews the concept and provides feedback. Some comments may be straightforward... Others can completely change the scope of a project.”. For example, an early meeting might reveal the city wants a different driveway location or needs a larger water line extension than you assumed. Catching those now saves you from a likely plan rejection or major revision later. The pre-app meeting also helps align expectations and build rapport with staff – they see you’re proactive, which can smooth the review path.


Best Practices – Phase 4 (Design Coordination):

  • Hold Regular Coordination Meetings: Schedule weekly (or biweekly) design team meetings with all consultants during active drafting. Use these to go over plan progress, resolve design conflicts in real time, and ensure everyone is on the same page. Continuous communication prevents siloed decisions that clash.

  • Maintain a “Clash Log”: Keep a simple spreadsheet of coordination issues that need resolution (e.g., “Lighting vs. Tree conflict at northwest corner – resolve by moving tree 5 feet”). Update it as items are fixed. This helps track that all known conflicts are addressed before finalizing plans.

  • Peer Review Against Regulations: Have someone on the team (often the civil engineer or a planning consultant) do a thorough review of the plan against the zoning/development code line by line. Confirm setbacks are met (using the survey, double-check distances), open space percentages are labeled and met, required parking calc is shown and correct, etc. This internal review can be done using the city’s own site plan review checklist if available.

  • Engage the Fire Marshal and Utility Providers: Don’t hesitate to run parts of the plan by specific officials early. For instance, ask the fire marshal to look at your truck access and hydrant placement before you submit – they might point out a needed change that’s easier to make now. Similarly, many utility companies will do a preliminary design or comment (especially if you need to coordinate a new transformer or special meter). This informal review can save a round of revisions later.

  • Document All Mitigations: If any studies (TIA, environmental) recommended specific mitigation measures, clearly incorporate those into the plans or notes. Also, prepare a short narrative you can include in your submission explaining how you addressed each requirement from those studies. This heads off reviewer questions like “How are you addressing the 30% traffic increase on Main St.?” by proactively showing the turn lane you’re adding.

  • Quality Assurance Before Submission: Do a final QA/QC of the entire plan set: verify consistent north arrows and scales, correct sheet numbering, and that all required sheets are included (site plan, grading, utility, landscape, lighting, building elevations if needed for design review, etc.). Ensure professional seals/signatures as required. A clean, complete package creates a good first impression with reviewers, potentially leading to a smoother approval.

  • Continuous Value Engineering: As plans get detailed, costs also firm up. Keep an eye on cost drivers in the design – if that fancy paver driveway or extensive retaining wall looks expensive, discuss with the team (and owner) whether it’s necessary or if there are cheaper alternatives. It’s better to value-engineer now, during design, than to wait until contractor bids come in over budget and then scramble to change the plans.

  • Gas Station Tip: Engage a petroleum equipment contractor/specialist during design. They often provide a layout for tanks, lines, vents, and can ensure compliance with myriad fuel regulations (like proper vent line slope and separation, leak detection systems, etc.). Integrate their design into your site plan sheets to show the AHJ that the fuel system is well-planned and meets environmental safety.

  • Multifamily Tip: Coordinate the site plan with building architectural design guidelines if any (some cities have design review for multifamily). For example, ensuring the site plan allows for foundation landscaping, or that the dumpster is screened per design standards, will be noticed. Also, if the project triggers any public amenities (like a sidewalk extension or park dedication), include those in your plan set clearly to demonstrate community benefit.


Phase 5: Permitting & Planning Submissions – Navigating Approvals in the Site Plan Process


With a comprehensive site plan in hand, the next hurdle is obtaining permits and approvals from the relevant authorities. This phase can be one of the most challenging in the commercial site planning process, as it involves meticulous review by regulators and often some iteration to address their comments. It may also involve public hearings and neighbor input. The goal is to secure all necessary entitlements – from site plan approval to building permits – so that construction can commence.


Key steps and considerations during permitting and approvals:

  • Site Plan Application Submission: The first major milestone is typically submitting the site plan (and supporting documents) to the local planning or development department. This package might be called a Site Plan Review application, Development Plan, or similar. It usually includes the plan drawings, drainage report, traffic study, landscape calculations, photometric (lighting) plan, building renderings (if architectural design review is needed), and a summary narrative. Timelines for the review process vary widely by jurisdiction. Some municipalities can approve a straightforward site plan administratively in a month or two; others require multiple rounds of review and even planning commission hearings that can stretch close to a year for complex cases. A fast-track scenario (by-right project, no significant issues) might see approval in ~3–6 months, whereas a discretionary or contentious project can easily take 6–12+ months. It’s crucial to understand whether your project is “by-right” (conforming to zoning, thus mostly administrative review) or “discretionary” (needing special approvals or facing subjective criteria). By-right projects tend to have more predictable and shorter timelines; discretionary projects (like a gas station requiring a conditional use permit, or a multifamily needing rezoning) will involve public notice and hearings, adding time.

  • Agency Reviews and Comments: Once submitted, the plans will circulate to various city/county departments: planning/zoning, engineering (stormwater, utilities), fire department, transportation, environmental, etc. Each will review according to their regulations and issue comments. Expect a letter or report consolidating these review comments typically within a few weeks (commonly 2–4 weeks for first review cycle, but it could be longer if backlog). The project team must then respond to each comment and revise plans accordingly. Common comments might include requests for more detail (e.g. “Show all existing utility lines and their sizes”), corrections (“Driveway spacing does not meet minimum 200’ separation – revise location or seek a variance”), or additional studies (“Submit a geotechnical report and foundation plan for review”). It’s normal to have a couple of review cycles of comments and resubmittals. The key is to respond thoroughly and not ignore any item, as incomplete responses lead to further delays. Typical number of cycles might be 2 or 3 for a normal project; more if complex. Many delays are caused by resubmittals that don’t fully address comments, prompting another round. Thus, read comments carefully and even have a clarification call with reviewers if needed, to get it right the next time.

  • Public Hearings and Approvals: If the project requires a public hearing (common for conditional uses, rezonings, variances, or simply because of local ordinance for certain site plans), this adds a layer. For example, a fuel station often triggers a conditional use permit hearing due to the fuel sales use – neighbors will be notified, and the planning commission or a board will consider testimony. Multifamily projects might require a hearing if they are large or need rezoning or special exceptions (some communities want any sizable development to get commission approval). To prepare, the development team should engage in community outreach ahead of the hearing. This could mean meeting with neighbors or homeowner associations to explain the project and address concerns. It’s also wise to have renderings or visual aids to show at hearings how the project will look and that it meets requirements. Addressing community concerns can make or break the approval. Common concerns for gas stations are traffic, noise, and environmental risks – be ready to explain mitigation like sound buffering, limited hours for deliveries, spill containment measures, etc. For multifamily, concerns might be density, parking overflow, or school impacts – you might highlight, for instance, that the project is near transit (reducing traffic) or that you’re contributing to a school impact fee. At the hearing, ensure experts (engineers, traffic consultants) are on hand to answer technical questions. If the project is well-prepared and aligns with the jurisdiction’s plans, a “fast” discretionary approval might still be ~3–6 months, factoring in hearing schedules, while contentious cases or those needing higher-level political approval (city council) could extend beyond a year.

  • Conditional Approvals and Revisions: It’s common for approval to come with conditions. For example, the planning commission might approve a site plan “conditional on adding a sidewalk along the frontage” or “subject to staff approval of a revised landscaping plan with more evergreen trees in the buffer.” Take these conditions seriously and incorporate the required changes quickly. Some conditions might require returning to the commission for confirmation, while others can be handled administratively. Sometimes, a project is approved conceptually but must “come back for final plan approval” after making certain changes. Factor in time for these conditional follow-ups. Also, regulators might ask for developer agreements for certain improvements (like you agree to pay for a traffic signal, or extend a sewer line). Work with legal counsel to review such agreements promptly so as not to delay permitting.

  • Obtaining Specialized Permits: Beyond the general site plan or planning approval, identify and pursue all other permits needed:

    • Environmental Permits: If disturbing a large area, an NPDES stormwater construction permit (from state environmental agency) will be needed for erosion control. If impacting wetlands or streams, a Corps of Engineers Section 404 permit and state wetland permits are required (which can take months – often started during site plan phase). For fuel stations, specific permits for underground storage tanks (USTs) are required – these might involve separate review by a state environmental department to ensure leak prevention, monitoring systems, and secondary containment are in place. Additionally, many air quality districts require permits for vapor recovery at gas pumps.

    • DOT/Right-of-Way Permits: If your project requires work in a public right-of-way (road widening, new driveway cuts, utility connections under a street), you will need permits from the city or state DOT. These often have their own review process and lead time. Coordinate the road improvement plans with the agency early. For example, adding a driveway on a state highway may need a highway occupancy permit and the design must meet state standards distinct from local ones.

    • Utility Will-Serve and Permits: Ensure will-serve letters from utility providers are secured (water, sewer, electric). Some utilities require their own design approval of extensions or service connections. For instance, the water authority might need to approve the water line layout and meter sizing before they sign off. If capacity upgrades are needed (like a bigger water main), a development agreement on cost-sharing might be needed.

    • Building Permit (for vertical construction): While site plan approval is a major milestone, remember that each building will need a building permit. Often, building construction drawings are submitted in parallel or after site plan approval. Building departments check structural, life safety, electrical, plumbing, mechanical plans per building code. This is typically separate from the site plan review, but the two can overlap. For a smooth process, ensure any site-related building code items have been considered – for example, fire apparatus access (site issue) ties into whether a building needs sprinklers (building code issue). If your site plan assumptions (like not needing a second fire access because building has sprinklers) are part of your strategy, confirm the building officials agree. Also, some municipalities won’t issue a building permit until the site plan or development plan is approved, so plan scheduling accordingly.

  • Navigating Bureaucracy and Keeping Timeline: Permitting can be unpredictable, but there are ways to keep it on track:

    • Follow Up Frequently: Don’t just submit and wait. Politely check on review status if you’re past the expected timeline. Sometimes files get stuck or staff is waiting on something – a check-in can prompt action or at least give insight.

    • Build Relationships: If possible, have consistent points of contact (e.g., a project manager in the planning department) and maintain a professional rapport. Attending any public meetings or open houses about development can also help network with officials. A bit of goodwill can translate to your application not languishing unnecessarily.

    • Address Issues Head-On: If a particular aspect becomes controversial (say, neighbors fight the gas station use), consider voluntary concessions to ease concerns – perhaps enhanced landscaping, limited hours for a car wash, etc. Demonstrating flexibility can turn opponents to neutral or win support from officials who want to see compromise.

    • Leverage Expert Help: A knowledgeable land use attorney or permit expediter can be very helpful for tricky approvals. They understand the process, know the code nuances, and can interface with the city on complex issues. For large multifamily or high-stakes projects, having legal counsel manage entitlement strategy is often worth the cost.

    • Keep Investors/Lenders in Loop: Delays in permitting can affect financing and closing dates. Regularly update your partners on the timeline and any emerging risks. If delays occur, a documented explanation (e.g. “City staff requested a complete traffic signal design, adding 6 weeks”) shows you’re actively managing the process.

  • Approval to Permit Transition: Once you finally receive site plan approval (congratulations!), make sure to fulfill any remaining “pre-permit” conditions. This may include posting bond or surety for public improvements, paying impact fees or permit fees, and obtaining any sign-offs from external agencies. Many jurisdictions require an approved site plan to be signed and sometimes recorded. After that, a site development permit or grading permit might be issued, allowing you to begin site work (grading, utilities) even if building permits for structures are still under review. Take advantage of that if possible to keep on schedule.


It’s worth noting a truth: “Permitted doesn’t mean done.” Even after securing the main approvals, additional minor permits or conditions precedent may exist. Always read the fine print on your approval documents to ensure all conditions are satisfied before moving forward.


Best Practices – Phase 5 (Permitting & Approvals):

  • Track the Timeline and Set Realistic Expectations: In your project schedule, build in adequate time for permitting – it often takes longer than hoped. As a rough guide from industry insight: a well-aligned project might achieve full entitlement in 6–12 months, typical cases 12–24 months, and challenging ones 24+ months. Communicate these realities to stakeholders. Avoid making promises of “we’ll be permitted in 3 months” unless you have certainty. It’s better to under-promise and over-deliver if you expedite it faster.

  • Organize Comment Responses Cleanly: When you get review comments, respond in a clear, organized way. Consider writing a response letter that lists each comment and your response/actions taken, and reference any plan sheet changes. This helps reviewers quickly verify that you addressed everything – speeding up their second review. Many jurisdictions appreciate a comment-response matrix; some even require it.

  • Hold Inter-Departmental Meetings if Needed: If reviews reveal conflicting requirements between departments (e.g., planning wants more landscaping which conflicts with utility dept.’s sewer line location), request a joint meeting with those reviewers to hash out a compromise. Getting everyone in the same room (or Zoom) can resolve stalemates faster than back-and-forth memos.

  • Public Relations: For contentious projects, invest in some PR. Simple things like a project website or hotline, community meetings, or informational mailers can educate the public and dispel rumors. Sometimes opposition is based on misconceptions (e.g., people think a gas station will leak toxins; you can share modern UST safety info). Winning community support or at least reducing opposition will ease the approval in hearings.

  • Document Approvals Thoroughly: Once approved, keep multiple copies of all approval letters, stamped plans, permits, etc., and distribute to your team. The construction manager will need to know the permit conditions (like allowable work hours, tree protection requirements, etc.), and lenders often require copies too. Also diarize any expiration dates – many site plan approvals expire after 1-2 years if you don’t start construction, so know your deadline or seek extensions if needed.

  • Gas Station Specific: Ensure compliance with all environmental conditions is meticulously planned. There might be requirements like testing of tanks and lines post-installation, groundwater monitoring wells if near sensitive areas, or an emergency response plan for spills. These often come in the permit or as state regulations. Plan to implement them and budget accordingly (for example, Stage II vapor recovery systems can add cost and maintenance).

  • Multifamily Specific: If your project had to provide community benefits (like a certain number of affordable units or improvements to a public park), memorialize these in agreements and make sure to integrate them in final plans. Failing to follow through on promised conditions can halt your later occupancy permits. Additionally, be prepared to address construction logistics during permitting if required – large multi-unit builds may need a construction management plan (where will contractors park, how will you stage materials, etc.) for approval in dense urban areas.


Phase 6: Pre-Construction – Final Design Development, Cost Estimating, and Contractor Bidding


After securing the necessary approvals, the project shifts from planning to the pre-construction phase. This is the bridge between paper and shovels in the ground. In pre-construction, the developer finalizes design details, locks in construction costs, and prepares the site and team for actual construction work. While some of these activities can overlap with late-stage permitting, it’s important that by the time you mobilize on site, you have addressed all critical design decisions and have your contractors lined up.


Key components of the pre-construction phase:

  • Final Design and Construction Documents: Ensure that all design documents are advanced to 100% construction-ready status. This may involve the architect and engineers producing full construction document (CD) sets for the building(s) – including structural drawings, detailed MEP plans, interior layouts, etc., which weren’t part of the site plan package. The civil engineer will finalize construction details for site utilities, pavement sections, stormwater facilities, and so on. During this stage, some further coordination tweaks may happen due to late-breaking permit conditions or value engineering decisions. It’s critical to incorporate any changes required by the permit approvals into the plans now (for example, if the city approval required a different tree species in landscaping, update the landscape plan in the CD set). Double-check that all building code requirements are addressed in the final plans – compliance with all local, state, and federal building standards (from structural safety to ADA accessibility) is not only legally required but also avoids costly corrections during construction. For instance, confirm fire-rated wall designs if buildings are close to property lines, verify that site lighting meets energy codes, and that stormwater plans meet the latest drainage manual criteria.

  • Value Engineering (VE): Often after initial contractor pricing or as a proactive step, the team will undertake value engineering to reduce costs without compromising key project goals. This could include substituting materials, simplifying design elements, or phasing certain improvements. For site work, VE might suggest using less expensive paving materials (asphalt vs. concrete), adjusting grading to minimize import/export of soil, or resizing stormwater facilities if analysis shows some conservatism. However, VE must be done carefully: ensure any design changes still comply with permits and codes. If, say, you decide to thin out landscaping for cost savings, you must still meet the minimum landscape requirements in your approval – or you’ll need to seek a minor modification from the city, which is an extra step. Ideally, involve the contractor and engineers jointly in VE sessions to balance cost and compliance.

  • Detailed Cost Estimating and Budget Finalization: With final plans, the contractor (or your cost estimator) will prepare a detailed bill of quantities and pricing for all aspects of the project. By pre-construction, you should convert any earlier budget assumptions into confirmed costs. This is when you’ll finalize the construction contract amount or the Guaranteed Maximum Price (GMP) if using that format. Scrutinize the cost estimate line by line. Pay attention to site development costs, as those can sometimes be underestimated – for example, earthwork volumes, utility connection fees, or environmental mitigation costs can be significant. For gas station projects, factor in the cost of specialized equipment (tanks, dispensers, canopies) and regulatory compliance (monitoring systems, fire suppression) which can be a large portion of the budget. For multifamily, check that costs for site amenities (pool, landscaping, parking structures) are accurately included. Update your financial pro forma with the final costs and ensure financing is in place to cover them, including a contingency for any unknowns.

  • Contractor Selection and Bidding: If not already done earlier, bid out the project to qualified contractors. There are a few approaches:

    • Competitive Bidding: You prepare bid packages (with plans, specs, and bid forms) and solicit bids from multiple general contractors. This can ensure a competitive price. Provide clear instructions, a bid deadline, and ideally hold a pre-bid meeting on-site so bidders can ask questions and inspect the site.

    • Negotiated Contract: You might select a contractor based on qualifications or an existing relationship and negotiate the price with them (often using open-book review of costs). This can be effective if speed is important or the contractor has special expertise (e.g. a contractor experienced in fuel station construction might be preferred even if not the absolute lowest bid, due to their knowledge of tank installation and compliance).

    • Construction Manager / GC already involved: Sometimes a construction manager was on board during design (CMAR approach), providing input and now finalizing their GMP.


    Whichever route, ensure the contractor (and their key subcontractors) have relevant experience. A gas station project should have a GC who has built fuel stations or at least similar retail with fuel components – check that they plan to use a certified petroleum installation subcontractor. A multifamily project might need a GC who understands tight construction sequencing for multi-unit buildings and has the workforce for a larger project. In bidding, require references and a portfolio of similar jobs.

    Review bids carefully for scope completeness. The lowest bid might miss some scope that becomes a change order later. It’s often wise to create a bid comparison sheet listing each major scope item and cost, to spot inconsistencies. If one bidder vastly underpriced the earthwork, did they misread the quantities? Clarify such anomalies with bidders to avoid future issues.

  • Construction Scheduling and Phasing Plan: Work with the chosen contractor to develop a detailed construction schedule. Identify the critical path and any long-lead items (for example, prefabricated steel canopies or specialized equipment might have long lead times – ordering those early is crucial). For multifamily, perhaps breaking the project into phases or sequences (grading, then foundations, then vertical construction, etc.) with target dates. For gas stations, sequencing might involve first installing underground infrastructure (tanks, utilities) then surface improvements. Also plan for any required road work scheduling with local authorities (they may restrict when you can disrupt traffic). If the jurisdiction requires a construction management plan (particularly in urban areas), prepare that now – showing where you’ll stage materials on site, how erosion control will be managed, construction entrance location, etc. Getting these logistics sorted out prevents chaos when equipment arrives.

  • Site Preparations: Before full construction, there may be site prep tasks:

    • Site Clearing and Demo: Arrange for demolition of any existing structures (after obtaining demo permits) and clearing of vegetation. Make sure any environmental requirements are met – e.g., if there are protected trees that must be saved, mark and fence them off before clearing. If the site has known contamination, coordinate the remediation work here – perhaps removing contaminated soil as part of initial grading (with proper disposal and documentation per environmental regs). For a fuel station on a previously contaminated site, this could involve removing old tanks or soil clean-up now, as part of preparing a clean slate.

    • Construction Entrance and Utilities Setup: Establish a stabilized construction entrance for vehicles to prevent tracking dirt onto roads. Also, bring in temporary utilities (water, power) or arrange generators if needed. Ensure erosion and sediment controls (silt fence, etc.) are installed per your permit before major earthwork – inspectors will check this.

    • Survey Staking: Have the surveyor (or contractor’s survey crew) stake out key points: property limits (so contractors don’t encroach), building footprint, grading elevations or clearing limits, centerlines of roads, etc. This guides the site work and helps avoid mistakes like grading beyond your site boundary.

    • Pre-construction Meeting: Many jurisdictions require a pre-construction meeting with inspectors and the project team after permits are issued and before work starts. This is an opportunity to clarify inspection procedures, communication protocols, and any special conditions during construction. Attend with your contractor and be prepared to take notes on anything the inspectors emphasize (like “call us 48 hours before pouring curbs” etc.).

  • Final Permits and Insurance: By the start of construction, ensure all final permits are in hand (building permit, site grading permit, environmental clearances, etc.). Also verify that all insurance is in place (builder’s risk, general liability, any required bonds). If your project required a performance bond or letter of credit for public improvements, make sure that’s been posted to the city.

  • Kick-Off Construction: With everything ready, you can issue the Notice to Proceed to your contractor to begin work on a certain date. From this point, construction management processes take over (which is beyond this guide’s primary scope but equally important to project success).


Best Practices – Phase 6 (Pre-Construction & Bidding):

  • Involve the Operations Perspective: If you or the end users will operate the facility (especially relevant for things like gas stations or apartments that you might manage), involve operations staff in final design review. They can catch practical issues – e.g., property managers might point out if dumpster enclosures aren’t accessible enough for pickups, or a gas station operator might notice you need an extra storage room for convenience store inventory. Tweaking now can improve long-term functionality.

  • Don’t Rush the Final Details: There’s often pressure to “hurry up and build” once permits are in hand, but resist cutting short the final prep. For instance, double-check submittals on critical equipment early. A mistake in ordering, say, the wrong fuel tank capacity or a transformer with insufficient voltage, can cause expensive delays mid-construction. Take the time now to get those details right.

  • Monitor Market Conditions: During pre-construction, keep an eye on construction market trends – material prices, labor conditions – especially if there’s a gap between design and construction. If asphalt prices are spiking, maybe lock in that subcontractor early or consider material alternatives. If labor is scarce, ensure your contractor has a solid plan for workforce (maybe they need to stagger trades differently).

  • Maintain Contingency: Even with thorough planning, unexpected issues can arise once ground is broken (unseen rock, archeological finds, etc.). Keep a contingency budget (often 5-10% of project cost) allocated for the construction phase. Your investors/financiers will be more comfortable knowing you have a buffer for surprises.

  • Plan Construction Safety and Compliance: The contractor will create a site-specific safety plan, but as developer, ensure that things like OSHA requirements and any special safety conditions (for example, if building near a roadway or in a populated area) are accounted for. For gas stations, safety is paramount given flammable fuel – confirm the contractor’s plans for safe tank installation, vapor handling, and coordination with fire authorities. For multifamily, ensure site safety for neighboring residents (secure fencing, controlled hours, etc.) as often projects are infill in communities.

  • Communicate with Neighbors and Authorities: Before construction starts, it can be beneficial to send a notice to neighbors that work is commencing, including contact info for concerns. A little goodwill here can prevent angry calls to city hall later. Also, maintain communication with any city inspectors or project manager – let them know the schedule of major activities (like “we plan to start blasting rock next month” or “road closures on X date for utility tie-in”). Keeping them in the loop fosters a cooperative relationship.

  • Post-Permit Adjustments: If any design changes happen during construction (due to field conditions or change orders), promptly communicate with the design professionals and the permitting authority. Many changes can be approved as field changes or minor amendments as long as you ask permission rather than forgiveness. For example, if you need to slightly relocate a catch basin due to unexpected underground obstructions, get the engineer to update the plan and submit it for approval if required. Unapproved deviations can cause issues at final inspection.

  • Commissioning and Testing Plans: Plan ahead for final steps like commissioning of systems (especially for fuel systems – they will require testing for leaks, sensor functionality, etc., and inspectors will witness these tests). For multifamily, plan for inspections for life safety (fire alarms, sprinklers) and arrange them in advance. Knowing the protocol to obtain a Certificate of Occupancy (CO) at project’s end is useful to map out now, so you’re not scrambling with paperwork after construction.


By following these pre-construction best practices, you set the stage for a smoother build process and reduce the likelihood of costly hiccups. A well-planned project will transition into construction ready for success, having navigated the long commercial site plan process from concept to groundbreaking.


Conclusion


Embarking on a commercial development in the U.S. is a complex journey – a true test of planning, coordination, and persistence. From the early zoning due diligence through surveying, design, permitting, and pre-construction, each step of the commercial site planning process has its challenges and its best practices. Developers and investors who approach each phase with thorough analysis and professional expertise greatly improve their project’s odds of success. Key takeaways include the importance of front-loading your efforts (to catch “deal killers” and design flaws early), actively engaging stakeholders (from city officials to neighbors) throughout, and maintaining flexibility to adapt the project in response to technical findings or community input. Whether it’s a gas station with underground fuel tanks or a multi-story apartment building, the fundamentals of site planning remain the same – understand your site, respect the regulations, assemble the right team, and plan diligently.


By using this guide as an evergreen roadmap, developers can navigate the site plan approval maze more efficiently and anticipate the needs at each stage. The result is not just a set of permits on paper, but a project positioned to be built on time, on budget, and in harmony with its environment and community. In the dynamic world of real estate development, knowledge and preparation are your best ground-up foundation. Here’s to your next successful commercial development, built on a solid site planning process from concept to keys-in-hand.


Sources:

  • HOVER Architecture - The Importance of a Pre-Application Meeting in Development, Aug 21, 2025

  • Henrico County, VA - Pre-Application Meeting for Plans of Development, Site Plans, and Subdivisions

  • City of Westminster, CO - Step 1 Pre-Application Review

  • NYC Department of City Planning - Preparing an Application

  • New York State Department of State - Site Plan Review

  •  U.S. EPA - Stormwater Discharges from Construction Activities

  • FHWA - Access Management (Driveways)

  • NFPA - NFPA 30A Standard (Motor Fuel Dispensing Facilities and Repair Garages)

  • U.S. HUD - HUD Multifamily Programs (includes 221(d)(4))


 
 
 
Architectural site plan and CAD drafting layout created by InnoWave Studio for U
innowave studio logo black.png
info@innowave-studio.com —
 Email monitored 24/7
Phone: +1 (510) 519-9005
Mon–Thu 7am–10pm • Fri 7am–3pm
PRACTICE AREAS
  • RV parks, RV resorts & RV storage
  • Multi-Family developments
  • Mixed-Use development
  • Hotels & Motels
  • Industrial & Warehouse
  • Urban development
  • Site plan
  • Visualisation
  • Feasibility study for Rv parks & RV resorts
Innovative site plans and
Architectural visualizations
Service Company
InnoWave Studio, LLC
8 The Green, Suite A, Dover, DE 19901
  • Facebook
  • Twitter
  • LinkedIn
  • Instagram

Copyright © 2024 Innowave Studio

bottom of page